Parks / recreation facility
Columbus Park Pavilion
55 MULBERRY STREET · BIN 1079268
💬 Discuss this project
1935Year Built
1Stories
Q1Building Class
PARKZoning
3,183 sfGross Floor Area
2Units
0 Open ViolationsFDNY Report ↗
Parks / recreation facility · Owner of record: NYC DEPARTMENT OF PARKS AND RECREATION · 145,365 sf lot · 0.02 FAR built · Flood zone X
Locations of Work
Architecture
Roof1p · 1 filing · 15 docs
Floor 12p · 1 filing · 15 docs
Basement2p · 1 filing · 15 docs
1 job · most recent 02/20/2026
Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
02/20/2026——Heating and Air Conditioning Systems, Ventilation Systems
Heat / Cool
Mitsubishi Electric MODEL NTXWPH15B112AA 14,000 BTU · Fan Coil Indoor ×4
MODEL NTXMPH48A182BA 48,000 BTU · Vrf Indoor ×1
Ventilation
Renewaire RENEWAIRE HE 05IN 375 CFM · Ahu ×1
1 job · most recent 02/20/2026
Storm
FiledStatusContractorScope
02/20/2026——Storm
Building Lifecycle
All (28)Filed (3)Violation (2)Objection (14)Special Inspection (9)
09/08/2026
Objection resolved — Resolved
03/19/2026
Objection resolved — Addressed
03/17/2026
Objection raised — Other
03/12/2026
Objection resolved — Resolved
02/26/2026
Objection resolved — Resolved
02/23/2026
Objection raised — Energy
02/23/2026
Objection raised — Admin
02/23/2026
Objection raised — Other
02/20/2026
Filed — Alteration
INSTALLATION OF 3 NEW FLOOR DRAINS CONNECTED TO EXISTING STORM DRAIN SYSTEM.
M01308514-S2
02/05/2026
Filed — Alteration
INSTALLATION OF 3 NEW FLOOR DRAINS CONNECTED TO EXISTING STORM DRAIN SYSTEM.
M01308514-S1
01/26/2026
Special inspection requirement — Duct leakage testing, insulation and design
01/26/2026
Special inspection requirement — Shutoff dampers
01/26/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
01/26/2026
Special inspection requirement — Energy Code Compliance Inspections
01/26/2026
Special inspection requirement — HVAC-R and service water heating system controls
01/26/2026
Special inspection requirement — HVAC-R and service water heating equipment
01/26/2026
Special inspection requirement — Maintenance information
12/30/2025
Objection resolved — Addressed
12/30/2025
Objection resolved — Addressed
12/30/2025
Objection resolved — Addressed
12/22/2025
Special inspection requirement — Final
12/22/2025
Special inspection requirement — Mechanical Systems
11/12/2025
Objection raised — Fire_Protection
11/07/2025
Objection raised — Scope
11/07/2025
Objection raised — Scope
10/27/2025
Filed — Alteration
INSTALLATION OF 3 NEW FLOOR DRAINS CONNECTED TO EXISTING STORM DRAIN SYSTEM.
M01308514-I1
02/27/2013
Violation issued (FDNY_ORDER, closed)
10/17/2006
Violation issued (FDNY_ORDER, closed)
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NYC DEPT OF PARKS & RECREATION102/20/2026
DEPARTMENT OF PARKS AND RECREATION102/05/2026
NYC PARKS DEPT110/27/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
NYC DEPT OF PARKS & RECREATION603/21/2026
Nothing on file for this building.
▾Special Inspection Requirements (DOB NOW) — 9
DateRequirementInspectorRole
01/26/2026Duct leakage testing, insulation and design—energy_progress
01/26/2026Shutoff dampers—energy_progress
01/26/2026HVAC-R and service water piping design and insulation—energy_progress
01/26/2026Energy Code Compliance Inspections—progress
01/26/2026HVAC-R and service water heating system controls—energy_progress
01/26/2026HVAC-R and service water heating equipment—energy_progress
01/26/2026Maintenance information—energy_progress
12/22/2025Final—progress
12/22/2025Mechanical Systems—special
▾Documents — 15 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/15/2026M01308514-I1Request digital key ↗
08/15/2026M01308514-S2Request digital key ↗
08/15/2026M01308514-S1Request digital key ↗
▸Seals & Professional Certifications3
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/21/2026M01308514-S1Open ↗
08/21/2026M01308514-I1Open ↗
08/21/2026M01308514-S2Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/15/2026M01308514-I1Open ↗
08/15/2026M01308514-S2Open ↗
08/15/2026M01308514-S1Open ↗
▸Approvals, Objections & Sign-offs6
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter3
08/15/2026M01308514-I1Open ↗
08/15/2026M01308514-S2Open ↗
08/15/2026M01308514-S1Open ↗
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)3
08/13/2026M01308514-S1Open ↗
08/13/2026M01308514-I1Open ↗
08/13/2026M01308514-S2Open ↗