← Back
Office, 20+ stories, with or without commercial
550 7 AVENUE
MANHATTAN · BIN 1014501
💬 Discuss this project
1924Year Built
23Stories
O4Building Class
M1-9A/R12Zoning
225,981 sfGross Floor Area
30Units
LL97 Covered24 Open Violations ▸FISP: SAFEFDNY Report ↗
Office, 20+ stories, with or without commercial · Owner of record: 550 ADLER REALTY RL, LLC · 9,875 sf lot · 22.88 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionCivilGeneralOther
Permit Issued — active, not yet Signed-off
Roof3p · 2 filings · 20 docs
Bulkhead2p · 2 filings · 17 docs
Floor 259p · 1 filing · 20 docs
Floor 24
Floor 23
Floor 22
Floor 211p · 1 filing · 6 docs
Floor 2010p · 2 filings · 6 docs
Floor 191p · 1 filing · 8 docs
Floor 18Under Construction13p · 2 filings · 11 docs
Floor 17
Floor 16
Floor 15
Floor 149p · 4 filings · 20 docs
Floor 13
Floor 124p · 3 filings · 15 docs
Floor 113p · 3 filings · 18 docs
Floor 10
Floor 94p · 2 filings · 17 docs
Floor 84p · 2 filings · 17 docs
Floor 75p · 2 filings · 20 docs
Floor 6Under Construction2p · 2 filings · 20 docs
Floor 5Under Construction1p · 1 filing · 5 docs
Floor 4Under Construction12p · 3 filings · 20 docs
Floor 31p · 1 filing · 8 docs
Floor 210p · 4 filings · 20 docs
Floor 1
Basement2p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
ADLER GROUP35509/01/2026
654 MADISON AVE ASSCO5107/08/2026
NOVA503/22/2026
550 ADLER REALTY RL, LLC303/22/2026
550 ALDER REALTY RL LLC103/22/2026
OWNER OF 550 7 AVE103/22/2026
450 7 AVE ASSOCIATES103/22/2026
REALTY CO. ( ADLER)103/22/2026
THE ADLER GROUND INC103/22/2026
BIDERMANN USA INC203/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
KAZAM CONSULTANTS4003/21/2026
JAM CONSULTANTS, INC.2903/21/2026
RIZZO GROUP1403/21/2026
STUDIO DB LLC603/21/2026
DIRECT ACCESS EXPEDITING, INC.1003/21/2026
EA DESIGN GROUP2403/21/2026
AE DESIGN SOLUTION403/21/2026
ROCK ARCH ENG CORP203/21/2026
BOYD CONSULTING403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
INTERIOR BUILDING SERVICEGeneral Contractor2308/27/2026
NATIONAL MAINTENANCEScaffold2007/08/2026
WEST NEW YORK RESTORATION OF CTGeneral Contractor1107/08/2026
PREMIER SANITATION LLCGeneral Contractor1007/08/2026
NOVA CONSTRUCTION SERVICEGeneral Contractor903/21/2026
SPRING SCAFFOLDING LLCGeneral Contractor807/08/2026
GRUSHINSKY PIPNG & HTG INFire Protection707/08/2026
FULL CIRCLE PLUMBING CORP.Plumbing707/08/2026
JEFFREY VULPIS PLMBNG LLCPlumbing607/08/2026
TRITON CONSTRUCTION CO.,General Contractor407/08/2026
CONSTRUCTION BROOKLYN INCGeneral Contractor409/01/2026
ONE TEN GROUP INCGeneral Contractor407/08/2026
CALIK, MURATElectrical303/21/2026
ARIEL CONSULTANTS LLCGeneral Contractor303/21/2026
CORBETT, RICHARDElectrical303/21/2026
PLATINUM GENERAL SERVICESGeneral Contractor303/21/2026
CONTRACTING BY REJI INCElectrical303/21/2026
ALKLEM PLUMBING INCPlumbing307/08/2026
PFL MECHANICAL CORPPlumbing307/08/2026
ABE HIMELFARBElectrical203/21/2026
DEMAR MECHANICAL INCPlumbing208/26/2026
CHRISTOPHER HANDElectrical103/21/2026
JOHN CORBETTElectrical103/21/2026
COPPER PLUMBING INCPlumbing107/08/2026
ARIANA CONTRACTING INCFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
JACK GREEN ASSOCIATES4222104/14/2026
CHRISTIAN L. MARTOS ENGIN5965103/04/2026
STUDIO DB LLC7533302/25/2026
COLLECTIF ENGINEERING, PL7799202/25/2026
SPECIAL TESTING & CONSULT1688411/02/2023
CHEN ENGINEERING SERVICES1826211/30/2022
AK ENGINEERING PC678306/13/2022
ROBERT F. GERMAIN JR. PE5100605/11/2022
Building Lifecycle
All (300)Filed (71)Permit Issued (70)Signed Off (45)Facade (FISP) (12)Violation (24)Inspection (44)Objection (4)Special Inspection (30)
08/31/2026
Permit issued — Mechanical Systems
M01336377-S1-MS
08/26/2026
Permit issued — Mechanical Systems
M01341310-S1-MS
08/13/2026
Signed off — Alteration
Construction work related as shown herewith on drawings. No change in use, occupancy or egress.
M01386620-I1
06/03/2026
Permit issued — General Construction
M00652278-I1-GC
04/28/2026
Permit issued — General Construction
M01386620-I1-GC
04/24/2026
Permit issued — Sprinklers
M01341310-S2-EW-SP
04/21/2026
Filed — Alteration
Construction work related as shown herewith on drawings. No change in use, occupancy or egress.
M01386620-I1
04/14/2026
Filed — Alteration
Mechanical work elated to interior renovations as shown herewith on drawings. No change to use, egress, or occupancy.
M01341310-S1
04/14/2026
Filed — Alteration
Mechanical work elated to interior renovations as shown herewith on drawings. No change to use, egress, or occupancy.
M01341310-S2
03/05/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
03/04/2026
Filed — Alteration
Widening of existing exterior door opening at 24th floor set back penthouse level. No Change to use, egress or occupancy.
M01336377-S3
03/04/2026
Special inspection requirement — Fire-Resistance Rated Construction
DAMIAN ZUNINO
03/04/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
DAMIAN ZUNINO
03/04/2026
Special inspection requirement — Final
DAMIAN ZUNINO
03/02/2026
Signed off — Alteration
General construction related to interior partitions and installation of doors and frames as shown herewith on drawings. No change to use, egress, or occupancy.
M01294819-I1
03/02/2026
Signed off — Alteration
Office modifications to the 8th and 9th floors
M00623667-I1
02/25/2026
Filed — Alteration
Widening of existing exterior door opening at 24th floor set back penthouse level. No Change to use, egress or occupancy.
M01336377-S2
02/25/2026
Filed — Alteration
Widening of existing exterior door opening at 24th floor set back penthouse level. No Change to use, egress or occupancy.
M01336377-S1
02/24/2026
Filed — Alteration
Widening of existing exterior door opening at 24th floor set back penthouse level. No Change to use, egress or occupancy.
M01336377-P1
02/04/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
01/30/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
01/30/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
01/29/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
01/26/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
01/23/2026
Permit issued — General Construction
M01336377-I1-GC
01/23/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
01/22/2026
Special inspection requirement — Final
DAMIAN ZUNINO
01/22/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
DAMIAN ZUNINO
01/22/2026
Special inspection requirement — Fire-Resistance Rated Construction
DAMIAN ZUNINO
01/21/2026
Permit issued — Sprinklers
M01327407-I1-EW-SP
01/20/2026
Permit issued — Plumbing
M01327407-I1-PL
01/20/2026
Permit issued — Plumbing
M01341310-I1-PL
01/09/2026
Filed — Alteration
Additions/Modifications to existing mechanical system as per plans herewith. No change to use, egress, or occupancy.
M01122784-P1
01/09/2026
Filed — Alteration
Modifications to the existing plumbing and sprinkler systems on the 4th floor. No change to use, egress, or occupancy.
M01327407-I1
01/09/2026
Permit issued — General Construction
M01336377-I1-GC
01/08/2026
Filed — Alteration
Mechanical work elated to interior renovations as shown herewith on drawings. No change to use, egress, or occupancy.
M01341310-I1
01/08/2026
Special inspection requirement — Mechanical Systems
RAFAEL FIGUEROA
01/08/2026
Special inspection requirement — Final
RAFAEL FIGUEROA
01/05/2026
Filed — Alteration
Widening of existing exterior door opening at 24th floor set back penthouse level. No Change to use, egress or occupancy.
M01336377-I1
12/02/2025
Special inspection requirement — Mechanical Systems
JACK GREEN
12/02/2025
Special inspection requirement — Energy Code Compliance Inspections
JACK GREEN
12/02/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
JACK GREEN
12/02/2025
Special inspection requirement — Final
JACK GREEN
11/20/2025
Signed off — Alteration
Construction of interior partitions and installation of doors and frames as shown in drawings provided herewith. No change in use, occupancy, or egress as of right.
M01142806-I1
10/21/2025
Permit issued — General Construction
M01294819-I1-GC
10/10/2025
Filed — Alteration
General construction related to interior partitions and installation of doors and frames as shown herewith on drawings. No change to use, egress, or occupancy.
M01294819-I1
10/07/2025
Signed off — Alteration
Sprinkler system work as shown of drawings filed herewith. No change to egress, use or egress as of right.
M01149646-I1
10/07/2025
Signed off — Alteration
Plumbing work as shown on drawings submitted herewith. No change to use, egress and occupancy as of right.
M01149643-I1
10/07/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
09/23/2025
Signed off — Alteration
Additions/Modifications to existing mechanical system as per plans herewith. No change to use, egress, or occupancy.
M01122784-I1
09/12/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
09/09/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
08/26/2025
Permit issued — Sprinklers
M01149646-I1-EW-SP
08/19/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
05/27/2025
Permit issued — Mechanical Systems
M01122784-S2-MS
05/14/2025
Violation issued (FDNY_ORDER, closed)
05/14/2025
Violation issued (FDNY_ORDER, closed)
04/10/2025
Permit issued — Mechanical Systems
M01149638-I1-MS
04/03/2025
Filed — Alteration
Sprinkler system work as shown of drawings filed herewith. No change to egress, use or egress as of right.
M01149646-I1
04/03/2025
Filed — Alteration
M01149638-I1
Latest 60 of 300 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offCONSTRUCTION BROOKLYN INC08/31/2026
DOB NOWMechanical SystemsSigned-offINTERIOR BUILDING SERVICE08/26/2026
DOB NOWGeneral ConstructionPermit IssuedPREMIER SANITATION LLC06/03/2026
DOB NOWGeneral ConstructionSigned-offINTERIOR BUILDING SERVICE04/28/2026
DOB NOWSprinklersPermit IssuedGRUSHINSKY PIPNG & HTG IN04/24/2026
DOB NOWGeneral ConstructionSigned-offCONSTRUCTION BROOKLYN INC01/23/2026
DOB NOWSprinklersPermit IssuedVULPIS & VULPIS PLBG INC01/21/2026
DOB NOWPlumbingSigned-offJEFFREY VULPIS PLMBNG LLC01/20/2026
DOB NOWPlumbingSigned-offJEFFREY VULPIS PLMBNG LLC01/20/2026
DOB NOWGeneral ConstructionSigned-offPREMIER SANITATION LLC01/09/2026
DOB NOWGeneral ConstructionSigned-offINTERIOR BUILDING SERVICE10/21/2025
DOB NOWSprinklersSigned-offGRUSHINSKY PIPNG & HTG IN08/26/2025
DOB NOWMechanical SystemsPermit IssuedINTERIOR BUILDING SERVICE05/27/2025
DOB NOWMechanical SystemsPermit IssuedINTERIOR BUILDING SERVICE04/10/2025
DOB NOWPlumbingSigned-offPFL MECHANICAL CORP01/24/2025
DOB NOWGeneral ConstructionSigned-offINTERIOR BUILDING SERVICE12/13/2024
DOB NOWPlumbingSigned-offPFL MECHANICAL CORP11/06/2024
DOB NOWGeneral ConstructionSigned-offINTERIOR BUILDING SERVICE10/23/2024
DOB NOWGeneral ConstructionPermit IssuedPREMIER SANITATION LLC06/04/2024
DOB NOWGeneral ConstructionSigned-offINTERIOR BUILDING SERVICE04/12/2024
DOB NOWGeneral ConstructionSigned-offPLATINUM GENERAL SERVICES12/14/2023
DOB NOWSidewalk ShedSigned-offA. PETER LUGER CONST INC04/03/2023
DOB NOWGeneral ConstructionPermit IssuedPREMIER SANITATION LLC03/29/2023
DOB NOWSprinklersSigned-offAMOK INC01/13/2023
DOB NOWSprinklersSigned-offARIANA CONTRACTING INC01/04/2023
DOB NOWPlumbingPermit IssuedFULL CIRCLE PLUMBING CORP12/14/2022
DOB NOWMechanical SystemsSigned-offTRITON CONSTRUCTION CO.,11/14/2022
DOB NOWProtection and Mechanical MethodsSigned-offA. PETER LUGER CONST INC09/27/2022
DOB NOWPlumbingPermit IssuedCOPPER MECHANICAL INC07/27/2022
DOB NOWGeneral ConstructionSigned-offA. PETER LUGER CONST INC07/26/2022
DOB NOWGeneral ConstructionPermit IssuedPREMIER SANITATION LLC06/24/2022
DOB NOWGeneral ConstructionSigned-offINTERIOR BUILDING SERVICE06/23/2022
DOB NOWPlumbingSigned-offJEFFREY VULPIS PLMBNG LLC06/21/2022
DOB NOWSprinklersSigned-offGRUSHINSKY PIPNG & HTG IN06/16/2022
DOB NOWMechanical SystemsSigned-offINTERIOR BUILDING SERVICE06/13/2022
DOB NOWPlumbingSigned-offDEMAR MECHANICAL INC06/08/2022
DOB NOWSprinklersSigned-offDEMAR PLUMBING CORP06/08/2022
DOB NOWSupported ScaffoldSigned-offA. PETER LUGER CONST INC06/02/2022
DOB NOWSprinklersSigned-offGRUSHINSKY PIPNG & HTG IN05/27/2022
DOB NOWMechanical SystemsSigned-offINTERIOR BUILDING SERVICE05/25/2022
+ 60 more permits on file
3 projects · most recent 04/14/2026
Heating and Air Conditioning Systems Ventilation Systems Air Conditioning Systems Heating Systems
FiledStatusContractorScopeMake / Model / Capacity
04/14/2026Signed-offINTERIOR BUILDING SERVICEHeating and Air Conditioning Systems, Ventilation Systems
Heat / Cool
Heat Controller MCR060AK C30COPS 60,000 BTU · Wshp ×1
MCR060AK C30COPS 60,000 BTU · Wshp ×1
Sigma SDSV-C.11802S2DS 185,000 BTU · Wshp ×1
Ventilation
Greenheck CSP-A700 450 CFM · Exhaust Fan ×1
SP-B150 50 CFM · Exhaust Fan ×1
03/04/2026Signed-offCONSTRUCTION BROOKLYN INCHeating and Air Conditioning Systems, Ventilation Systems
Heat / Cool
Ventilation
01/09/2026Permit IssuedINTERIOR BUILDING SERVICEAir Conditioning Systems, Heating Systems
Cooling
Comfort Aire HBH-060 58,800 BTU · Wshp ×12
Heating
Comfort Aire HBH-060 71,000 BTU · Wshp ×10
1 project · most recent 04/14/2026
FiledStatusContractorScope
04/14/2026Permit IssuedGRUSHINSKY PIPNG & HTG IN108 heads
3 projects · most recent 04/14/2026
Water/Sanitary
FiledStatusContractorScope
04/14/2026Signed-offJEFFREY VULPIS PLMBNG LLCWater/Sanitary
06/13/2022Signed-offJEFFREY VULPIS PLMBNG LLCWater/Sanitary
01/19/2021Permit IssuedFULL CIRCLE PLUMBING CORPWater/Sanitary
16 projects · most recent 08/04/2026
General Wiring Lighting Boiler Controls HVAC Wiring
FiledStatusContractorScope
08/04/2026Permit IssuedCENTENNIAL ELEVATOR INDUSGeneral Wiring
02/16/2026CompleteGLENDALE ELECTL CONTNG IN—
01/22/2026Permit IssuedJER ELECTRIC CORPGeneral Wiring, Lighting
01/12/2023CompleteMAXIMUM ELECTRIC CORP.Boiler Controls
06/08/2022CompleteDELCO ELECTRICAL CORP.General Wiring
05/09/2022CompleteJER ELECTRIC CORPGeneral Wiring
04/14/2022Permit IssuedCITYWIDE ELEC'L WIRING INGeneral Wiring
09/09/2021CompleteLAREDO ELECTRIC, INC.General Wiring
08/12/2021Permit IssuedCITYWIDE ELEC'L WIRING INGeneral Wiring
04/16/2021CompleteNASH ELECTRIC SERVICES IN—
04/29/2020CompleteE-J ELEC. INSTALLATION COGeneral Wiring
03/05/2020Permit IssuedJER ELECTRIC CORPHVAC Wiring
02/18/2020Permit IssuedJER ELECTRIC CORPGeneral Wiring, Lighting
02/18/2020Permit IssuedJER ELECTRIC CORPGeneral Wiring, Lighting
01/20/2020Permit IssuedCITYWIDE ELEC'L WIRING INGeneral Wiring
1 project · most recent 03/04/2026
Steel Concrete Masonry Wood
FiledStatusContractorScope
03/04/2026Signed-offCONSTRUCTION BROOKLYN INCSteel, Concrete, Masonry, Wood
▾Field Inspections (DOB CAP) — 44
DateTypeResultReport
03/05/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
02/04/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
01/30/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
01/30/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
01/29/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/26/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
01/23/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/07/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/12/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
09/09/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
08/19/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/07/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
11/15/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/16/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
09/21/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/07/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/07/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
04/05/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
04/03/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
04/03/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/13/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
03/13/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
02/07/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
02/07/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
02/03/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
Latest 25 of 44.
▾Special Inspection Requirements (DOB NOW) — 107
DateRequirementInspectorRole
03/04/2026Fire-Resistance Rated ConstructionDAMIAN ZUNINOprogress
03/04/2026Fire-Resistant Penetrations and JointsDAMIAN ZUNINOspecial
03/04/2026FinalDAMIAN ZUNINOprogress
01/22/2026FinalDAMIAN ZUNINOprogress
01/22/2026Fire-Resistance Rated ConstructionDAMIAN ZUNINOprogress
01/22/2026Fire-Resistant Penetrations and JointsDAMIAN ZUNINOspecial
01/08/2026FinalRAFAEL FIGUEROAprogress
01/08/2026Mechanical SystemsRAFAEL FIGUEROAspecial
12/02/2025Fire-Resistant Penetrations and JointsJACK GREENspecial
12/02/2025FinalJACK GREENprogress
12/02/2025Energy Code Compliance InspectionsJACK GREENprogress
12/02/2025Mechanical SystemsJACK GREENspecial
03/07/2025FinalNicholas Tjartjalisprogress
03/07/2025Energy Code Compliance InspectionsNicholas Tjartjalisprogress
03/07/2025Interior lighting powerNicholas Tjartjalisenergy_progress
10/07/2024FinalNicholas Tjartjalisprogress
04/02/2024Energy Code Compliance InspectionsNicholas Tjartjalisprogress
04/02/2024FinalNicholas Tjartjalisprogress
11/03/2023FinalDAVID CHAGNONprogress
11/03/2023Fire-Resistant Penetrations and JointsSEBASTIAN SETTEDUCATE JR., P.Especial
11/02/2023FinalDAVID CHAGNONprogress
11/02/2023Fire-Resistant Penetrations and JointsSEBASTIAN SETTEDUCATE JR., P.Especial
08/14/2023FinalNicholas Tjartjalisprogress
08/14/2023Energy Code Compliance InspectionsNicholas Tjartjalisprogress
08/14/2023Interior lighting powerNicholas Tjartjalisenergy_progress
Latest 25 of 107.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
BSO Seventh AvenueUnknown—
Project M08049425 Alteration · LOC Issued · 12/12/2022
Read from each project’s drawing title blocks and cover sheets and checked twice; a name appears only when it is the occupant, never the owner, landlord or designer.
▾Documents — 2,267 on file (BIS + DOB NOW)
▸Plans & Drawings102
▸DOB NOWPlans/Sketch71
09/06/2026M00001235-I1Request digital key ↗
09/06/2026M00002280-I1Request digital key ↗
09/06/2026M00006724-I1Request digital key ↗
Showing 3 of 71 on file for this type
▸DOB NOWPlans/Sketch - Plumbing11
09/05/2026M00294704-I1Request digital key ↗
09/04/2026M00362678-P1Request digital key ↗
09/04/2026M00362678-I1Request digital key ↗
Showing 3 of 11 on file for this type
▸DOB NOWPlans/Sketch - Sign7
09/05/2026M00266736-I1Request digital key ↗
09/05/2026M00266731-I1Request digital key ↗
09/05/2026M00266724-I1Request digital key ↗
Showing 3 of 7 on file for this type
▸DOB NOWPlans/Sketch - Sprinkler4
09/05/2026M00290798-I1Request digital key ↗
09/05/2026M00294685-I1Request digital key ↗
09/04/2026M00468371-P1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems3
09/05/2026M00285929-I1Request digital key ↗
09/05/2026M00294744-I1Request digital key ↗
09/04/2026M00468377-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Boiler Equipment3
09/03/2026M00362689-I1Request digital key ↗
09/03/2026M00362689-P2Request digital key ↗
Showing 2 of 3 on file for this type
▸DOB NOWPlans/Sketch - General Construction3
09/04/2026M00453166-P1Request digital key ↗
09/04/2026M00469396-I1Request digital key ↗
Showing 2 of 3 on file for this type
▸Applications & Permits325
▸BISPLAN / WORK APPROVAL APPLICATION177
02/02/2026101337313Open ↗
08/06/2025102730840Open ↗
01/25/2024104080236Open ↗
Showing 3 of 177 on file for this type
▸BISWORK PERMIT APPLICATION144
12/10/2020140988091Open ↗
09/04/2020140942041Open ↗
06/29/2020140915730Open ↗
Showing 3 of 144 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWHPD Certification Letter or CPC Special Permit2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Seals & Professional Certifications614
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION256
03/18/2020123832610Open ↗
01/24/2020123719976Open ↗
01/24/2020123719976Open ↗
Showing 3 of 256 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature101
09/06/2026M00006724-I1Open ↗
09/06/2026M00030409-I1Open ↗
09/06/2026M00030404-I1Open ↗
Showing 3 of 101 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST81
03/18/2020123832610Open ↗
12/23/2019123725200Open ↗
12/20/2019123848177Open ↗
Showing 3 of 81 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT62
12/09/2020140988091Open ↗
08/31/2020140942041Open ↗
06/24/2020140915730Open ↗
Showing 3 of 62 on file for this type
▸DOB NOWProgress Inspector Seal & Signature56
09/28/2026M00664290-P1Open ↗
09/28/2026M00664290-P1Open ↗
09/28/2026M00664290-P1Open ↗
Showing 3 of 56 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature26
09/23/2026M00362689-I1Open ↗
09/23/2026M00362689-I1Open ↗
09/23/2026M00704776-I1Open ↗
Showing 3 of 26 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM19
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 19 on file for this type
▸BISPC FULL REPORT4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISProfessional and Owner Certification (POC3)3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION3
12/09/2020140988091Open ↗
08/31/2020140942041Open ↗
06/24/2020140915730Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY3
12/09/2020140988091Open ↗
08/31/2020140942041Open ↗
06/24/2020140915730Open ↗
▸Trade Schedules & Equipment159
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE35
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 35 on file for this type
▸BISEQUIPMENT USE PERMITS33
10/26/2020123720429Open ↗
10/26/2020123720429Open ↗
10/22/2020123720429Open ↗
Showing 3 of 33 on file for this type
▸BISSELF-CERT PLUMBING NOTICE29
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 29 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA21
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 21 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT17
10/26/2020123720429Open ↗
10/22/2020123720429Open ↗
Showing 2 of 17 on file for this type
▸BISSCHEDULE B - PLUMBING12
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 12 on file for this type
▸BISSPRINKLER INSP REPORT : FP-856
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISFIRE PROTECTION PLAN(FPP): FDNY APPROVAL1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Safety & Tenant Protection82
▸DOB NOWHPD-1: Anti-Harassment Area Checklist63
09/05/2026M00266736-I1Open ↗
09/04/2026M00362678-I1Open ↗
09/04/2026M00362678-P2Open ↗
Showing 3 of 63 on file for this type
▸DOB NOWCertificate of No Harassment6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISTenant Protection Plan and Notes4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISANTI-HARASSMENT CHECKLIST3
03/18/2020123832610Open ↗
Showing 1 of 3 on file for this type
▸BISHPD: SRO MD CERTIFICATE OF NO HARASSMENT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Environmental & Asbestos195
▸BISASBESTOS: CERTIFICATION (DEP ACP5)83
12/10/2020140988091Open ↗
12/09/2020140988091Open ↗
09/04/2020140942041Open ↗
Showing 3 of 83 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report81
09/06/2026M00006724-I1Open ↗
09/06/2026M00030409-I1Open ↗
09/06/2026M00030404-I1Open ↗
Showing 3 of 81 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'14
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 14 on file for this type
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP 20-21-5)4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form2
09/04/2026M00362678-I1Open ↗
Showing 1 of 2 on file for this type
▸Energy Compliance158
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS85
03/18/2020123832610Open ↗
12/23/2019123725200Open ↗
12/20/2019123848177Open ↗
Showing 3 of 85 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS48
10/24/2025140988091Open ↗
09/30/2022140915730Open ↗
06/15/2021140988091Open ↗
Showing 3 of 48 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY10
10/24/2025140988091Open ↗
10/24/2025140988091Open ↗
06/15/2021140988091Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWEN2: As Built Energy Analysis9
09/03/2026M00656556-I1Open ↗
09/02/2026M00750320-I1Open ↗
09/04/2026M00468377-I1Open ↗
Showing 3 of 9 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
12/09/2020140988091Open ↗
06/24/2020140915730Open ↗
▸BISTR8: Energy Code Progress Inspections2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISNYCECC ANALYSIS1
06/24/2020140915730Open ↗
▸DOB NOWPreliminary Commissioning Report Certification1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Inspections & Test Reports26
▸BISTECHNICAL REPORT: RESPONSIBILITY22
10/24/2025140988091Open ↗
10/24/2025140988091Open ↗
08/08/2025102730840Open ↗
Showing 3 of 22 on file for this type
▸BISHYDRAULIC FLOW CALCULATIONS2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISBORINGS / TEST PITS (TR-4) 27-7201
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BIS* FINAL INSPECTION DIRECTIVE 14 OF 19751
08/08/2025102730840Open ↗
▸Approvals, Objections & Sign-offs158
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST123
10/24/2025140988091Open ↗
10/14/2022140915730Open ↗
06/15/2021140988091Open ↗
Showing 3 of 123 on file for this type
▸BISADMINISTRATIVE OBJECTIONS19
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 19 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION11
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 11 on file for this type
▸BISSUPERSEDING LETTER2
03/13/2020104596439Open ↗
Showing 1 of 2 on file for this type
▸BISLETTERS - APPROVED FABRICATION CERTIFICATIONS1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISTRANSIT AUTHORITY/MTA/PANYNJ APPROVAL1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISCONSTRUCTION CODE DETERMINATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Cost, Insurance & Ownership212
▸BISCOST AFFIDAVIT212
10/24/2025140988091Open ↗
08/07/2025102730840Open ↗
09/30/2022140915730Open ↗
Showing 3 of 212 on file for this type
▸Filing & Intake Forms223
▸BISEFILING COVER SHEET112
03/18/2020123832610Open ↗
12/23/2019123725200Open ↗
12/23/2019123725200Open ↗
Showing 3 of 112 on file for this type
▸BISBOROUGH INTAKE FORM76
01/24/2020123719976Open ↗
01/23/2020104452496Open ↗
01/21/2020123809058Open ↗
Showing 3 of 76 on file for this type
▸BISADDITIONAL INFORMATION31
04/29/2021123848177Open ↗
12/29/2020140988091Open ↗
12/16/2020140988091Open ↗
Showing 3 of 31 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET4
12/09/2020140988091Open ↗
08/31/2020140942041Open ↗
06/24/2020140915730Open ↗
Showing 3 of 4 on file for this type
▸Other Documents12
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸DOB NOWProof of Historic Building4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISSupporting Document: Fee Exempt1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISLAA - Supporting Documentation1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type