💬 Discuss this project
2019Year Built
6Stories
M1Building Class
R6Zoning
33,280 sfGross Floor Area
31Units
LL97 Covered1 Active Violation 0 unresolved · 1 paperwork only ▸FDNY Report ↗
Church, synagogue, chapel · 5,760 sf lot · 5.78 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbingGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Floor 4Gerer Yeshiva/mesivta Bais Yisroel22p · 1 filing · 18 docs
Floor 3Gerer Yeshiva/mesivta Bais Yisroel22p · 1 filing · 18 docs
Floor 2Gerer Yeshiva/mesivta Bais Yisroel11p · 1 filing · 18 docs
Floor 1Gerer Yeshiva/mesivta Bais Yisroel13p · 2 filings · 18 docs
MezzanineGerer Yeshiva/mesivta Bais Yisroel10p · 1 filing · 18 docs
CellarGerer Yeshiva/mesivta Bais Yisroel10p · 1 filing · 18 docs
Sub-CellarGerer Yeshiva/mesivta Bais Yisroel10p · 1 filing · 18 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Ohr Torah907/08/2026
Gerer Yeshiva School103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
AL Ffred Architecture612/08/2023
David Silberman, P.E202/17/2020
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
XYZ Code Consulting603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Global Home ImprovementsGeneral Contractor503/22/2026
P.H. WorksPlumbing207/08/2026
Alfred MierzejewskiElectrical103/21/2026
Illuminous ElectricElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
M. International Engineering3129512/08/2023
Building Lifecycle
All (91)Filed (8)Permit Issued (2)Signed Off (1)Violation (41)Inspection (3)Objection (14)Special Inspection (22)
12/03/2025
Violation issued (FDNY_ORDER, closed)
12/03/2025
Violation issued (FDNY_ORDER, closed)
11/27/2024
Violation issued (FDNY_ORDER, closed)
12/26/2023
Signed off — Alteration CO
FILING FOR INTERIOR RENOVATION TO CONVERT THE EXISTING DORMITORIES ON THE 3RD AND 4TH FLOOR TO A SCHOOL COMMUNITY FACILITY.
B00807605-S1
12/20/2023
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
12/08/2023
Filed — Alteration CO
FILING FOR INTERIOR RENOVATION TO CONVERT THE EXISTING DORMITORIES ON THE 3RD AND 4TH FLOOR TO A SCHOOL COMMUNITY FACILITY.
B00807605-P4
11/30/2023
Special inspection requirement — Energy Code Compliance Inspections
NANIK MASSAND
11/30/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
NANIK MASSAND
11/15/2023
Violation issued (FDNY_NOV, closed)
11/15/2023
Violation issued (FDNY_NOV, closed)
11/08/2023
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
10/31/2023
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
09/20/2023
Filed — Alteration CO
FILING FOR INTERIOR RENOVATION TO CONVERT THE EXISTING DORMITORIES ON THE 3RD AND 4TH FLOOR TO A SCHOOL COMMUNITY FACILITY.
B00807605-P3
06/30/2023
Permit issued — Plumbing
B00807605-S1-PL
06/29/2023
Filed — Alteration CO
FILING FOR INTERIOR RENOVATION TO CONVERT THE EXISTING DORMITORIES ON THE 3RD AND 4TH FLOOR TO A SCHOOL COMMUNITY FACILITY.
B00807605-P2
06/29/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
NANIK MASSAND
06/29/2023
Special inspection requirement — Energy Code Compliance Inspections
NANIK MASSAND
06/06/2023
Permit issued — General Construction
B00807605-I1-GC
05/24/2023
Objection resolved — Addressed
05/24/2023
Objection resolved — Addressed
05/24/2023
Special inspection requirement — Interior lighting power
NANIK MASSAND
05/24/2023
Special inspection requirement — Fenestration and door U-factor and product ratings
NANIK MASSAND
05/24/2023
Special inspection requirement — Fenestration areas
NANIK MASSAND
05/24/2023
Special inspection requirement — Insulation placement and R values
NANIK MASSAND
05/24/2023
Special inspection requirement — Air barrier - visual inspection
NANIK MASSAND
05/24/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
NANIK MASSAND
05/24/2023
Special inspection requirement — Energy Code Compliance Inspections
NANIK MASSAND
05/24/2023
Special inspection requirement — Fire-Resistance Rated Construction
NANIK MASSAND
05/24/2023
Special inspection requirement — Fenestration air leakage
NANIK MASSAND
05/23/2023
Objection raised — Other
05/23/2023
Objection raised — Other
05/22/2023
Filed — Alteration CO
FILING FOR INTERIOR RENOVATION TO CONVERT THE EXISTING DORMITORIES ON THE 3RD AND 4TH FLOOR TO A SCHOOL COMMUNITY FACILITY.
B00807605-P1
05/19/2023
Special inspection requirement — Fire-Resistance Rated Construction
05/19/2023
Special inspection requirement — Fenestration and door U-factor and product ratings
05/19/2023
Special inspection requirement — Air barrier - visual inspection
05/19/2023
Special inspection requirement — Fenestration air leakage
05/19/2023
Special inspection requirement — Fenestration areas
05/19/2023
Special inspection requirement — Insulation placement and R values
05/19/2023
Special inspection requirement — Interior lighting power
05/19/2023
Special inspection requirement — Energy Code Compliance Inspections
05/19/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
04/03/2023
Filed — Alteration CO
FILING FOR INTERIOR RENOVATION TO CONVERT THE EXISTING DORMITORIES ON THE 3RD AND 4TH FLOOR TO A SCHOOL COMMUNITY FACILITY.
B00807605-S1
03/28/2023
Violation issued (FDNY_NOV, closed)
01/19/2023
Objection raised — Other
01/19/2023
Objection resolved — Addressed
01/19/2023
Objection raised — Other
01/19/2023
Objection resolved — Addressed
01/17/2023
Objection raised — Scope
01/17/2023
Objection resolved — Addressed
01/17/2023
Objection raised — Other
01/17/2023
Objection resolved — Addressed
01/17/2023
Objection raised — Other
01/17/2023
Objection resolved — Addressed
01/09/2023
Filed — Alteration CO
FILING FOR INTERIOR RENOVATION TO CONVERT THE EXISTING DORMITORIES ON THE 3RD AND 4TH FLOOR TO A SCHOOL COMMUNITY FACILITY.
B00807605-I1
09/16/2022
Violation issued (FDNY_ORDER, closed)
09/16/2022
Violation issued (FDNY_ORDER, closed)
07/06/2022
Violation issued (FDNY_NOV, closed)
04/26/2021
Violation issued (FDNY_NOV, closed)
02/17/2020
Filed — No Work
B00317118-I1
02/17/2020
Filed — No Work
B00316844-I1
Latest 60 of 91 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offP.H. Works06/30/2023
DOB NOWGeneral ConstructionPermit IssuedGlobal Home Improvements06/06/2023
BIS—ISSUEDTownhouse Builders03/08/2019
BISMHISSUEDAlef Construction05/04/2018
BISPLISSUEDNew York Standard Mechanical07/31/2001
BISPLISSUEDNew York Standard Mechanical07/31/2001
BISSPISSUEDNew York Standard Mechanical Co03/05/2001
BISPLISSUEDNew York Standard Mechanical03/05/2001
BISFPISSUEDIdeal Fire Control05/02/2000
1 project · most recent 12/08/2023
Water/Sanitary
FiledStatusContractorScope
12/08/2023Signed-offP.H. WorksWater/Sanitary
1 project · most recent 10/15/2020
FiledStatusContractorScope
10/15/2020CompleteStar Electrical Contractors—
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
12/20/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
11/08/2023Pass-Final CND-Occupancy InspectionPassView ↗
10/31/2023Fail-Final CND-Occupancy InspectionFailView ↗
▾Special Inspection Requirements (DOB NOW) — 22
DateRequirementInspectorRole
11/30/2023Energy Code Compliance InspectionsNANIK MASSANDprogress
11/30/2023Fire-Resistant Penetrations and JointsNANIK MASSANDspecial
06/29/2023Fire-Resistant Penetrations and JointsNANIK MASSANDspecial
06/29/2023Energy Code Compliance InspectionsNANIK MASSANDprogress
05/24/2023Interior lighting powerNANIK MASSANDenergy_progress
05/24/2023Fenestration and door U-factor and product ratingsNANIK MASSANDenergy_progress
05/24/2023Fenestration areasNANIK MASSANDenergy_progress
05/24/2023Insulation placement and R valuesNANIK MASSANDenergy_progress
05/24/2023Air barrier - visual inspectionNANIK MASSANDenergy_progress
05/24/2023Fire-Resistant Penetrations and JointsNANIK MASSANDspecial
05/24/2023Energy Code Compliance InspectionsNANIK MASSANDprogress
05/24/2023Fire-Resistance Rated ConstructionNANIK MASSANDprogress
05/24/2023Fenestration air leakageNANIK MASSANDenergy_progress
05/19/2023Fire-Resistance Rated Construction—progress
05/19/2023Fenestration and door U-factor and product ratings—energy_progress
05/19/2023Air barrier - visual inspection—energy_progress
05/19/2023Fenestration air leakage—energy_progress
05/19/2023Fenestration areas—energy_progress
05/19/2023Insulation placement and R values—energy_progress
05/19/2023Interior lighting power—energy_progress
05/19/2023Energy Code Compliance Inspections—progress
05/19/2023Fire-Resistant Penetrations and Joints—special
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Gerer Yeshiva/mesivta Bais YisroelEducationSub-cellar, Cellar, Floors 1–4, Mezzanine
Project B00807605 Alteration CO · Permit Entire · 01/09/2023
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 122 on file (BIS + DOB NOW)
▸Plans & Drawings8
▸DOB NOWPlans/Sketch6
08/27/2026B00807605-P2Request digital key ↗
08/27/2026B00807605-S1Request digital key ↗
08/27/2026B00807605-P3Request digital key ↗
Showing 3 of 6 on file for this type
▸DOB NOWPlans/Sketch - Place of Assembly2
09/02/2026B00316844-I1Request digital key ↗
09/02/2026B00317118-I1Request digital key ↗
▸Applications & Permits19
▸BISPLAN / WORK APPROVAL APPLICATION12
10/23/2020322052871Open ↗
10/16/2020322052871Open ↗
02/27/2020321938999Open ↗
Showing 3 of 12 on file for this type
▸BISWORK PERMIT APPLICATION2
03/11/2019322052871Open ↗
05/07/2018321748212Open ↗
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION2
05/28/2019322052871Open ↗
05/28/2019322052871Open ↗
▸BISREJECTED! PROVIDE APPLICATION FOR STREET NUMBER STAMPED BY TOPO1
11/18/2020322052871Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
04/01/2019321938999Open ↗
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
09/05/2019322052871Open ↗
▸Zoning, Tax Lot & Property Records2
▸BISVERIFY TAX LOT1
06/26/2020322052871Open ↗
▸BISZONING DIAGRAM1
06/04/2019322052871Open ↗
▸Seals & Professional Certifications22
▸DOB NOWDPL-1: Design Professional Seal & Signature8
08/27/2026B00807605-S1Open ↗
08/27/2026B00807605-I1Open ↗
08/27/2026B00807605-P4Open ↗
Showing 3 of 8 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION5
12/11/2018322052871Open ↗
07/20/2018321748212Open ↗
07/10/2018321748212Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
09/01/2026B00807605-P4Open ↗
08/30/2026B00807605-I1Open ↗
08/30/2026B00807605-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
09/01/2026B00807605-P4Open ↗
08/30/2026B00807605-I1Open ↗
08/24/2026B00807605-P2Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
05/04/2018321748212Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
05/07/2018321748212Open ↗
▸Trade Schedules & Equipment8
▸BISRPZ/DDCV TEST REPORT : GEN215B3
09/13/2013320771759Open ↗
09/13/2013320771759Open ↗
09/13/2013320771759Open ↗
▸BISEQUIPMENT USE APPLICATION/PERMIT2
07/19/2018321748212Open ↗
05/04/2018321748212Open ↗
▸BISEQUIPMENT USE PERMITS2
07/19/2018321748212Open ↗
05/04/2018321748212Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
12/11/2018322052871Open ↗
▸Safety & Tenant Protection4
▸DOB NOWStreet Tree Checklist2
08/13/2026B00807605-P1Open ↗
08/13/2026B00807605-I1Open ↗
▸BISSTREET TREE CHECKLIST1
12/11/2018322052871Open ↗
▸DOB NOWStreet Tree Sign Off1
08/13/2026B00807605-I1Open ↗
▸Environmental & Asbestos7
▸DOB NOWDEP ACP-5: Asbestos Assessment Report6
08/27/2026B00807605-P4Open ↗
08/27/2026B00807605-P3Open ↗
08/27/2026B00807605-P2Open ↗
Showing 3 of 6 on file for this type
▸BISASBESTOS: EXEMPTION (ASB4)1
05/04/2018321748212Open ↗
▸Energy Compliance1
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
12/11/2018322052871Open ↗
▸Approvals, Objections & Sign-offs23
▸BISSCHEDULE A - OCCUPANCY - USE8
02/14/2014320771759Open ↗
02/14/2014320771759Open ↗
02/14/2014320771759Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter8
08/13/2026B00807605-P3Open ↗
08/13/2026B00807605-S1Open ↗
08/13/2026B00807605-P4Open ↗
Showing 3 of 8 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST6
12/15/2020322052871Open ↗
11/18/2020322052871Open ↗
09/17/2020322052871Open ↗
Showing 3 of 6 on file for this type
▸BISBPP-8 - Request Items for Builders Pavement Plan Signoff1
06/26/2019321938999Open ↗
▸Cost, Insurance & Ownership3
▸BISCOST AFFIDAVIT3
11/02/2020322052871Open ↗
07/10/2018321748212Open ↗
05/07/2018321748212Open ↗
▸Filing & Intake Forms20
▸BISADDITIONAL INFORMATION10
11/02/2020322052871Open ↗
09/17/2020322052871Open ↗
07/07/2020322052871Open ↗
Showing 3 of 10 on file for this type
▸BISBOROUGH INTAKE FORM5
07/19/2019320771759Open ↗
05/28/2019322052871Open ↗
05/28/2019322052871Open ↗
Showing 3 of 5 on file for this type
▸BISEFILING COVER SHEET4
04/01/2019321938999Open ↗
12/11/2018322052871Open ↗
05/07/2018321748212Open ↗
Showing 3 of 4 on file for this type
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
04/01/2019321938999Open ↗
▸Other Documents5
▸DOB NOWProperty Ownership Certification2
08/15/2026B00807605-I1Open ↗
08/14/2026B00807605-P1Open ↗
▸BISPLOT DIAGRAM1
11/13/2020322052871Open ↗
▸BISPROVIDE PLOT DIAGRAM (PD1) & APPLICAITON FOR STREET # STAMPED BY TOPO. NOT IN THE VIRTUAL FOLDER (NEW BUILDING)1
11/18/2020322052871Open ↗
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
05/04/2018321748212Open ↗