| Owner | Filings | Most Recent |
|---|---|---|
| NYC School Construction Authority | 95 | 07/08/2026 |
| NYC Department of Education | 2 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Homerun Solar | 1 | 08/31/2026 |
| Nomad R&D | 2 | 08/25/2026 |
| NYC School Construction Authority | 13 | 10/01/2025 |
| Eme Consulting Engineering Group | 2 | 09/05/2023 |
| NYMS Consulting | 4 | 01/11/2023 |
| MSS Engineering | 6 | 12/23/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| NYC School Construction Authority | 15 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| KW Tech | General Contractor | 26 | 07/08/2026 |
| KW Tech | Scaffold | 15 | 07/08/2026 |
| Forsythe P&H | Plumbing | 5 | 07/08/2026 |
| Falcon Electrical Contracting | Electrical | 2 | 03/21/2026 |
| Hexagon Group | Scaffold | 2 | 08/27/2026 |
| Sunkeeper Solar Electric | specialty_contractor | 1 | 09/02/2026 |
| RPM Electric | Electrical | 1 | 03/21/2026 |
| Titan Electrical & Elev Contracting | Electrical | 1 | 03/21/2026 |
| Laser Electrical Contracting | Electrical | 1 | 03/22/2026 |
| Falcon Electrical Contracting | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Homerun Solar | 8772 | 1 | 08/31/2026 |
| 20/20 Inspections | 1471 | 21 | 10/01/2025 |
| JPC Logistics Dba JPCL EN | 351 | 2 | 09/05/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Permit Issued | Sunkeeper Solar Electric | 09/01/2026 |
| DOB NOW | Construction Fence | Permit Issued | Hexagon Group | 08/26/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | Hexagon Group | 08/21/2026 |
| DOB NOW | Plumbing | Permit Issued | Forsythe P&H | 07/01/2026 |
| DOB NOW | General Construction | Permit Issued | KW Tech | 08/27/2025 |
| DOB NOW | Plumbing | Permit Issued | Forsythe P&H | 07/28/2025 |
| DOB NOW | Boiler Equipment | Signed-off | Champion Combustion | 10/21/2024 |
| DOB NOW | General Construction | Permit Issued | KW Tech | 10/01/2024 |
| DOB NOW | Structural | Permit Issued | KW Tech | 10/01/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | KW Tech | 10/01/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | KW Tech | 09/23/2024 |
| DOB NOW | General Construction | Permit Issued | KW Tech | 09/19/2024 |
| DOB NOW | Construction Fence | Signed-off | KW Tech | 09/19/2024 |
| DOB NOW | Supported Scaffold | Signed-off | KW Tech | 09/03/2024 |
| DOB NOW | Mechanical Systems | Signed-off | KW Tech | 08/30/2024 |
| DOB NOW | Plumbing | Permit Issued | Forsythe P&H | 08/26/2024 |
| DOB NOW | Boiler Equipment | Signed-off | Champion Combustion | 10/24/2023 |
| DOB NOW | General Construction | Permit Issued | KW Tech | 10/05/2023 |
| DOB NOW | Structural | Permit Issued | KW Tech | 10/05/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | KW Tech | 10/05/2023 |
| DOB NOW | General Construction | Permit Issued | KW Tech | 09/22/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | KW Tech | 09/22/2023 |
| DOB NOW | Construction Fence | Signed-off | KW Tech | 09/22/2023 |
| DOB NOW | General Construction | Permit Issued | KW Tech | 09/22/2023 |
| DOB NOW | Structural | Permit Issued | KW Tech | 09/22/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | KW Tech | 09/21/2023 |
| DOB NOW | Plumbing | Permit Issued | Forsythe P&H | 09/20/2023 |
| DOB NOW | Construction Fence | Signed-off | KW Tech | 09/05/2023 |
| DOB NOW | Mechanical Systems | Signed-off | KW Tech | 08/31/2023 |
| DOB NOW | Supported Scaffold | Signed-off | KW Tech | 08/31/2023 |
| DOB NOW | Boiler Equipment | Signed-off | Champion Combustion | 10/20/2022 |
| DOB NOW | Plumbing | Permit Issued | Forsythe P&H | 10/20/2022 |
| DOB NOW | Structural | Permit Issued | KW Tech | 10/13/2022 |
| DOB NOW | General Construction | Permit Issued | KW Tech | 10/06/2022 |
| DOB NOW | General Construction | Permit Issued | KW Tech | 10/06/2022 |
| DOB NOW | Mechanical Systems | Permit Issued | KW Tech | 10/06/2022 |
| DOB NOW | Construction Fence | Signed-off | KW Tech | 10/05/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | KW Tech | 09/30/2022 |
| DOB NOW | Supported Scaffold | Signed-off | KW Tech | 09/28/2022 |
| DOB NOW | Mechanical Systems | Signed-off | KW Tech | 09/27/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 10/01/2025 | Permit Issued | KW Tech | Air Conditioning Systems, Associated Ducts and Piping, Heating Systems, Refrigeration Systems | Heating Burnham 4FHL-827-50 5,540 CFM · Boiler ×6 |
| 09/05/2023 | — | — | Heating and Air Conditioning Systems | Heat / Cool |
| 07/19/2021 | — | — | Air Conditioning Systems | Cooling |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/01/2025 | Permit Issued | Forsythe P&H | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/21/2026 | Permit Issued | Kanta Electric | General Wiring |
| 07/21/2026 | Permit Issued | Sunkeeper Solar Electric | — |
| 05/14/2026 | Complete | Gemini Electric Co | — |
| 07/17/2025 | Complete | Falcon Electrical Contracting | General Wiring |
| 06/05/2024 | Complete | Titan Electrical & Elev Contracting | — |
| 01/03/2024 | Complete | Gemini Electric Co | — |
| 12/06/2022 | Complete | Falcon Electrical Contracting | — |
| 10/19/2022 | Permit Issued | Robert Chimenti | 2 meters, 1 new_meters |
| 09/30/2022 | Complete | Falcon Electrical Contracting | — |
| 09/26/2022 | Complete | A.T.J. Electrical Co | General Wiring |
| 05/16/2022 | Complete | Charan Electrical Enterp's | — |
| 02/23/2022 | Complete | Charan Electrical Enterp's | — |
| 10/17/2019 | Complete | Laser Electrical Contracting | — |
| 02/07/2019 | Complete | Charan Electrical Enterp's | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/01/2025 | Permit Issued | Forsythe P&H | Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/31/2026 | Permit Issued | Sunkeeper Solar Electric | 293 panels, 117.26 kw, 7,325 roof_area_sqft |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/23/2022 | Signed-off | KW Tech | Scaffold |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/24/2026 | Fire-Resistant Penetrations and Joints | RAYMOND PANCHARI | special |
| 07/24/2026 | Air barrier - visual inspection | RAYMOND PANCHARI | energy_progress |
| 07/24/2026 | Final | RAYMOND PANCHARI | progress |
| 07/24/2026 | Energy Code Compliance Inspections | RAYMOND PANCHARI | progress |
| 07/24/2026 | Structural Stability – Alterations of existing buildings | RAYMOND PANCHARI | special |
| 09/26/2025 | Mechanical Systems | JACOB HAAS | special |
| 09/26/2025 | Chimneys and vents | JACOB HAAS | special |
| 09/26/2025 | Final | JACOB HAAS | progress |
| 09/26/2025 | Energy Code Compliance Inspections | JACOB HAAS | progress |
| 09/26/2025 | Post-installed Anchors | JACOB HAAS | special |
| 09/26/2025 | Fire-Resistant Penetrations and Joints | JACOB HAAS | special |
| 09/26/2025 | Shutoff dampers | JACOB HAAS | energy_progress |
| 09/26/2025 | Maintenance information | JACOB HAAS | energy_progress |
| 09/26/2025 | HVAC-R and service water piping design and insulation | JACOB HAAS | energy_progress |
| 09/26/2025 | Electrical motors and elevators | JACOB HAAS | energy_progress |
| 09/26/2025 | HVAC-R and service water heating system controls | JACOB HAAS | energy_progress |
| 09/26/2025 | HVAC-R and service water heating equipment | JACOB HAAS | energy_progress |
| 09/26/2025 | Fire-Resistance Rated Construction | JACOB HAAS | progress |
| 06/17/2025 | Post-installed Anchors | JACOB HAAS | special |
| 06/17/2025 | Fire-Resistant Penetrations and Joints | JACOB HAAS | special |
| 05/08/2025 | Fire-Resistant Penetrations and Joints | JACOB HAAS | special |
| 05/08/2025 | Post-installed Anchors | JACOB HAAS | special |
| 01/14/2025 | HVAC-R and service water heating equipment | JACOB HAAS | energy_progress |
| 01/14/2025 | HVAC-R and service water heating system controls | JACOB HAAS | energy_progress |
| 01/14/2025 | Post-installed Anchors | JACOB HAAS | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| P.S. M79 - Horan School | Education | Floors 1, 2 | Project M01446803 Project M00928151 Project M07995435 Project M07998134 Project M07998148 Project M07998158 Project M00556489 |
| School P.S. 79 | Education | Cellar, Floors 1–3 | Project M00633271 |