| Owner | Filings | Most Recent |
|---|---|---|
| 550 55TH STREET REALTY LLC | 14 | 03/22/2026 |
| Z J W CONSTRUCTION | 2 | 03/22/2026 |
| 550 55TH ST CORP | 3 | 03/22/2026 |
| 550 55 STREET CORP. | 2 | 03/22/2026 |
| 55O 55 ST CORP % MILAN FA | 1 | 03/22/2026 |
| MAG REALTY | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 06/25/2014 | $2.4M | — | OCELOT REALTY HOLDINGS LLC → 550 55TH STREET REALTY LLC | $209/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| CL ENGINEERING P.C. | 4 | 10/23/2023 |
| LEE ENGINEERING, P.C. | 2 | 02/15/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| LEE ENGINEERING P C | 4 | 03/21/2026 |
| EL CHOUM CONSULTING | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| STANTON CONSTRUCTION CORP | General Contractor | 6 | 07/08/2026 |
| MARIUSZ ZALEWSKI | Electrical | 3 | 03/21/2026 |
| PROSTO ELECTRIC CORP 005210 | General Contractor | 3 | 03/22/2026 |
| PROSTO ELECTRIC CORP | Electrical | 2 | 03/22/2026 |
| Z.J.W. CONSTRUCTION, INC | General Contractor | 2 | 07/08/2026 |
| ADVANCED PLUMBING MECH | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CL ENGINEERING P.C. | 6781 | 4 | 10/23/2023 |
| LEE ENGINEERING, P.C. | 2157 | 2 | 02/15/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | STANTON CONSTRUCTION CORP | 12/08/2023 |
| DOB NOW | Structural | Signed-off | STANTON CONSTRUCTION CORP | 12/08/2023 |
| DOB NOW | General Construction | Signed-off | STANTON CONSTRUCTION CORP | 11/03/2023 |
| DOB NOW | General Construction | Signed-off | STANTON CONSTRUCTION CORP | 10/16/2023 |
| DOB NOW | General Construction | Signed-off | Z.J.W. CONSTRUCTION, INC | 05/05/2023 |
| DOB NOW | Structural | Signed-off | Z.J.W. CONSTRUCTION, INC | 05/05/2023 |
| DOB NOW | Plumbing | Signed-off | ADVANCED PLUMBING MECH | 03/24/2020 |
| BIS | OT | ISSUED | NORTHEAST CONSTRUCTION/RE | 02/26/2021 |
| BIS | OT | ISSUED | NORTHEAST CONTRACTING GP | 03/19/2020 |
| BIS | OT | ISSUED | Z.J.W. CONSTRUCTION, INC | 06/13/2018 |
| BIS | PL | ISSUED | ADVANCED PLUMBING MECH | 06/13/2018 |
| BIS | PL | ISSUED | ADVANCED PLUMBING MECH | 07/28/2017 |
| BIS | OT | ISSUED | Z.J.W. CONSTRUCTION, INC | 07/28/2017 |
| BIS | PL | ISSUED | ADVANCED PLUMBING MECH | 11/30/2016 |
| BIS | OT | ISSUED | Z.J.W. CONSTRUCTION, INC | 11/30/2016 |
| BIS | OT | ISSUED | Z.J.W. CONSTRUCTION, INC | 02/02/2016 |
| BIS | PL | ISSUED | ADVANCED PLUMBING MECH | 02/02/2016 |
| BIS | PL | ISSUED | DYCKMAN PLBG AND HTG INC | 07/18/2014 |
| BIS | PL | ISSUED | AURORA P & H CONT INC | 10/18/2001 |
| BIS | BL | ISSUED | AURORA P & H CONT INC | 10/18/2001 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/10/2024 | Complete | PROSTO ELECTRIC CORP | General Wiring |
| 11/03/2023 | Complete | PROSTO ELECTRIC CORP | General Wiring |
| 06/27/2023 | Complete | PROSTO ELECTRIC CORP | Boiler Controls |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/25/2023 | Structural Stability – Alterations of existing buildings | CHRISTIAN LOZADA | special |
| 10/25/2023 | Final | CHRISTIAN LOZADA | progress |
| 10/23/2023 | Final | CHRISTIAN LOZADA | progress |
| 10/23/2023 | Structural Stability – Alterations of existing buildings | CHRISTIAN LOZADA | special |
| 10/25/2022 | Structural Stability – Alterations of existing buildings | CHRISTIAN LOZADA | special |
| 10/25/2022 | Fire-Resistant Penetrations and Joints | CHRISTIAN LOZADA | special |
| 10/25/2022 | Final | CHRISTIAN LOZADA | progress |
| 02/15/2022 | Energy Code Compliance Inspections | YEON LEE | progress |
| 02/15/2022 | Fire-Resistant Penetrations and Joints | YEON LEE | special |
| 12/16/2021 | Energy Code Compliance Inspections | YEON LEE | progress |
| 12/16/2021 | Fire-Resistant Penetrations and Joints | YEON LEE | special |