| Owner | Filings | Most Recent |
|---|---|---|
| AY CONSULTING | 35 | 07/08/2026 |
| CANNON CAPITAL GROUP | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/01/2024 | $950K | — | Private party → 542 PENNSYLVANIA LLC | $396/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| NOEL WONG, RA | 11 | 12/02/2024 |
| ADVANCED ENGINEERING & INSPECT. PLL | 2 | 04/09/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| EXPRESS FILING INC | 24 | 03/21/2026 |
| ADVANCED BUILDERS SERVICES | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JSB WORKS INC | General Contractor | 9 | 03/21/2026 |
| POWER DIRECT ELECTRIC INC | Electrical | 1 | 03/22/2026 |
| S & J INDUSTRIAL CORP | Fire Protection | 1 | 07/08/2026 |
| KISHAN PLUMBING INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 10 | 12/02/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Construction Fence | Signed-off | JSB WORKS INC | 06/06/2024 |
| DOB NOW | Sprinklers | Signed-off | S & J INDUSTRIAL CORP | 05/28/2024 |
| DOB NOW | Mechanical Systems | Signed-off | JSB WORKS INC | 04/15/2024 |
| DOB NOW | Plumbing | Signed-off | N AND S PLUMBING INC | 04/11/2024 |
| DOB NOW | General Construction | Permit Issued | JSB WORKS INC | 04/09/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 12/02/2024 | Signed-off | JSB WORKS INC | Heating and Air Conditioning Systems | Heat / Cool |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/02/2024 | Signed-off | S & J INDUSTRIAL CORP | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/02/2024 | Signed-off | KISHAN PLUMBING INC | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/13/2024 | Complete | POWER DIRECT ELECTRIC INC | General Wiring |
| 04/11/2024 | Complete | POWER DIRECT ELECTRIC INC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/02/2024 | Signed-off | JSB WORKS INC | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/06/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/22/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 08/15/2024 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 08/08/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/05/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/25/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/13/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/17/2024 | Structural Stability – Alterations of existing buildings | FAHAD FATEH | special |
| 12/17/2024 | Permanent certificate | FAHAD FATEH | energy_progress |
| 12/17/2024 | Fenestration air leakage | FAHAD FATEH | energy_progress |
| 12/17/2024 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 12/17/2024 | Maintenance information | FAHAD FATEH | energy_progress |
| 12/17/2024 | Metering | FAHAD FATEH | energy_progress |
| 12/17/2024 | Interior lighting power | FAHAD FATEH | energy_progress |
| 12/17/2024 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 12/17/2024 | Fenestration and door U-factor and product ratings | FAHAD FATEH | energy_progress |
| 12/17/2024 | Fenestration areas | FAHAD FATEH | energy_progress |
| 12/17/2024 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 12/17/2024 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 12/17/2024 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 12/17/2024 | Exterior Insulation and Finish Systems (EIFS) | FAHAD FATEH | special |
| 11/27/2024 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 11/27/2024 | Fenestration air leakage | FAHAD FATEH | energy_progress |
| 11/27/2024 | Permanent certificate | FAHAD FATEH | energy_progress |
| 11/27/2024 | Maintenance information | FAHAD FATEH | energy_progress |
| 11/27/2024 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 11/27/2024 | Metering | FAHAD FATEH | energy_progress |
| 11/27/2024 | Interior lighting power | FAHAD FATEH | energy_progress |
| 11/27/2024 | Fenestration and door U-factor and product ratings | FAHAD FATEH | energy_progress |
| 11/27/2024 | Fenestration areas | FAHAD FATEH | energy_progress |
| 11/27/2024 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 11/27/2024 | Exterior Insulation and Finish Systems (EIFS) | FAHAD FATEH | special |