| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/15/2020 | $1.7M | — | Private party → Private party | $642/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| ALL CITY ENGINEERING, P.C. | 5 | 10/02/2023 |
| CELMER ARCHITECTURE PLLC | 3 | 09/28/2023 |
| NTD ENGINEERING CONSULTANT LLC | 2 | 09/28/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| COMMERCIAL CAPITAL USA | 20 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| KAPLAN HOME IMPROVEMENT C | General Contractor | 17 | 07/08/2026 |
| ORBIT PLBG & HTG INC | Plumbing | 8 | 07/08/2026 |
| DARIUSZ GRYGLEWSKI | Electrical | 1 | 03/21/2026 |
| EDWARD BYRNE | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SD TESTING & INSPECTION S | 7010 | 8 | 10/02/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | KAPLAN HOME IMPROVEMENT C | 03/28/2024 |
| DOB NOW | Plumbing | Permit Issued | ORBIT PLBG & HTG INC | 01/17/2024 |
| DOB NOW | Structural | Signed-off | KAPLAN HOME IMPROVEMENT C | 11/08/2023 |
| DOB NOW | General Construction | Signed-off | KAPLAN HOME IMPROVEMENT C | 11/08/2023 |
| DOB NOW | Mechanical Systems | Signed-off | KAPLAN HOME IMPROVEMENT C | 12/12/2022 |
| DOB NOW | Structural | Signed-off | KAPLAN HOME IMPROVEMENT C | 12/12/2022 |
| DOB NOW | Plumbing | Permit Issued | ORBIT PLBG & HTG INC | 12/10/2022 |
| DOB NOW | General Construction | Signed-off | KAPLAN HOME IMPROVEMENT C | 12/09/2022 |
| DOB NOW | General Construction | Signed-off | KAPLAN HOME IMPROVEMENT C | 10/13/2022 |
| BIS | OT | ISSUED | ACCORD POWER INC | 08/29/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 10/02/2023 | Signed-off | KAPLAN HOME IMPROVEMENT C | Heating and Air Conditioning Systems, Others, Ventilation Systems | Heat / Cool Mitsubishi Electric MXZ-SM48NAMHZ 54,000 BTU · Condensing Unit ×4 MXZ-SM36NAMHZ 36,000 BTU · Condensing Unit ×2 PUMY-SM60NAM-U1 60,000 BTU · Vrf Outdoor ×2 Ventilation Other Qmark N/A 6,826 BTU ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/02/2023 | Permit Issued | ORBIT PLBG & HTG INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/21/2023 | Complete | NEWGRANGE ELECTRIC, INC | — |
| 12/08/2022 | Permit Issued | FSM ELECTRICAL CORPORATIO | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/02/2023 | Signed-off | KAPLAN HOME IMPROVEMENT C | Steel, Concrete, Wood |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/02/2023 | Maintenance information | XIUCHENG LI | energy_progress |
| 10/02/2023 | Mechanical Systems | XIUCHENG LI | special |
| 10/02/2023 | Fire-Resistant Penetrations and Joints | XIUCHENG LI | special |
| 10/02/2023 | Energy Code Compliance Inspections | XIUCHENG LI | progress |
| 10/02/2023 | Final | XIUCHENG LI | progress |
| 10/02/2023 | HVAC-R and service water heating equipment | XIUCHENG LI | energy_progress |
| 10/02/2023 | Duct leakage testing, insulation and design | XIUCHENG LI | energy_progress |
| 10/02/2023 | Ventilation and air distribution system | XIUCHENG LI | energy_progress |
| 10/02/2023 | HVAC-R and service water heating system controls | XIUCHENG LI | energy_progress |
| 10/02/2023 | Permanent certificate | XIUCHENG LI | energy_progress |
| 10/02/2023 | HVAC-R and service water piping design and insulation | XIUCHENG LI | energy_progress |
| 09/28/2023 | Structural Stability – Alterations of existing buildings | XIUCHENG LI | special |
| 09/28/2023 | Concrete - Cast-In-Place | XIUCHENG LI | special |
| 09/28/2023 | Fire-Resistant Penetrations and Joints | XIUCHENG LI | special |
| 09/28/2023 | Structural Stability – Alterations of existing buildings | XIUCHENG LI | special |
| 09/28/2023 | Final | XIUCHENG LI | progress |
| 09/28/2023 | Fire-Resistance Rated Construction | XIUCHENG LI | progress |
| 09/28/2023 | Energy Code Compliance Inspections | XIUCHENG LI | progress |
| 09/28/2023 | Fenestration areas | XIUCHENG LI | energy_progress |
| 09/28/2023 | Fenestration and door U-factor and product ratings | XIUCHENG LI | energy_progress |
| 09/28/2023 | Air barrier - visual inspection | XIUCHENG LI | energy_progress |
| 09/28/2023 | Insulation placement and R values | XIUCHENG LI | energy_progress |
| 09/28/2023 | Interior lighting power | XIUCHENG LI | energy_progress |
| 09/28/2023 | Fenestration air leakage | XIUCHENG LI | energy_progress |
| 09/28/2023 | Preliminary | XIUCHENG LI | progress |