← Back
Community center
Harlem Temple
540 LENOX AVENUE · BIN 1053901
💬 Discuss this project
1987Year Built
2Stories
P5Building Class
R7-2Zoning
32,892 sfGross Floor Area
2Units
LL97 Covered12 Open Violations ▸FDNY Report ↗
Community center · 19,984 sf lot · 1.65 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbing
Roof4p · 1 filing · 20 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
S. SCHWARTZ ENGINEERING707/12/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
PAUL FUSCO CONSULTING1403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
HYDRO MECHANICAL INCPlumbing407/08/2026
JORDAN, JOSEPHElectrical103/21/2026
J & Y ELECTRIC AND INTER*Electrical103/22/2026
VAN KLEECK, ADAMElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
METROPOLITAN MECHANICAL C2277406/22/2022
Building Lifecycle
All (71)Filed (7)Permit Issued (4)Signed Off (3)Violation (39)Inspection (6)Special Inspection (12)
10/30/2025
Violation issued (FDNY_ORDER, closed)
10/30/2025
Violation issued (FDNY_NOV, closed)
10/30/2025
Violation issued (FDNY_ORDER, closed)
08/21/2025
Violation issued (FDNY_ORDER, closed)
09/23/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
09/23/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/27/2024
Violation issued (FDNY_NOV, closed)
07/20/2023
Violation issued (FDNY_ORDER, closed)
06/30/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/30/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
09/27/2022
Signed off — Alteration
INSTALLATION OF BOILER EQUIPMENT AND ASSOCIATED PIPING AS PER PLANS SUBMITTED HEREWITH. NO CHANGE TO USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION
M00569528-S1
09/27/2022
Signed off — Alteration
INSTALLATION OF BOILER EQUIPMENT AND ASSOCIATED PIPING AS PER PLANS SUBMITTED HEREWITH. NO CHANGE TO USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION
M00569528-S2
09/27/2022
Signed off — Alteration
INSTALLATION OF BOILER EQUIPMENT AND ASSOCIATED PIPING AS PER PLANS SUBMITTED HEREWITH. NO CHANGE TO USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION
M00569528-I1
07/15/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
07/12/2022
Filed — Alteration
INSTALLATION OF BOILER EQUIPMENT AND ASSOCIATED PIPING AS PER PLANS SUBMITTED HEREWITH. NO CHANGE TO USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION
M00569528-P4
06/30/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
06/29/2022
Inspection — Pass-Final Boiler Equipment Inspection
Pass
View inspection ↗
06/29/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
06/24/2022
Special inspection requirement — Heating Systems
PATRICK MCDONALD
06/22/2022
Filed — Alteration
INSTALLATION OF BOILER EQUIPMENT AND ASSOCIATED PIPING AS PER PLANS SUBMITTED HEREWITH. NO CHANGE TO USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION
M00569528-P3
06/22/2022
Filed — Alteration
INSTALLATION OF BOILER EQUIPMENT AND ASSOCIATED PIPING AS PER PLANS SUBMITTED HEREWITH. NO CHANGE TO USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION
M00569528-P2
06/14/2022
Special inspection requirement — Heating Systems
PATRICK MCDONALD
06/09/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
06/01/2022
Permit issued — Boiler Equipment
M00569528-S2-BE
05/17/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/06/2022
Filed — Alteration
INSTALLATION OF BOILER EQUIPMENT AND ASSOCIATED PIPING AS PER PLANS SUBMITTED HEREWITH. NO CHANGE TO USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION
M00569528-S2
05/06/2022
Filed — Alteration
INSTALLATION OF BOILER EQUIPMENT AND ASSOCIATED PIPING AS PER PLANS SUBMITTED HEREWITH. NO CHANGE TO USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION
M00569528-P1
05/06/2022
Special inspection requirement — HVAC-R and service water heating equipment
PATRICK MCDONALD
05/06/2022
Special inspection requirement — Maintenance information
PATRICK MCDONALD
05/06/2022
Special inspection requirement — Heating Systems
PATRICK MCDONALD
05/06/2022
Special inspection requirement — HVAC-R and service water heating system controls
PATRICK MCDONALD
05/06/2022
Special inspection requirement — Permanent certificate
PATRICK MCDONALD
03/18/2022
Special inspection requirement — Heating Systems
PATRICK MCDONALD
03/18/2022
Special inspection requirement — HVAC-R and service water heating equipment
PATRICK MCDONALD
03/18/2022
Special inspection requirement — Permanent certificate
PATRICK MCDONALD
03/18/2022
Special inspection requirement — Maintenance information
PATRICK MCDONALD
03/18/2022
Special inspection requirement — HVAC-R and service water heating system controls
PATRICK MCDONALD
03/11/2022
Permit issued — Boiler Equipment
M00569528-I1-BE
03/10/2022
Permit issued — Plumbing
M00569528-S1-PL
11/16/2021
Permit issued — Plumbing
M00569528-S1-PL
11/15/2021
Filed — Alteration
INSTALLATION OF BOILER EQUIPMENT AND ASSOCIATED PIPING AS PER PLANS SUBMITTED HEREWITH. NO CHANGE TO USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION
M00569528-S1
10/06/2021
Filed — Alteration
INSTALLATION OF BOILER EQUIPMENT AND ASSOCIATED PIPING AS PER PLANS SUBMITTED HEREWITH. NO CHANGE TO USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION
M00569528-I1
04/29/2021
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
02/02/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
11/02/2020
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
08/02/2020
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
05/02/2020
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
02/02/2020
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/02/2019
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
08/02/2019
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
05/02/2019
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
10/03/2018
Violation issued (FDNY_ORDER, closed)
04/06/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
04/06/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
12/07/2016
Violation issued (FDNY_NOV, closed)
08/11/2016
Violation issued (FDNY_NOV, closed)
01/04/2016
Violation issued (FDNY_NOV, closed)
03/31/2014
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
04/07/2010
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
11/10/2009
Violation issued (ECB, closed)
Elevators
Latest 60 of 71 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWBoiler EquipmentSigned-offHYDRO MECHANICAL INC06/01/2022
DOB NOWBoiler EquipmentSigned-offHYDRO MECHANICAL INC03/11/2022
DOB NOWPlumbingSigned-offHYDRO MECHANICAL INC03/10/2022
DOB NOWPlumbingSigned-offHYDRO MECHANICAL INC11/16/2021
BISFPISSUEDFIRE COMMAND CO., INC.09/04/2008
BISEQISSUEDT.B.R. INC.09/30/1998
2 projects · most recent 12/29/2024
General Wiring
FiledStatusContractorScope
12/29/2024Permit IssuedJ & Y ELECTRIC AND INTER*General Wiring
08/20/2022CompleteJ & Y ELECTRIC AND INTER*General Wiring
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
07/15/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
06/30/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
06/29/2022Pass-Final Boiler Equipment InspectionPassView ↗
06/29/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
06/09/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/17/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 12
DateRequirementInspectorRole
06/24/2022Heating SystemsPATRICK MCDONALDspecial
06/14/2022Heating SystemsPATRICK MCDONALDspecial
05/06/2022HVAC-R and service water heating equipmentPATRICK MCDONALDenergy_progress
05/06/2022Maintenance informationPATRICK MCDONALDenergy_progress
05/06/2022Heating SystemsPATRICK MCDONALDspecial
05/06/2022HVAC-R and service water heating system controlsPATRICK MCDONALDenergy_progress
05/06/2022Permanent certificatePATRICK MCDONALDenergy_progress
03/18/2022Heating SystemsPATRICK MCDONALDspecial
03/18/2022HVAC-R and service water heating equipmentPATRICK MCDONALDenergy_progress
03/18/2022Permanent certificatePATRICK MCDONALDenergy_progress
03/18/2022Maintenance informationPATRICK MCDONALDenergy_progress
03/18/2022HVAC-R and service water heating system controlsPATRICK MCDONALDenergy_progress
▾Documents — 49 on file (BIS + DOB NOW)
▸Plans & Drawings7
▸DOB NOWPlans/Sketch7
09/02/2026M00569528-P4Request digital key ↗
09/02/2026M00569528-P3Request digital key ↗
09/02/2026M00569528-P2Request digital key ↗
Showing 3 of 7 on file for this type
▸Applications & Permits3
▸BISPLAN / WORK APPROVAL APPLICATION2
08/21/2008110314133Open ↗
08/21/2008110314133Open ↗
▸BISWORK PERMIT APPLICATION1
09/04/2008110314133Open ↗
▸Seals & Professional Certifications20
▸DOB NOWProgress Inspector Seal & Signature8
09/23/2026M00569528-I1Open ↗
09/23/2026M00569528-I1Open ↗
09/23/2026M00569528-I1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature7
08/13/2026M00569528-P3Open ↗
08/13/2026M00569528-S2Open ↗
08/13/2026M00569528-P1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/23/2026M00569528-I1Open ↗
09/23/2026M00569528-S2Open ↗
09/01/2026M00569528-P1Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
08/23/2008110314133Open ↗
▸Environmental & Asbestos8
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
08/13/2026M00569528-P3Open ↗
08/13/2026M00569528-I1Open ↗
08/13/2026M00569528-P1Open ↗
Showing 3 of 7 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
08/21/2008110314133Open ↗
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026M00569528-I1Open ↗
▸Approvals, Objections & Sign-offs8
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter7
08/13/2026M00569528-P2Open ↗
08/13/2026M00569528-S2Open ↗
08/13/2026M00569528-I1Open ↗
Showing 3 of 7 on file for this type
▸BISADMINISTRATIVE OBJECTIONS1
08/21/2008110314133Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
09/04/2008110314133Open ↗
08/21/2008110314133Open ↗