| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/03/2021 | Complete | RIGHTWAY ELECTRICAL INC | General Wiring |
| 03/10/2021 | Complete | RIGHTWAY ELECTRICAL INC | — |
| 08/17/2020 | Complete | TOP SHELF ELECTRIC CORP | — |
| Owner | Filings | Most Recent |
|---|---|---|
| UNIVERSAL SYSTEMS | 4 | 07/08/2026 |
| 5417 9TH AVE LLC | 1 | 03/22/2026 |
| KW DEVELOPMENT CONTRACTIN | 4 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/21/2019 | $1.9M | — | — → — | $326/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| A & T ENGINEERING, P.C. | 10 | 06/24/2021 |
| ALBERTO ROMAN | 1 | 10/26/2020 |
| ASHRAF CORP | 1 | 08/20/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| EUROCELT EXPEDITING, INC | 2 | 03/21/2026 |
| JD DESIGN ASSOCIATES INC | 2 | 03/21/2026 |
| S Y CONSULTING VIOLATIONS | 2 | 03/21/2026 |
| AEGIS DESIGN BUILD | 2 | 03/21/2026 |
| A T | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| KW DEVELOPMENT CONTRACTIN | General Contractor | 9 | 07/08/2026 |
| QMB PLUMBING & HEATING INC | Plumbing | 4 | 07/08/2026 |
| ROBERT H LIN | Electrical | 3 | 03/21/2026 |
| QMB PLUMBING & HTG INC | Fire Protection | 1 | 07/08/2026 |
| A T ENGINEERING P C | General Contractor | 1 | 03/22/2026 |
| UNIVERSAL SYSTEMS INC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| A & T DESIGN GROUP LLC | 1088 | 9 | 06/24/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | KW DEVELOPMENT CONTRACTIN | 06/10/2021 |
| DOB NOW | Boiler Equipment | Signed-off | QMB PLUMBING & HEATING INC | 05/02/2021 |
| DOB NOW | Supported Scaffold | Signed-off | KW DEVELOPMENT CONTRACTIN | 12/17/2020 |
| DOB NOW | Construction Fence | Signed-off | KW DEVELOPMENT CONTRACTIN | 12/17/2020 |
| DOB NOW | Supported Scaffold | Signed-off | KW DEVELOPMENT CONTRACTIN | 10/27/2020 |
| DOB NOW | Plumbing | Signed-off | QMB PLUMBING & HTG INC | 10/19/2020 |
| DOB NOW | Sprinklers | Signed-off | QMB PLUMBING & HEATING INC | 10/19/2020 |
| DOB NOW | Structural | Signed-off | KW DEVELOPMENT CONTRACTIN | 09/09/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | UNIVERSAL SYSTEMS INC | 08/20/2020 |
| DOB NOW | Construction Fence | Signed-off | KW DEVELOPMENT CONTRACTIN | 07/16/2020 |
| BIS | — | ISSUED | KW DEVELOPMENT CONTRACTIN | 12/18/2020 |
| BIS | — | ISSUED | KW DEVELOPMENT CONTRACTIN | 07/16/2020 |
| BIS | — | ISSUED | KW DEVELOPMENT CONTRACTIN | 07/16/2020 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/21/2021 | HVAC and service water heating system controls | ROBERT LIN | energy_progress |
| 07/21/2021 | HVAC and service water heating equipment | ROBERT LIN | energy_progress |
| 07/21/2021 | Maintenance information | ROBERT LIN | energy_progress |
| 07/21/2021 | Energy Code Compliance Inspections | ROBERT LIN | progress |
| 07/21/2021 | Fire-Resistance Rated Construction | ROBERT LIN | progress |
| 07/21/2021 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | ROBERT LIN | special |
| 07/21/2021 | Post-installed Anchors | ROBERT LIN | special |
| 07/21/2021 | Sprinkler Systems | ROBERT LIN | special |
| 07/21/2021 | Fire-Resistant Penetrations and Joints | ROBERT LIN | special |
| 06/24/2021 | Fire-Resistant Penetrations and Joints | ROBERT LIN | special |
| 06/24/2021 | Post-installed Anchors | ROBERT LIN | special |
| 06/24/2021 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | ROBERT LIN | special |
| 06/24/2021 | Sprinkler Systems | ROBERT LIN | special |
| 06/24/2021 | Energy Code Compliance Inspections | ROBERT LIN | progress |
| 06/24/2021 | Fire-Resistance Rated Construction | ROBERT LIN | progress |
| 06/24/2021 | Maintenance information | ROBERT LIN | energy_progress |
| 06/24/2021 | HVAC and service water heating system controls | ROBERT LIN | energy_progress |
| 06/24/2021 | HVAC and service water heating equipment | ROBERT LIN | energy_progress |
| 06/24/2021 | Heating Systems | ROBERT LIN | special |
| 06/24/2021 | Fire-Resistant Penetrations and Joints | ROBERT LIN | special |
| 06/24/2021 | Chimneys and vents | ROBERT LIN | special |
| 06/24/2021 | Mechanical Systems | ROBERT LIN | special |
| 06/24/2021 | Final | ROBERT LIN | progress |
| 06/24/2021 | Energy Code Compliance Inspections | ROBERT LIN | progress |
| 06/24/2021 | Shutoff dampers | ROBERT LIN | energy_progress |