| Owner | Filings | Most Recent |
|---|---|---|
| LE CAPITAL NYC | 13 | 07/08/2026 |
| HPD | 3 | 07/08/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/01/2024 | $4.9M | — | AYE 55 HOLDINGS LLC → Private party | $1,541/sf building |
| 09/07/2022 | $1.9M | — | Private party → AYE 55 HOLDINGS LLC | $583/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| SQUARE ARCH, LLC | 2 | 10/29/2025 |
| THOMAS C. TUNG, P.E. | 8 | 06/24/2024 |
| TWIG CONSULTING ENGINEERS PC | 1 | 05/21/2024 |
| AK CONSULTING SERVICES, INC | 1 | 11/18/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| KAMTECH RESTORATION CORP | 4 | 03/21/2026 |
| WM ARCH | 18 | 03/21/2026 |
| AK CONSULTING SERVICES | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| J&J DESIGNS INC | General Contractor | 4 | 07/08/2026 |
| WCK ELECTRIC CORP. | Electrical | 2 | 03/22/2026 |
| INNOVATIVE CONSTRUCTION & | General Contractor | 1 | 07/08/2026 |
| KAMTECH RESTORATION CORP | General Contractor | 1 | 07/08/2026 |
| RRP PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SQ. ARCH, LLC | 4802 | 2 | 10/29/2025 |
| CL ENGINEERING P.C. | 6781 | 4 | 05/14/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | KAMTECH RESTORATION CORP | 07/21/2025 |
| DOB NOW | General Construction | Signed-off | J&J DESIGNS INC | 06/04/2024 |
| DOB NOW | Plumbing | Signed-off | RRP PLUMBING CORP | 06/20/2023 |
| DOB NOW | General Construction | Signed-off | J&J DESIGNS INC | 05/23/2023 |
| DOB NOW | Construction Fence | Signed-off | INNOVATIVE CONSTRUCTION & | 01/12/2023 |
| BIS | OT | ISSUED | J&J DESIGNS INC | 09/13/2023 |
| BIS | OT | ISSUED | J&J DESIGNS INC | 02/28/2023 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/29/2025 | Complete | BERGER QUALITY ELEC'L CON | — |
| 05/29/2025 | Cancelled | BERGER QUALITY ELEC'L CON | — |
| 04/05/2024 | Complete | WCK ELECTRIC CORP. | General Wiring |
| 07/20/2023 | Complete | NEW CENTURY ELEC'L CONTR | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/09/2024 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 05/24/2024 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 03/15/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/13/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 09/28/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 08/07/2023 | Pass-Final PL - Underground | Pass | View ↗ |
| 07/19/2023 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/10/2025 | Energy Code Compliance Inspections | Kaijin Liang | progress |
| 11/10/2025 | Air barrier - visual inspection | Kaijin Liang | energy_progress |
| 11/10/2025 | Fire-Resistant Penetrations and Joints | Kaijin Liang | special |
| 11/10/2025 | Final | Kaijin Liang | progress |
| 05/29/2024 | Energy Code Compliance Inspections | CALVIN TRAN | progress |
| 05/21/2024 | Fenestration areas | CALVIN TRAN | energy_progress |
| 05/21/2024 | Air barrier - visual inspection | CALVIN TRAN | energy_progress |
| 05/21/2024 | Fenestration air leakage | CALVIN TRAN | energy_progress |
| 05/21/2024 | Fenestration and door U-factor and product ratings | CALVIN TRAN | energy_progress |
| 05/21/2024 | Energy Code Compliance Inspections | CALVIN TRAN | progress |
| 05/21/2024 | Fire-Resistance Rated Construction | CALVIN TRAN | progress |
| 04/30/2024 | Final | CALVIN TRAN | progress |
| 04/30/2024 | Fire-Resistance Rated Construction | CALVIN TRAN | progress |
| 04/30/2024 | Structural Steel - High Strength Bolting | CHRISTIAN LOZADA | special |
| 04/30/2024 | Energy Code Compliance Inspections | CALVIN TRAN | progress |
| 04/30/2024 | Structural Steel - Welding | CHRISTIAN LOZADA | special |
| 04/30/2024 | Construction Operations Influencing Adjacent Structures | CHRISTIAN LOZADA | special |
| 04/30/2024 | Fire-Resistant Penetrations and Joints | CHRISTIAN LOZADA | special |
| 04/30/2024 | Structural Stability – Alterations of existing buildings | CHRISTIAN LOZADA | special |
| 04/30/2024 | Structural Steel - Details | CHRISTIAN LOZADA | special |
| 04/30/2024 | Interior lighting power | CALVIN TRAN | energy_progress |
| 04/30/2024 | HVAC-R and service water heating system controls | — | energy_progress |
| 04/30/2024 | HVAC-R and service water heating equipment | — | energy_progress |
| 04/30/2024 | Fenestration and door U-factor and product ratings | CALVIN TRAN | energy_progress |
| 04/30/2024 | Fenestration air leakage | CALVIN TRAN | energy_progress |