| Firm | Filings | Most Recent |
|---|---|---|
| FIRST HEC DESIGN INC. | 3 | 01/19/2024 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| STRUCTURE R US INC | General Contractor | 3 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| W CHAN ENGINEERING PC | 2881 | 3 | 01/19/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | STRUCTURE R US INC | 03/11/2023 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/09/2025 | Complete | GOODALL ELECTRIC CORP | 3 meters, 3 new_meters |
| 05/18/2023 | Complete | AL-LECTRIC ELECT'L CONTRG | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/02/2024 | Fire-Resistant Penetrations and Joints | KANG CHAN | special |
| 01/02/2024 | Energy Code Compliance Inspections | KANG CHAN | progress |
| 01/02/2024 | Air barrier - visual inspection | KANG CHAN | energy_progress |
| 01/02/2024 | Insulation placement and R values | KANG CHAN | energy_progress |
| 01/02/2024 | Fenestration air leakage | KANG CHAN | energy_progress |
| 01/02/2024 | Fenestration and door U-factor and product ratings | KANG CHAN | energy_progress |
| 01/02/2024 | Fenestration areas | KANG CHAN | energy_progress |
| 05/02/2023 | Fire-Resistant Penetrations and Joints | KANG CHAN | special |
| 05/02/2023 | Energy Code Compliance Inspections | KANG CHAN | progress |
| 05/02/2023 | Air barrier - visual inspection | KANG CHAN | energy_progress |
| 05/02/2023 | Fenestration areas | KANG CHAN | energy_progress |
| 05/02/2023 | Insulation placement and R values | KANG CHAN | energy_progress |
| 05/02/2023 | Fenestration air leakage | KANG CHAN | energy_progress |
| 05/02/2023 | Fenestration and door U-factor and product ratings | KANG CHAN | energy_progress |