| Owner | Filings | Most Recent |
|---|---|---|
| METRO CONTRACTING NY | 8 | 07/08/2026 |
| MR | 18 | 07/08/2026 |
| RENNON CONSTRUCTION | 5 | 03/22/2026 |
| T-MOBILE | 3 | 03/22/2026 |
| 544 PARK AVENUE REALTY | 52 | 03/22/2026 |
| MARBLE KNIT INC | 3 | 03/22/2026 |
| M.S KNITTING INC | 1 | 03/22/2026 |
| 544 PARK REALTY LLC | 7 | 03/21/2026 |
| VERIZON WIRELESS | 1 | 03/21/2026 |
| 544K PARK AVENUE REALTY | 3 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ENTHINK ENGINEERS LLC | 2 | 08/10/2022 |
| GRANT ENGINEERING CONSULTANTS, LLC | 1 | 12/20/2021 |
| JAMES H. FAHEY | 1 | 11/30/2021 |
| ASHRAF CORP | 1 | 10/12/2021 |
| FL&M ENGINEERING DESIGN &INSPECTION | 2 | 08/23/2021 |
| IKRA CONSULTING LLC | 1 | 03/04/2021 |
| TECTONIC ENGINEERING | 2 | 08/23/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| GREEN STUDIO | 4 | 03/21/2026 |
| AK CONSULTING SERVICES | 2 | 03/21/2026 |
| CONSTRUCTION PERMIT SERVICES | 2 | 03/21/2026 |
| Rigid Structural Design, LLC | 1 | 03/21/2026 |
| VERTICAL RIGGING | 2 | 03/21/2026 |
| CCM CONSULTING GROUP, INC. | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| FAST TRACK ELECTRIC CORP | General Contractor | 4 | 03/21/2026 |
| MANHATTAN D ENTERPRISES | General Contractor | 4 | 07/08/2026 |
| LIVOTI ENTERPRISE LLC | General Contractor | 3 | 03/21/2026 |
| METRO CONTRACTING NY, INC. | General Contractor | 3 | 07/08/2026 |
| WATCH HILL WIRELESS SOLU | General Contractor | 3 | 03/21/2026 |
| LEVEST ELECTRIC CORP | General Contractor | 2 | 03/21/2026 |
| CROSSLINK WIRELESS LLC | General Contractor | 2 | 03/21/2026 |
| RENNON CONSTRUCTION CORP | General Contractor | 2 | 03/21/2026 |
| SQUAN CONSTRUCTION SERVIC | General Contractor | 2 | 03/21/2026 |
| ROTH MOSHE | Electrical | 1 | 03/21/2026 |
| MOSHE ROTH | Electrical | 1 | 03/21/2026 |
| GREEN LIGHT ELECL & MECH | Electrical | 1 | 03/22/2026 |
| TIMOTHY COLEMAN | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| GRANT ENGINEERING CONSULT | 3512 | 1 | 12/20/2021 |
| STRUCTURAL CONSULTING SER | 1919 | 1 | 11/30/2021 |
| IKRA CONSULTING LLC | 7032 | 1 | 03/04/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Suspended Scaffold | Permit Issued | VERTICAL RIGGING INC | 02/11/2025 |
| DOB NOW | Antenna | Signed-off | FAST TRACK ELECTRIC | 10/05/2023 |
| DOB NOW | Antenna | Signed-off | FAST TRACK ELECTRIC | 06/08/2023 |
| DOB NOW | Supported Scaffold | Permit Issued | METRO CONTRACTING NY, INC. | 08/11/2022 |
| DOB NOW | Sidewalk Shed | Permit Issued | METRO CONTRACTING NY, INC. | 08/10/2022 |
| DOB NOW | Antenna | Signed-off | LIVOTI ENTERPRISE LLC | 06/30/2022 |
| DOB NOW | Antenna | Signed-off | SQUAN CONSTRUCTION SERVIC | 01/13/2022 |
| DOB NOW | Antenna | Signed-off | WATCH HILL WIRELESS SOLU | 12/23/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | MANHATTAN D ENTERPRISES | 10/13/2021 |
| DOB NOW | Supported Scaffold | Signed-off | MANHATTAN D ENTERPRISES | 03/24/2021 |
| DOB NOW | Supported Scaffold | Signed-off | RENNON CONSTRUCTION CORP | 03/04/2021 |
| DOB NOW | Antenna | Signed-off | STEADFAST DEVEL AND CONS | 11/22/2019 |
| DOB NOW | Antenna | Signed-off | LEVEST ELECTRIC CORP | 08/02/2018 |
| BIS | OT | ISSUED | DANIEL J. CONSTRUCTION IN | 06/22/2022 |
| BIS | OT | ISSUED | DANIEL J. CONSTRUCTION IN | 06/17/2021 |
| BIS | OT | ISSUED | DANIEL J. CONSTRUCTION IN | 01/11/2021 |
| BIS | EQ | ISSUED | SILVERCUP SCFFLDNG I LLC | 07/20/2020 |
| BIS | OT | ISSUED | DANIEL J. CONSTRUCTION IN | 07/06/2020 |
| BIS | EQ | ISSUED | SILVERCUP SCFFLDNG I LLC | 07/22/2019 |
| BIS | OT | ISSUED | BWT CONSTRUCTION CORP | 07/10/2019 |
| BIS | PL | ISSUED | SO PLUMBING & HEATING INC | 07/10/2019 |
| BIS | OT | ISSUED | CONTINENTAL WINDOW CLEANI | 07/11/2018 |
| BIS | EQ | ISSUED | SILVERCUP SCFFLDNG I LLC | 06/13/2018 |
| BIS | OT | ISSUED | SJ EMPIRE CORP | 01/31/2018 |
| BIS | OT | ISSUED | E&J ALL SEASONS CONSTRUCT | 08/29/2017 |
| BIS | EQ | ISSUED | SILVERCUP SCFFLDNG I LLC | 07/27/2017 |
| BIS | OT | ISSUED | COM-TECH CONSTRUCTION INC | 06/08/2016 |
| BIS | OT | ISSUED | E&J ALL SEASONS CONSTRUCT | 10/09/2015 |
| BIS | OT | ISSUED | E&J ALL SEASONS CONSTRUCT | 08/06/2015 |
| BIS | OT | ISSUED | TELCOM ENGINEERING GP INC | 07/07/2015 |
| BIS | OT | ISSUED | TELCOM ENGINEERING GP INC | 04/03/2015 |
| BIS | EQ | ISSUED | ATCO RESTORATION INC | 02/20/2014 |
| BIS | OT | ISSUED | MARCO POLO DESIGN CORP | 10/17/2013 |
| BIS | OT | ISSUED | ODYSSIA GLOBAL COMM. CORP | 02/28/2013 |
| BIS | EQ | ISSUED | ATCO RESTORATION INC | 08/17/2012 |
| BIS | OT | ISSUED | ODYSSIA GLOBAL COMM. CORP | 07/03/2012 |
| BIS | PL | ISSUED | S. WACHTEL PLBG & HTG INC | 06/22/2012 |
| BIS | BL | ISSUED | S. WACHTEL PLBG & HTG INC | 06/22/2012 |
| BIS | OT | ISSUED | COSTROTTA CONSTRUCT MG IN | 03/16/2012 |
| BIS | OT | ISSUED | COSTROTTA CONSTRUCT MG IN | 01/11/2012 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/18/2023 | Permit Issued | ASSOCIATED ELEC CONT OF N | General Wiring |
| 08/10/2022 | Permit Issued | RICHARD NEU | — |
| 02/20/2020 | Permit Issued | R.C.M. ELECTRIC CORP. | — |
| 02/07/2019 | Permit Issued | GREEN LIGHT ELECL & MECH | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/23/2021 | Final | FADY HABEEL | progress |