| Owner | Filings | Most Recent |
|---|---|---|
| CITISCAPE CONSULTING LTD | 14 | 07/08/2026 |
| MOD CONSULTANTS | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| CITISCAPE CONSULTING LTD | 20 | 04/01/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| CITISCAPE CONSULTING LTD | 40 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MOD CONSULTANTS LLC | General Contractor | 9 | 07/08/2026 |
| VMC PLUMBING & HEATING IN | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| TRIANGLE INSPECTION & TES | 7495 | 17 | 04/01/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | MOD CONSULTANTS LLC | 01/23/2025 |
| DOB NOW | Mechanical Systems | Signed-off | MOD CONSULTANTS LLC | 12/05/2024 |
| DOB NOW | Plumbing | Signed-off | M. SPINELLI PLB & HTG INC | 07/09/2024 |
| DOB NOW | Construction Fence | Signed-off | MOD CONSULTANTS LLC | 04/15/2024 |
| DOB NOW | Support of Excavation | Signed-off | MOD CONSULTANTS LLC | 04/10/2024 |
| DOB NOW | Structural | Signed-off | MOD CONSULTANTS LLC | 04/10/2024 |
| DOB NOW | General Construction | Permit Issued | MOD CONSULTANTS LLC | 04/10/2024 |
| DOB NOW | Foundation | Signed-off | MOD CONSULTANTS LLC | 04/10/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 04/01/2025 | Signed-off | MOD CONSULTANTS LLC | Air Conditioning Systems | Cooling |
| 06/12/2023 | Signed-off | MOD CONSULTANTS LLC | Air Conditioning Systems | Cooling Cooper & Hunter CH-24LCDTU 24,000 BTU · Fan Coil Indoor ×12 CH-24LCU/O 24,000 BTU · Heat Pump Outdoor ×12 AHCH-18LCDTU 18,000 BTU · Fan Coil Indoor ×8 CH-36LCU/0 40,000 BTU · Condensing Unit ×4 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/12/2023 | — | — | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/01/2025 | Signed-off | VMC PLUMBING & HEATING IN | Plumbing-Sprinkler, Storm, Water/Sanitary |
| 06/12/2023 | — | — | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/18/2024 | Complete | RONEY ELECTRIC INC | General Wiring |
| 10/01/2024 | Complete | TRINCITY ELECTRIC, INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/01/2025 | Signed-off | MOD CONSULTANTS LLC | Steel, Masonry |
| 06/12/2023 | Signed-off | MOD CONSULTANTS LLC | Steel, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/12/2023 | Signed-off | MOD CONSULTANTS LLC | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/12/2025 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 02/11/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/18/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/05/2024 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 08/07/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/31/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/19/2024 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 07/19/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 07/19/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/08/2025 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | Rajasekhar Sakhamuri | special |
| 04/08/2025 | Excavations - Sheeting, Shoring, and Bracing | Rajasekhar Sakhamuri | special |
| 04/08/2025 | Subgrade Inspections | Rajasekhar Sakhamuri | special |
| 04/08/2025 | Exterior Insulation and Finish Systems (EIFS) | Rajasekhar Sakhamuri | special |
| 04/08/2025 | Masonry | Rajasekhar Sakhamuri | special |
| 04/08/2025 | Fire-Resistant Penetrations and Joints | Rajasekhar Sakhamuri | special |
| 04/08/2025 | Energy Code Compliance Inspections | Rajasekhar Sakhamuri | progress |
| 04/08/2025 | Fire-Resistance Rated Construction | Rajasekhar Sakhamuri | progress |
| 04/08/2025 | Fenestration air leakage | Rajasekhar Sakhamuri | energy_progress |
| 04/08/2025 | Metering | Rajasekhar Sakhamuri | energy_progress |
| 04/08/2025 | Fenestration and door U-factor and product ratings | Rajasekhar Sakhamuri | energy_progress |
| 04/08/2025 | Permanent certificate | Rajasekhar Sakhamuri | energy_progress |
| 04/08/2025 | Insulation placement and R values | Rajasekhar Sakhamuri | energy_progress |
| 04/08/2025 | Maintenance information | Rajasekhar Sakhamuri | energy_progress |
| 04/08/2025 | Fenestration areas | Rajasekhar Sakhamuri | energy_progress |
| 04/08/2025 | Protection of exposed foundation insulation | Rajasekhar Sakhamuri | energy_progress |
| 04/08/2025 | Air barrier - visual inspection | Rajasekhar Sakhamuri | energy_progress |
| 04/08/2025 | Electric vehicle service equipment requirements | Rajasekhar Sakhamuri | energy_progress |
| 04/08/2025 | Air barrier — testing | Rajasekhar Sakhamuri | energy_progress |
| 04/08/2025 | Interior lighting power | Rajasekhar Sakhamuri | energy_progress |
| 03/26/2025 | Excavations - Sheeting, Shoring, and Bracing | Rajasekhar Sakhamuri | special |
| 03/26/2025 | Exterior Insulation and Finish Systems (EIFS) | Rajasekhar Sakhamuri | special |
| 03/26/2025 | Fire-Resistant Penetrations and Joints | Rajasekhar Sakhamuri | special |
| 03/26/2025 | Masonry | Rajasekhar Sakhamuri | special |
| 03/26/2025 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | Rajasekhar Sakhamuri | special |