| Owner | Filings | Most Recent |
|---|---|---|
| SPRINGFIELD NORSE REALTY LLC | 30 | 08/26/2026 |
| JJS BUILDERS | 3 | 07/08/2026 |
| CYPRESS NORSE REALTY | 5 | 03/22/2026 |
| MANUFACTURERS HANOVER TRUST | 2 | 03/21/2026 |
| NORSE REALTY | 7 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| IW ARCHITECTURE, PLLC | 1 | 08/21/2026 |
| HNY CONSULTING ENGINEERS LLC | 2 | 08/19/2026 |
| BART J. HALVERSON, P.E., LLC | 1 | 08/14/2026 |
| JAM ARCHITECTS, D.P.C. | 2 | 08/13/2026 |
| LEON SKVIRSKY PE | 8 | 10/06/2020 |
| GREEN DESIGN | 1 | 02/04/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| BUILDING BROTHERS | 16 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ACTIVE SIGNS | Scaffold | 8 | 07/08/2026 |
| PROMETHEAN BUILDERS LLC | General Contractor | 4 | 08/26/2026 |
| MNK ENTERPRISES LLC | General Contractor | 1 | 07/08/2026 |
| SOLUTION MECH CONTNG LLC | Plumbing | 1 | 08/26/2026 |
| MAUCERI SIGN SYSTEMS | Scaffold | 1 | 08/26/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CROSSCHECK INSPECTION SER | 544 | 4 | 08/19/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | SOLUTION MECH CONTNG LLC | 08/25/2026 |
| DOB NOW | Sign | Permit Issued | MAUCERI SIGN CO., INC | 08/25/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | PROMETHEAN BUILDERS LLC | 08/25/2026 |
| DOB NOW | General Construction | Permit Issued | PROMETHEAN BUILDERS LLC | 08/24/2026 |
| DOB NOW | Structural | Permit Issued | PROMETHEAN BUILDERS LLC | 08/24/2026 |
| DOB NOW | General Construction | Permit Issued | PROMETHEAN BUILDERS LLC | 06/15/2026 |
| DOB NOW | Sign | Signed-off | ACTIVE SIGNS INC | 10/21/2020 |
| DOB NOW | Sign | Signed-off | ACTIVE SIGNS INC | 10/20/2020 |
| DOB NOW | Sign | Signed-off | ACTIVE SIGNS INC | 10/20/2020 |
| DOB NOW | Sign | Signed-off | ACTIVE SIGNS INC | 10/20/2020 |
| DOB NOW | Sign | Signed-off | ACTIVE SIGNS INC | 10/20/2020 |
| DOB NOW | Sign | Signed-off | ACTIVE SIGNS INC | 10/20/2020 |
| DOB NOW | Sign | Signed-off | ACTIVE SIGNS INC | 10/20/2020 |
| DOB NOW | Sign | Signed-off | ACTIVE SIGNS INC | 10/20/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | MNK ENTERPRISES LLC | 02/04/2020 |
| BIS | MH | ISSUED | AERO MECHANICAL OF NEW YO | 05/11/2020 |
| BIS | MH | ISSUED | AERO MECHANICAL OF NEW YO | 06/27/2019 |
| BIS | OT | ISSUED | OCS BUILDERS GROUP LLC | 08/14/2012 |
| BIS | OT | ISSUED | OCS BUILDERS GROUP LLC | 02/03/2012 |
| BIS | EQ | ISSUED | CEPRINE CONSTRUCTION INC | 04/06/2010 |
| BIS | PL | ISSUED | MAINLINE PL | 05/01/1997 |
| BIS | SD | ISSUED | CAPITOL FIRE SPKL CO,INC | 04/30/1997 |
| BIS | SP | ISSUED | CAPITOL FIRE SPKL CO,INC | 04/30/1997 |
| BIS | — | ISSUED | INTERBORO SIGN & MAINTANANCE CO. | 03/31/1997 |
| BIS | — | ISSUED | INTERBORO SIGN & MAINTANANCE CO. | 03/31/1997 |
| BIS | — | ISSUED | INTERBORO SIGN & MAINTENANCE CO. | 03/31/1997 |
| BIS | — | ISSUED | INTERBORO SIGN & MAINTENANCE CO. | 03/31/1997 |
| BIS | — | ISSUED | INTERBORO SIGN & MAINTENANCE CO. | 03/31/1997 |
| BIS | — | ISSUED | INTERBORO SIGN & MAINTENANCE CO. | 03/31/1997 |
| BIS | — | RE-ISSUED | INTERBORO SIGN & MAINTANANCE CO. | 03/31/1997 |
| BIS | PL | ISSUED | DUO PLUMBING & HTG CORP. | 12/17/1996 |
| BIS | — | ISSUED | MATASSA CONST INC. | 12/06/1996 |
| BIS | EQ | ISSUED | MATTASSA CONSTRUCTION | 12/06/1996 |
| BIS | MH | ISSUED | LANE ASSOC | 03/12/1993 |
| BIS | — | ISSUED | SILVERESCENT SIGN CO INC. | 10/14/1992 |
| BIS | PL | ISSUED | M & S BUILDING SERVICES I | 02/28/1991 |
| BIS | BL | ISSUED | LANE ASSOCIATES | 02/06/1991 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/19/2026 | Permit Issued | PROMETHEAN BUILDERS LLC | Heating and Air Conditioning Systems, Refrigeration Systems, Ventilation Systems | Heat / Cool Trane TTA240 382,000 BTU · Condensing Unit ×2 YSK150 12 tons · Rooftop Unit ×2 TWA072 49,000 BTU · Condensing Unit ×1 YHK048 4 tons · Rooftop Unit ×1 Addison PRRH 300 D4 279,000 BTU · Doas ×1 Ventilation Mitsubishi Electric PEAD-A24 742 CFM · Vrf Indoor ×1 Refrigeration |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/19/2026 | — | — | 125 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/19/2026 | Permit Issued | SOLUTION MECH CONTNG LLC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/11/2026 | Permit Issued | PATRIOT ELECTRIC CORP | General Wiring |
| 08/26/2026 | Permit Issued | PATRIOT ELECTRIC CORP | — |
| 09/16/2025 | Complete | PATRIOT ELECTRIC CORP | General Wiring |
| 09/30/2022 | Complete | WILLDAN ELECTRICAL OF NY | General Wiring |
| 10/01/2020 | Permit Issued | RAINBOW ELECTRIC CO., INC | — |
| 10/01/2020 | Permit Issued | RAINBOW ELECTRIC CO., INC | — |
| 02/04/2020 | Permit Issued | RICHARD NEU | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/19/2026 | Permit Issued | PROMETHEAN BUILDERS LLC | Steel, Concrete, Masonry |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/30/2026 | Final | Israel Wertentheil | progress |
| 06/18/2026 | Structural Steel - Welding | EUGENE BIFULCO | special |
| 06/18/2026 | Post-installed Anchors | EUGENE BIFULCO | special |
| 06/18/2026 | Fire-Resistant Penetrations and Joints | EUGENE BIFULCO | special |
| 06/18/2026 | Concrete - Cast-In-Place | EUGENE BIFULCO | special |
| 06/18/2026 | Masonry | EUGENE BIFULCO | special |
| 06/18/2026 | Post-installed Anchors | EUGENE BIFULCO | special |
| 06/18/2026 | Sprayed fire-resistant materials | EUGENE BIFULCO | special |
| 06/18/2026 | Structural Cold-Formed Steel | EUGENE BIFULCO | special |
| 06/18/2026 | Structural Stability – Alterations of existing buildings | EUGENE BIFULCO | special |
| 06/18/2026 | Structural Steel - High Strength Bolting | EUGENE BIFULCO | special |
| 06/18/2026 | Structural Steel - Details | EUGENE BIFULCO | special |
| 06/11/2026 | Shutoff dampers | EUGENE BIFULCO | energy_progress |
| 06/11/2026 | Fire-Resistant Penetrations and Joints | EUGENE BIFULCO | special |
| 06/11/2026 | Sprayed fire-resistant materials | EUGENE BIFULCO | special |
| 06/11/2026 | Final | EUGENE BIFULCO | progress |
| 06/11/2026 | HVAC-R and service water piping design and insulation | EUGENE BIFULCO | energy_progress |
| 06/11/2026 | Lighting controls | EUGENE BIFULCO | energy_progress |
| 06/11/2026 | Maintenance information | EUGENE BIFULCO | energy_progress |
| 06/11/2026 | HVAC-R and service water heating equipment | EUGENE BIFULCO | energy_progress |
| 06/11/2026 | Post-installed Anchors | EUGENE BIFULCO | special |
| 06/11/2026 | Energy Code Compliance Inspections | EUGENE BIFULCO | progress |
| 06/11/2026 | Interior lighting power | EUGENE BIFULCO | energy_progress |
| 06/11/2026 | HVAC-R and service water heating system controls | EUGENE BIFULCO | energy_progress |
| 06/05/2026 | Final | EUGENE BIFULCO | progress |