← Back
BuildNYC
Elevator cooperative
Rivercross
540 MAIN STREET · BIN 1084699
💬 Discuss this project
1975Year Built
20Stories
D4Building Class
R7-2Zoning
—Gross Floor Area
368Units
22 Active Violations ▸FISP: SWARMP
Elevator cooperative · Owner of record: Rivercross Tenants' · 6.98 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
Whole building & multi-floor projectsEnergy analysis and flood compliance calculationsUnder Construction1 filing
RoofExterior renovations multi-family buildingUnder Construction2 filings · 20 docs
Floor 21C+c Management2 filings · 20 docs
Floor 20
Floor 19
Floor 18
Floor 17
Floor 16
Floor 15
Floor 14
Floor 13
Floor 12Mechanical work1 filing · 4 docs
Floor 11
Floor 10
Floor 9
Floor 8
Floor 7
Floor 6
Floor 5Exterior renovations multi-family buildingUnder Construction1 filing · 20 docs
Floor 4Exterior renovations multi-family buildingUnder Construction1 filing · 20 docs
Floor 3Exterior renovations multi-family buildingUnder Construction1 filing · 20 docs
Floor 2Exterior renovations multi-family buildingUnder Construction2 filings · 20 docs
Floor 1Exterior renovations multi-family buildingUnder Construction2p · 5 filings · 20 docs
Site & exteriorOverhead protection via sidewalk shed6 filings · 17 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Roosevelt Landings Owner203/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
William Vitacco Associates1203/21/2026
Rigid Structural Design1103/21/2026
New York & Company1003/21/2026
AO Consulting and Drafting203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Skyline Scaffolding GroupScaffold1407/08/2026
GM EnterpriseGeneral Contractor804/09/2026
Jasa NYC GroupGeneral Contractor507/08/2026
Vik XS ServicesGeneral Contractor207/08/2026
National Mechanical Services PlumbingPlumbing207/08/2026
G.bassolino PlumbingPlumbing107/08/2026
Top Shelf ElectricElectrical103/21/2026
Plumbing P & HPlumbing107/08/2026
Alliance Elevator CompanyElectrical103/21/2026
Mje Mechanicalspecialty_contractor107/08/2026
George BassolinoPlumbing103/21/2026
4 Brothers & Sons FenceScaffold104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Domani Inspection Service843411/20/2025
AG Engineering8899107/22/2025
New York Engineering Associates851506/18/2024
Building Lifecycle
All (161)Filed (22)Permit Issued (29)Signed Off (12)Facade (FISP) (3)Violation (60)Inspection (5)Special Inspection (30)
07/21/2026
Signed off — Alteration
Installation of a temporary construction fence per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M01199292-I1
07/16/2026
Violation issued (ECB, open)
Elevators
07/06/2026
Violation issued (HPD, closed)
C
07/04/2026
Violation issued (HPD, closed)
B
06/24/2026
Signed off — Alteration
Exterior Renovations to existing Multi-Family building including overcladding with exterior insulation finish system (EIFS) on lower Level and Floors 1-5, Roof. No other work is proposed. There is no change to the proposed use, egress or occupancy
M00468985-S1
06/23/2026
Signed off — Alteration
Installation of a temporarily heavy-duty sidewalk shed per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M01267819-I1
06/23/2026
Signed off — Alteration
M01127115-I1
06/23/2026
Permit issued — Suspended Scaffold
M00468985-S1-SC
06/18/2026
Permit issued — Suspended Scaffold
M00468959-S2-SC
06/17/2026
Filed — Alteration
Suspended Scaffold Installation as per plans filed herewith. No change in use, egress or occupancy.
M00468959-S2
06/17/2026
Violation issued (HPD, open)
C
06/17/2026
Violation issued (HPD, closed)
C
06/08/2026
Signed off — Alteration
Suspended Scaffold Installation as per plans filed herewith. No change in use, egress or occupancy.
M00468959-S1
05/30/2026
Violation issued (ECB, closed)
Unknown
05/15/2026
Violation issued (HPD, open)
I
05/15/2026
Violation issued (HPD, closed)
I
05/15/2026
Violation issued (HPD, closed)
I
05/15/2026
Violation issued (HPD, closed)
I
05/14/2026
Permit issued — Protection and Mechanical Methods
M01127115-I1-PMM
05/12/2026
Violation issued (HPD, closed)
B
05/12/2026
Violation issued (HPD, closed)
B
05/12/2026
Violation issued (HPD, open)
B
05/12/2026
Violation issued (HPD, closed)
B
05/12/2026
Violation issued (HPD, closed)
C
05/12/2026
Violation issued (HPD, closed)
B
05/12/2026
Violation issued (HPD, closed)
B
05/12/2026
Violation issued (HPD, closed)
C
05/12/2026
Violation issued (HPD, closed)
C
05/12/2026
Violation issued (HPD, closed)
B
05/12/2026
Violation issued (HPD, closed)
B
05/12/2026
Violation issued (HPD, closed)
C
05/12/2026
Violation issued (HPD, closed)
C
05/12/2026
Violation issued (HPD, closed)
B
05/12/2026
Violation issued (HPD, closed)
B
05/12/2026
Violation issued (HPD, open)
B
05/12/2026
Violation issued (HPD, closed)
C
05/12/2026
Violation issued (HPD, open)
B
05/12/2026
Violation issued (HPD, closed)
B
05/12/2026
Violation issued (HPD, closed)
C
05/12/2026
Violation issued (HPD, closed)
B
05/12/2026
Violation issued (HPD, closed)
B
05/12/2026
Violation issued (HPD, closed)
B
05/12/2026
Violation issued (HPD, open)
C
04/30/2026
Violation issued (HPD, open)
A
04/23/2026
Signed off — Alteration
Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M01211231-I1
04/21/2026
Violation issued (HPD, open)
B
04/21/2026
Violation issued (HPD, open)
B
04/21/2026
Violation issued (HPD, closed)
C
04/21/2026
Violation issued (HPD, closed)
A
04/21/2026
Violation issued (HPD, open)
C
04/21/2026
Violation issued (HPD, open)
B
04/18/2026
Violation issued (HPD, open)
B
04/18/2026
Violation issued (HPD, closed)
B
04/03/2026
Violation issued (HPD, open)
C
04/03/2026
Violation issued (HPD, closed)
B
04/01/2026
Violation issued (HPD, closed)
C
04/01/2026
Violation issued (HPD, closed)
C
03/07/2026
Violation issued (HPD, open)
B
03/07/2026
Violation issued (HPD, closed)
C
02/19/2026
Permit issued — General Construction
M01257896-I1-GC
Latest 60 of 161 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSuspended ScaffoldSigned-offCristina Michaels Cons MN06/23/2026
DOB NOWSuspended ScaffoldPermit IssuedCristina Michaels Cons MN06/18/2026
DOB NOWProtection and Mechanical MethodsSigned-offSkyline Scaffolding Group05/14/2026
DOB NOWGeneral ConstructionPermit IssuedGM Enterprise02/19/2026
DOB NOWGeneral ConstructionPermit IssuedJasa NYC Group11/13/2025
DOB NOWGeneral ConstructionPermit IssuedJasa NYC Group11/13/2025
DOB NOWProtection and Mechanical MethodsSigned-offSkyline Scaffolding Group10/15/2025
DOB NOWGeneral ConstructionPermit IssuedGM Enterprise08/14/2025
DOB NOWSidewalk ShedSigned-offSkyline Scaffolding Group08/08/2025
DOB NOWSuspended ScaffoldSigned-offCristina Michaels Cons MN07/09/2025
DOB NOWConstruction FenceSigned-off4 Brothers Sons Fence05/06/2025
DOB NOWSupported ScaffoldSigned-offSkyline Scaffolding Group05/01/2025
DOB NOWGeneral ConstructionPermit IssuedJasa NYC Group03/24/2025
DOB NOWGeneral ConstructionPermit IssuedJasa NYC Group03/24/2025
DOB NOWSuspended ScaffoldSigned-offCristina Michaels Cons MN03/07/2025
DOB NOWProtection and Mechanical MethodsSigned-offSkyline Scaffolding Group10/18/2024
DOB NOWProtection and Mechanical MethodsSigned-offSkyline Scaffolding Group10/17/2024
DOB NOWSuspended ScaffoldSigned-offVik XS Services06/18/2024
DOB NOWGeneral ConstructionPermit IssuedVik XS Services06/14/2024
DOB NOWPlumbingSigned-offG.bassolino Plumbing06/11/2024
DOB NOWProtection and Mechanical MethodsSigned-offSkyline Scaffolding Group05/13/2024
DOB NOWPlumbingSigned-offNational Mechanical Services Plumbing04/30/2024
DOB NOWGeneral ConstructionPermit IssuedVik XS Services03/29/2024
DOB NOWProtection and Mechanical MethodsSigned-offSkyline Scaffolding Group09/13/2023
DOB NOWPlumbingSigned-offNational Mechanical Services Plumbing05/30/2023
DOB NOWGeneral ConstructionSigned-offGM Enterprise01/13/2022
DOB NOWMechanical SystemsPermit IssuedGM Enterprise01/07/2022
DOB NOWMechanical SystemsPermit IssuedMje Mechanical10/14/2021
DOB NOWPlumbingSigned-offPlumbing P & H08/09/2021
BISEQISSUEDSteel Systems07/07/2016
BISEQISSUEDSteel Systems08/10/2015
BISEQISSUEDSteel Systems07/08/2015
BISEQISSUEDRoma Scaffolding02/06/2014
BISEQISSUEDRoma Scaffolding02/06/2014
BISEQISSUEDRoma Scaffolding05/06/2013
BISEQISSUEDRoma Scaffolding05/06/2013
BISPLISSUEDWawel Plumbing and Heating04/30/2013
BISMHISSUEDEvco Mechanical04/15/2013
1 project · most recent 11/20/2025
Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
11/20/2025Permit IssuedGM EnterpriseHeating and Air Conditioning Systems, Ventilation Systems
Heat / Cool
Daikin FXAQ09PVJU 9,500 BTU · Vrf Indoor ×8
FXMQ72MVJU 6 tons · Vrf Indoor ×4
FXAQ07PVJU 7,500 BTU · Vrf Indoor ×2
FXAQ18PVJU 18,000 BTU · Vrf Indoor ×2
FXAQ24PVJU 24,000 BTU · Vrf Indoor ×2
RXYQ168TATJA 14 tons · Vrf Outdoor ×2
RXYQ72TATJA 6 tons · Vrf Outdoor ×2
Ventilation
Greenheck SQ-60-VG 100 CFM · Exhaust Fan ×2
4 projects · most recent 10/15/2024
General Wiring
FiledStatusContractorScope
10/15/2024CompleteTop Shelf Electric—
08/22/2023CompleteTop Shelf Electric—
10/12/2022CompleteP & Z ElectricGeneral Wiring
08/09/2019CompletePinpoint ElectricGeneral Wiring
2 projects · most recent 08/07/2025
Sidewalk Shed Fence
FiledStatusContractorScope
08/07/2025Signed-offSkyline Scaffolding GroupSidewalk Shed
05/05/2025Signed-off4 Brothers & Sons FenceFence
2 projects · most recent 06/17/2026
Suspended Scaffold Tenant Protection Plan 72 Hour
FiledStatusContractorScope
06/17/2026Permit IssuedCristina Michaels Cons MNSuspended Scaffold
07/22/2025Permit IssuedGM EnterpriseTenant Protection Plan 72 Hour
1 project · most recent 06/17/2026
Suspended Scaffold (SC)
FiledStatusContractorScope
06/17/2026Permit IssuedCristina Michaels Cons MNSuspended Scaffold (SC)
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
07/09/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
07/09/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/15/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
03/18/2022Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/13/2021Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 31
DateRequirementInspectorRole
12/29/2025HVAC-R and service water heating equipmentJOHN MCMONAGLEenergy_progress
12/29/2025Energy Code Compliance InspectionsJOHN MCMONAGLEprogress
12/29/2025FinalJOHN MCMONAGLEprogress
12/29/2025Mechanical SystemsJOHN MCMONAGLEspecial
12/29/2025HVAC-R and service water heating system controlsJOHN MCMONAGLEenergy_progress
07/22/2025Tenant Protection Plan ComplianceARIEL GOLSHANspecial
07/18/2025FinalNICHOLAS BRINENprogress
06/05/2025HVAC-R and service water heating equipmentJOHN MCMONAGLEenergy_progress
06/05/2025Mechanical SystemsJOHN MCMONAGLEspecial
06/05/2025Energy Code Compliance InspectionsJOHN MCMONAGLEprogress
06/05/2025FinalJOHN MCMONAGLEprogress
06/05/2025HVAC-R and service water heating system controlsJOHN MCMONAGLEenergy_progress
04/25/2024Tenant Protection Plan ComplianceLOUIS ARENAspecial
04/25/2024Energy Code Compliance InspectionsLOUIS ARENAprogress
10/25/2023Energy Code ComplianceJennifer Szeprogress
10/25/2023Insulation placement and R valuesJennifer Szeenergy_progress
10/25/2023FinalJennifer Szeprogress
10/25/2023Exterior Insulation and Finish Systems (EIFS)Jennifer Szespecial
10/13/2023Energy Code ComplianceJennifer Szeprogress
10/13/2023Insulation placement and R valuesJennifer Szeenergy_progress
10/13/2023FinalJennifer Szeprogress
10/13/2023Exterior Insulation and Finish Systems (EIFS)Jennifer Szespecial
05/12/2021Energy Code Compliance InspectionsJOHN MCMONAGLEprogress
05/12/2021Interior lighting powerJOHN MCMONAGLEenergy_progress
05/12/2021Lighting controlsJOHN MCMONAGLEenergy_progress
Latest 25 of 31.
▾Documents — 175 on file (BIS + DOB NOW)
▸Plans & Drawings22
▸DOB NOWPlans/Sketch15
09/03/2026M00468959-S2Request digital key ↗
09/03/2026M00468959-S1Request digital key ↗
08/29/2026M00932986-I1Request digital key ↗
Showing 3 of 15 on file for this type
▸DOB NOWPlans/Sketch - General Construction4
09/03/2026M00477209-I1Request digital key ↗
09/03/2026M00468959-I1Request digital key ↗
08/27/2026M00468985-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems2
08/20/2026M00477218-P1Request digital key ↗
08/20/2026M00477218-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing1
09/03/2026M00477227-I1Request digital key ↗
▸Applications & Permits16
▸BISWORK PERMIT APPLICATION9
07/13/2016140370480Open ↗
08/07/2015140387445Open ↗
07/06/2015140370480Open ↗
Showing 3 of 9 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION7
08/07/2015140387445Open ↗
07/06/2015140370480Open ↗
04/04/2014121555138Open ↗
Showing 3 of 7 on file for this type
▸Seals & Professional Certifications71
▸DOB NOWProgress Inspector Seal & Signature24
09/02/2026M01033643-P1Open ↗
09/01/2026M00477218-P1Open ↗
09/01/2026M00477218-P1Open ↗
Showing 3 of 24 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature22
09/03/2026M00477227-I1Open ↗
09/03/2026M00468959-S1Open ↗
09/03/2026M00468959-S2Open ↗
Showing 3 of 22 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature9
09/02/2026M01033643-P1Open ↗
09/01/2026M00477218-P1Open ↗
08/28/2026M01257896-I1Open ↗
Showing 3 of 9 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT4
08/07/2015140387445Open ↗
07/06/2015140370480Open ↗
05/03/2013140071785Open ↗
Showing 3 of 4 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION4
08/07/2015140387445Open ↗
07/06/2015140370480Open ↗
05/03/2013140071785Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY4
08/07/2015140387445Open ↗
07/06/2015140370480Open ↗
05/03/2013140071785Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION4
08/14/2017121555138Open ↗
01/30/2015121555138Open ↗
03/28/2013121555138Open ↗
Showing 3 of 4 on file for this type
▸Trade Schedules & Equipment5
▸BISSCHEDULE B - PLUMBING2
09/05/2013121555138Open ↗
03/28/2013121555138Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
04/04/2014121555138Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
03/28/2013121555138Open ↗
▸BISSELF-CERT PLUMBING NOTICE1
05/05/2014121555138Open ↗
▸Environmental & Asbestos14
▸DOB NOWDEP ACP-5: Asbestos Assessment Report9
09/03/2026M00468959-I1Open ↗
08/28/2026M00874371-P1Open ↗
08/28/2026M00874371-I1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form3
09/03/2026M00477227-I1Open ↗
08/13/2026M00477218-I1Open ↗
08/13/2026M00477209-I1Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
08/07/2015140387445Open ↗
03/28/2013121555138Open ↗
▸Energy Compliance2
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
07/06/2015140370480Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026M00477209-I1Open ↗
▸Inspections & Test Reports4
▸BISTECHNICAL REPORT: RESPONSIBILITY4
08/07/2015140387445Open ↗
07/06/2015140370480Open ↗
05/03/2013140071785Open ↗
Showing 3 of 4 on file for this type
▸Approvals, Objections & Sign-offs24
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter18
09/03/2026M00477227-I1Open ↗
08/28/2026M00874371-I1Open ↗
08/28/2026M00874371-P1Open ↗
Showing 3 of 18 on file for this type
▸BISLANDMARKS APPROVAL2
08/07/2015140387445Open ↗
07/06/2015140370480Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
01/30/2015121555138Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
03/28/2013121555138Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
07/13/2016140370480Open ↗
▸BISLETTERS - APPROVED FABRICATION CERTIFICATIONS1
03/28/2013121555138Open ↗
▸Cost, Insurance & Ownership3
▸BISCOST AFFIDAVIT3
01/30/2015121555138Open ↗
04/15/2013121555138Open ↗
03/28/2013121555138Open ↗
▸Filing & Intake Forms6
▸BISEFILING JOB APPLICATION COVER SHEET4
08/07/2015140387445Open ↗
07/06/2015140370480Open ↗
05/03/2013140071785Open ↗
Showing 3 of 4 on file for this type
▸BISADDITIONAL INFORMATION1
09/13/2013121555138Open ↗
▸BISEFILING COVER SHEET1
03/28/2013121555138Open ↗
▸Other Documents8
▸DOB NOWCalculations3
09/03/2026M00468959-S2Open ↗
08/13/2026M00468959-S1Open ↗
08/13/2026M00468985-S1Open ↗
▸DOB NOWManufacturer's Specifications3
09/03/2026M00468959-S2Open ↗
08/13/2026M00468959-S1Open ↗
08/13/2026M00468985-S1Open ↗
▸BISFEE EXEMPTION DOCUMENTATION2
08/07/2015140387445Open ↗
07/06/2015140370480Open ↗