| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/28/2025 | Permit Issued | AMERICAN STANDARD P&H COR | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/01/2022 | Complete | JAM ELECTRICAL CORP | — |
| 03/01/2022 | Complete | JAM ELECTRICAL CORP | — |
| 12/06/2019 | Permit Issued | R. DONOVAN & SON ELECTRIC | General Wiring |
| 09/04/2019 | Complete | RAINBOW ELECTRIC CO., INC | — |
| 09/04/2019 | Complete | RAINBOW ELECTRIC CO., INC | — |
| 08/22/2019 | Complete | HV ELECTRIC CORP | General Wiring |
| 07/18/2019 | Permit Issued | R. DONOVAN & SON ELECTRIC | General Wiring |
| 04/30/2019 | Complete | AMPERE ELECL SERVICES COR | — |
| 04/30/2019 | Complete | AMPERE ELECL SERVICES COR | — |
| 04/18/2019 | Complete | RAINBOW ELECTRIC CO., INC | — |
| 03/06/2019 | Complete | INFINITY ELECTRIC, INC | General Wiring |
| 08/31/2018 | Complete | HV ELECTRIC CORP | General Wiring |
| Owner | Filings | Most Recent |
|---|---|---|
| ST GEORGE OUTLET DEVELOPMENT | 128 | 07/08/2026 |
| HAAGEN-DAZS | 6 | 07/08/2026 |
| MEMBER | 3 | 07/08/2026 |
| EMPIRE OUTLETS BUILDERS | 30 | 03/22/2026 |
| BFC PARTNERS | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| NEW AIR SOLUTION INC. | 1 | 02/28/2025 |
| ZHENG & ASSOCIATES LLC | 1 | 08/10/2024 |
| BRIAN ILL DEVELOPMENT LLC | 3 | 04/06/2021 |
| AMERILAND BROOK LLC | 2 | 01/29/2021 |
| MAGO ARCHITECTURE, PLLC | 1 | 10/28/2020 |
| JOSE L. PENA,P.E. | 2 | 07/11/2019 |
| HC ARCHITECT, PC | 2 | 04/05/2019 |
| HM LOKE CONSULTING ENGINEERING PC | 1 | 04/02/2019 |
| LEON SKVIRSKY PE | 1 | 04/02/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| LOUIS STRIAR | 4 | 03/21/2026 |
| LLOYD NOEL BUILDING CONSULTANT | 2 | 03/21/2026 |
| BUILDING BROTHERS | 2 | 03/21/2026 |
| HM LOKE CONSULTING ENGINEERING PC | 1 | 03/21/2026 |
| LAM ASSOCIATES CONSULTING | 6 | 03/21/2026 |
| JP EXPEDITE | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SUPERIOR PLUMBING & HEATING | Plumbing | 3 | 07/08/2026 |
| WALSH, LINDA | Electrical | 3 | 03/21/2026 |
| HIGH QUALITY CONSTRUCTION | General Contractor | 2 | 03/21/2026 |
| CAD SIGNS NYC | Scaffold | 2 | 07/08/2026 |
| ZAQ CONSTRUCTION INC | General Contractor | 2 | 03/21/2026 |
| SIGNSTAR NYC | Scaffold | 2 | 07/08/2026 |
| AMERICAN STANDARD P&H CORORP. | Plumbing | 1 | 06/28/2026 |
| CASE PLUMBING LLC | Fire Protection | 1 | 07/08/2026 |
| R. DONOVAN & SON ELECTRIC | Electrical | 1 | 03/22/2026 |
| ACTIVE SIGNS | Scaffold | 1 | 07/08/2026 |
| PAUL SIGNS | Scaffold | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| NEW AIR SOLUTION INC | 8418 | 1 | 02/28/2025 |
| ZHENG & ASSOCIATES LLC | 7330 | 1 | 08/10/2024 |
| BRIAN ILL DEVELOPMENT LLC | 1402 | 3 | 04/06/2021 |
| AMERILAND BROOK LLC | 1506 | 2 | 01/29/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | AMERICAN STANDARD P&H CORORP. | 03/05/2025 |
| DOB NOW | General Construction | Permit Issued | ZAQ CONSTRUCTION INC | 08/13/2024 |
| DOB NOW | Mechanical Systems | Signed-off | HIGH QUALITY CONSTRUCTION | 03/26/2021 |
| DOB NOW | Plumbing | Signed-off | SUPERIOR PLUMBING & HEATI | 11/24/2020 |
| DOB NOW | Sign | Signed-off | ACTIVE SIGNS INC | 11/09/2020 |
| DOB NOW | Sprinklers | Signed-off | S & L PLUMBING INC | 10/30/2020 |
| DOB NOW | Plumbing | Signed-off | SUPERIOR PLUMBING & HEATI | 09/30/2019 |
| DOB NOW | Plumbing | Signed-off | SUPERIOR PLUMBING & HEATI | 09/03/2019 |
| DOB NOW | Sign | Signed-off | SIGNSTAR NYC | 07/15/2019 |
| DOB NOW | Sign | Signed-off | SIGNSTAR NYC | 07/15/2019 |
| DOB NOW | Sign | Signed-off | PAUL SIGNS, INC | 04/09/2019 |
| DOB NOW | Sign | Signed-off | SIGNS CAD CORP | 04/08/2019 |
| DOB NOW | Sign | Signed-off | SIGNS CAD CORP | 04/08/2019 |
| DOB NOW | Supported Scaffold | Signed-off | 04/03/2019 | |
| BIS | SP | ISSUED | J. CAIAZZO PLBG & HTG CORP | 01/10/2024 |
| BIS | PL | ISSUED | DRILON PLBG & HTG INC | 12/30/2020 |
| BIS | OT | ISSUED | ZR WHITESTONE INC | 07/07/2020 |
| BIS | OT | ISSUED | STAR BUILDERS INC | 10/09/2019 |
| BIS | SP | ISSUED | SKH MECHANICAL CORP | 04/02/2019 |
| BIS | OT | ISSUED | EMPIRE OUTLET BUILDERS | 03/29/2019 |
| BIS | — | ISSUED | EMPIRE OUTLET BUILDERS | 03/29/2019 |
| BIS | PL | ISSUED | CROWN PLUMBING INC | 03/26/2019 |
| BIS | MH | ISSUED | BEACON CONSTRUCTION SERV | 03/22/2019 |
| BIS | OT | ISSUED | BEACON CONSTRUCTION SERV | 03/22/2019 |
| BIS | PL | ISSUED | DRILON PLBG & HTG INC | 03/05/2019 |
| BIS | MH | ISSUED | RIDGE CONSTRUCTION CORP | 02/27/2019 |
| BIS | OT | ISSUED | RIDGE CONSTRUCTION CORP | 02/27/2019 |
| BIS | PL | ISSUED | CASINO MECHANICAL CORP | 02/12/2019 |
| BIS | MH | ISSUED | RIDGE CONSTRUCTION CORP | 01/31/2019 |
| BIS | OT | ISSUED | RIDGE CONSTRUCTION CORP | 01/31/2019 |
| BIS | EQ | ISSUED | CORE SCAFFOLD SYSTEMS INC. | 01/09/2019 |
| BIS | OT | ISSUED | EMPIRE OUTLET BUILDERS | 01/07/2019 |
| BIS | — | ISSUED | EMPIRE OUTLET BUILDERS | 12/31/2018 |
| BIS | OT | ISSUED | EMPIRE OUTLET BUILDERS | 12/05/2018 |
| BIS | EQ | ISSUED | LYNBROOK GLASS & ARCHITEC | 11/17/2018 |
| BIS | MH | ISSUED | TECTONIC BUILDERS INC | 10/11/2018 |
| BIS | OT | ISSUED | TECTONIC BUILDERS INC | 10/11/2018 |
| BIS | OT | ISSUED | TECTONIC BUILDERS INC | 10/11/2018 |
| BIS | OT | ISSUED | MICHELLE KUO CORP | 10/02/2018 |
| BIS | MH | ISSUED | MICHELLE KUO CORP | 10/02/2018 |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/26/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/26/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 03/23/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/21/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 03/11/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/27/2025 | Fire-Resistant Penetrations and Joints | Tianchen Hu | special |
| 08/10/2024 | Fire-Resistant Penetrations and Joints | Jinfar Liu | special |
| 08/10/2024 | Final | Jinfar Liu | progress |
| 08/10/2024 | Interior lighting power | Jinfar Liu | energy_progress |
| 04/06/2021 | Mechanical Systems | BRIAN ILL | special |
| 04/06/2021 | Final | BRIAN ILL | progress |
| 04/06/2021 | HVAC and service water heating system controls | BRIAN ILL | energy_progress |
| 04/06/2021 | HVAC and service water heating equipment | BRIAN ILL | energy_progress |
| 03/31/2021 | HVAC and service water heating system controls | BRIAN ILL | energy_progress |
| 03/31/2021 | Final | BRIAN ILL | progress |
| 03/31/2021 | HVAC and service water heating equipment | BRIAN ILL | energy_progress |
| 03/31/2021 | Mechanical Systems | BRIAN ILL | special |
| 01/22/2021 | Fire-Resistance Rated Construction | BRIAN ILL | progress |
| 01/22/2021 | Sprinkler Systems | XIAOHONG ZHAO | special |
| 07/29/2020 | Final | Hannibal Newsom | progress |
| 08/27/2019 | HVAC insulation and sealing | BRIAN ILL | energy_progress |
| 08/09/2019 | Energy Code Compliance Inspections | BRIAN ILL | progress |
| 08/09/2019 | Fire-Resistant Penetrations and Joints | BRIAN ILL | special |
| 07/11/2019 | Final | Jose Pena | progress |
| 07/11/2019 | Final | Jose Pena | progress |
| 04/02/2019 | Final | Hackjong Choi | progress |