← Back
Over six families without stores
550 AUDUBON AVENUE
MANHATTAN · BIN 1063874
💬 Discuss this project
1923Year Built
5Stories
C1Building Class
R7-2Zoning
39,485 sfGross Floor Area
45Units
LL97 CoveredRent Stabilized5 Open Violations ▸FDNY Report ↗
Over six families without stores · Owner of record: 550 AUDUBON ASSOC · 10,000 sf lot · 3.95 FAR built · Flood zone X
Locations of Work
MechanicalPlumbingLandscape
Basement1p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
A+ CHOICE CONSTRUCTION1307/08/2026
CITADEL REALTY SERVICES1807/08/2026
JIMMY G CONSTRUCTION503/22/2026
550 AUDUBON ASSOC1203/22/2026
550 AUDUBON ASSC103/22/2026
550 AUDUBON ASSO103/22/2026
OWNER OF 550 ADUBON AVE403/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NS ENGINEERS, P.C.602/24/2022
ENTHINK ENGINEERS LLC510/08/2021
LUIS PICHARDO, PE105/25/2021
GREEN DESIGN111/20/2020
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
YOUBER DESIGN1203/21/2026
JM ZONING, LLC.203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CLEAN TECH MECHANICAL INCPlumbing307/08/2026
A+ CHOICE CONSTRUCTION INGeneral Contractor207/08/2026
JIMMY G CONSTRUCTION CORPGeneral Contractor203/21/2026
MICHAEL SCHMIDTElectrical103/21/2026
SILVER, HUGHElectrical103/21/2026
D'ANNUNZIO MICHAELElectrical103/21/2026
TOUEY, CHRISTOPHERElectrical103/21/2026
SITRUK, MAURICEElectrical103/21/2026
METAL CRAFTS BY N BARSILYElectrical103/21/2026
MICHAEL D'ANNUNZIOElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
NS ENGINEERS, P.C.1442602/24/2022
ENTHINK ENGINEERS LLC6247209/01/2021
JOSE A SANTOS PE, PC3292105/25/2021
Building Lifecycle
All (110)Filed (13)Permit Issued (5)Signed Off (1)Violation (60)Inspection (6)Special Inspection (25)
12/14/2025
Violation issued (HPD, closed)
B
12/14/2025
Violation issued (HPD, closed)
C
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
02/14/2025
Violation issued (HPD, closed)
C
02/10/2025
Violation issued (HPD, closed)
C
12/01/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
09/23/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
09/23/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
07/13/2023
Violation issued (HPD, closed)
C
03/15/2023
Violation issued (HPD, closed)
A
03/11/2022
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
03/10/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
02/24/2022
Filed — Alteration
PROPOSE TO INSTALL TWO TANKLESS GAS HOT WATER HEATERS, NAVIEN NPE-240A. ONE WEIL MCLAIN SF750 HOT WATER HEATER AND TWO WEIL MCLAIN HOT WATER STORAGE TANKS, AS PER PLANS SUBMITTED HEREWITH.
M00518540-P3
02/17/2022
Special inspection requirement — HVAC-R and service water heating system controls
Shamsul Siddique
02/17/2022
Special inspection requirement — Maintenance information
Shamsul Siddique
02/17/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Shamsul Siddique
02/17/2022
Special inspection requirement — HVAC-R and service water heating equipment
Shamsul Siddique
02/17/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
Shamsul Siddique
02/17/2022
Special inspection requirement — Energy Code Compliance Inspections
Shamsul Siddique
02/15/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
02/09/2022
Filed — Alteration
PROPOSE TO INSTALL TWO TANKLESS GAS HOT WATER HEATERS, NAVIEN NPE-240A. ONE WEIL MCLAIN SF750 HOT WATER HEATER AND TWO WEIL MCLAIN HOT WATER STORAGE TANKS, AS PER PLANS SUBMITTED HEREWITH.
M00518540-P2
02/01/2022
Special inspection requirement — Heating Systems
Shamsul Siddique
01/31/2022
Filed — Alteration
PROPOSE TO INSTALL TWO TANKLESS GAS HOT WATER HEATERS, NAVIEN NPE-240A. ONE WEIL MCLAIN SF750 HOT WATER HEATER AND TWO WEIL MCLAIN HOT WATER STORAGE TANKS, AS PER PLANS SUBMITTED HEREWITH.
M00518540-P1
01/28/2022
Signed off — Alteration
FACADE REPAIR, POINTING AS PER PLAN. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
M00470121-I1
01/28/2022
Inspection — Pass-Final Boiler Equipment Inspection
Pass
View inspection ↗
01/28/2022
Special inspection requirement — Heating Systems
Shamsul Siddique
01/28/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Shamsul Siddique
01/28/2022
Special inspection requirement — Energy Code Compliance Inspections
Shamsul Siddique
01/28/2022
Special inspection requirement — HVAC-R and service water heating equipment
Shamsul Siddique
01/28/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
Shamsul Siddique
01/28/2022
Special inspection requirement — Maintenance information
Shamsul Siddique
01/28/2022
Special inspection requirement — HVAC-R and service water heating system controls
Shamsul Siddique
01/25/2022
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
01/22/2022
Violation issued (HPD, closed)
C
01/22/2022
Violation issued (HPD, closed)
C
01/19/2022
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
12/11/2021
Permit issued — Boiler Equipment
M00518540-S1-BE
12/03/2021
Filed — Alteration
PROPOSE TO INSTALL TWO TANKLESS GAS HOT WATER HEATERS, NAVIEN NPE-240A. ONE WEIL MCLAIN SF750 HOT WATER HEATER AND TWO WEIL MCLAIN HOT WATER STORAGE TANKS, AS PER PLANS SUBMITTED HEREWITH.
M00518540-S1
12/01/2021
Filed — Alteration
PROPOSE TO INSTALL TWO TANKLESS GAS HOT WATER HEATERS, NAVIEN NPE-240A. ONE WEIL MCLAIN SF750 HOT WATER HEATER AND TWO WEIL MCLAIN HOT WATER STORAGE TANKS, AS PER PLANS SUBMITTED HEREWITH.
M00518540-S2
11/29/2021
Special inspection requirement — Energy Code Compliance Inspections
Shamsul Siddique
11/19/2021
Special inspection requirement — Final
Shamsul Siddique
11/19/2021
Special inspection requirement — Chimneys and vents
Shamsul Siddique
10/08/2021
Filed — Alteration
M00470114-P2
09/01/2021
Filed — Alteration
FACADE REPAIR, POINTING AS PER PLAN. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
M00470121-P1
09/01/2021
Special inspection requirement — Energy Code Compliance Inspections
Sunil Saigal
09/01/2021
Special inspection requirement — Final
Sunil Saigal
09/01/2021
Special inspection requirement — Masonry
Sunil Saigal
09/01/2021
Special inspection requirement — Structural Stability – Alterations of existing buildings
Sunil Saigal
06/03/2021
Permit issued — Plumbing
M00518540-I1-PL
05/25/2021
Filed — Alteration
M00518505-I1
05/13/2021
Filed — Alteration
PROPOSE TO INSTALL TWO TANKLESS GAS HOT WATER HEATERS, NAVIEN NPE-240A. ONE WEIL MCLAIN SF750 HOT WATER HEATER AND TWO WEIL MCLAIN HOT WATER STORAGE TANKS, AS PER PLANS SUBMITTED HEREWITH.
M00518540-I1
05/10/2021
Filed — Alteration
M00470114-P1
04/29/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
04/21/2021
Special inspection requirement — Energy Code Compliance Inspections
Sunil Saigal
04/21/2021
Special inspection requirement — Final
Sunil Saigal
04/21/2021
Special inspection requirement — Structural Stability – Alterations of existing buildings
Sunil Saigal
04/21/2021
Special inspection requirement — Masonry
Sunil Saigal
03/05/2021
Permit issued — General Construction
M00470121-I1-GC
02/24/2021
Filed — Alteration
FACADE REPAIR, POINTING AS PER PLAN. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
M00470121-I1
Latest 60 of 110 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWBoiler EquipmentSigned-offCLEAN TECH MECHANICAL INC12/11/2021
DOB NOWPlumbingSigned-offCLEAN TECH MECHANICAL INC06/03/2021
DOB NOWGeneral ConstructionSigned-offA+ CHOICE CONSTRUCTION IN03/05/2021
DOB NOWSidewalk ShedPermit IssuedA+ CHOICE CONSTRUCTION IN02/18/2021
DOB NOWSidewalk ShedPermit IssuedJIMMY G CONSTRUCTION CORP11/24/2020
BISOTISSUEDA+ CHOICE CONSTRUCTION IN11/30/2020
BISOTISSUEDPHILIP TOSCANO09/07/2016
BISPLISSUEDBILLHARZ PLUMBING, INC03/16/2016
BISOTISSUEDKINGS STAR CONSTRUCTION C02/03/2016
BISOTISSUEDVALLEY CONSTRUCTION SERVICES10/01/2008
BISPLISSUEDGUSTAVE M. MENOCAL CONTRACTING09/30/2008
BIS—ISSUED550 AUDUBON ASSOC.CITADEL MGMT.05/14/1992
BISOTISSUEDJETWORK SERVICES LLC10/22/1991
BISPLISSUEDJETWORK SERVICES LLC10/22/1991
BISBLISSUEDBURNSIDE OIL BURNER SERVICE07/30/1991
1 project · most recent 02/24/2022
Gas Water/Sanitary
FiledStatusContractorScope
02/24/2022Signed-offCLEAN TECH MECHANICAL INCGas, Water/Sanitary
1 project · most recent 03/08/2021
FiledStatusContractorScope
03/08/2021Permit IssuedRICHARD NEU—
1 project · most recent 11/20/2020
Sidewalk Shed
FiledStatusContractorScope
11/20/2020Permit IssuedJIMMY G CONSTRUCTION CORPSidewalk Shed
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
03/11/2022Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/10/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
02/15/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/28/2022Pass-Final Boiler Equipment InspectionPassView ↗
01/25/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
01/19/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
▾Special Inspection Requirements (DOB NOW) — 25
DateRequirementInspectorRole
02/17/2022HVAC-R and service water heating system controlsShamsul Siddiqueenergy_progress
02/17/2022Maintenance informationShamsul Siddiqueenergy_progress
02/17/2022Fire-Resistant Penetrations and JointsShamsul Siddiquespecial
02/17/2022HVAC-R and service water heating equipmentShamsul Siddiqueenergy_progress
02/17/2022HVAC-R and service water piping design and insulationShamsul Siddiqueenergy_progress
02/17/2022Energy Code Compliance InspectionsShamsul Siddiqueprogress
02/01/2022Heating SystemsShamsul Siddiquespecial
01/28/2022Heating SystemsShamsul Siddiquespecial
01/28/2022Fire-Resistant Penetrations and JointsShamsul Siddiquespecial
01/28/2022Energy Code Compliance InspectionsShamsul Siddiqueprogress
01/28/2022HVAC-R and service water heating equipmentShamsul Siddiqueenergy_progress
01/28/2022HVAC-R and service water piping design and insulationShamsul Siddiqueenergy_progress
01/28/2022Maintenance informationShamsul Siddiqueenergy_progress
01/28/2022HVAC-R and service water heating system controlsShamsul Siddiqueenergy_progress
11/29/2021Energy Code Compliance InspectionsShamsul Siddiqueprogress
11/19/2021FinalShamsul Siddiqueprogress
11/19/2021Chimneys and ventsShamsul Siddiquespecial
09/01/2021Energy Code Compliance InspectionsSunil Saigalprogress
09/01/2021FinalSunil Saigalprogress
09/01/2021MasonrySunil Saigalspecial
09/01/2021Structural Stability – Alterations of existing buildingsSunil Saigalspecial
04/21/2021Energy Code Compliance InspectionsSunil Saigalprogress
04/21/2021FinalSunil Saigalprogress
04/21/2021Structural Stability – Alterations of existing buildingsSunil Saigalspecial
04/21/2021MasonrySunil Saigalspecial
▾Documents — 117 on file (BIS + DOB NOW)
▸Plans & Drawings13
▸DOB NOWPlans/Sketch7
09/03/2026M00518505-I1Request digital key ↗
09/02/2026M00518540-I1Request digital key ↗
09/02/2026M00518540-S2Request digital key ↗
Showing 3 of 7 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed4
09/04/2026M00427194-I1Request digital key ↗
09/03/2026M00470114-I1Request digital key ↗
08/15/2026M00470114-P1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - General Construction2
09/03/2026M00470121-I1Request digital key ↗
09/03/2026M00470121-P1Request digital key ↗
▸Applications & Permits12
▸BISPLAN / WORK APPROVAL APPLICATION6
11/20/2020140982131Open ↗
06/29/2016122654966Open ↗
06/16/2016122654966Open ↗
Showing 3 of 6 on file for this type
▸BISWORK PERMIT APPLICATION6
11/30/2020140982131Open ↗
09/22/2016122654966Open ↗
03/28/2016122654966Open ↗
Showing 3 of 6 on file for this type
▸Seals & Professional Certifications50
▸DOB NOWProgress Inspector Seal & Signature16
09/01/2026M00470121-P1Open ↗
09/01/2026M00470121-P1Open ↗
09/01/2026M00518540-P2Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature13
09/03/2026M00518505-I1Open ↗
09/03/2026M00470121-P1Open ↗
09/03/2026M00470121-I1Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature9
09/23/2026M00518540-S1Open ↗
09/01/2026M00470121-P1Open ↗
09/01/2026M00470121-P1Open ↗
Showing 3 of 9 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT3
11/20/2020140982131Open ↗
11/20/2020140982131Open ↗
01/25/2016122654966Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION3
01/05/2018122654966Open ↗
01/25/2016122654966Open ↗
09/16/2008110343744Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM2
09/16/2008110343744Open ↗
09/16/2008110343744Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST2
01/25/2016122654966Open ↗
09/16/2008110343744Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
11/20/2020140982131Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
11/20/2020140982131Open ↗
▸Trade Schedules & Equipment4
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE2
06/29/2016122654966Open ↗
01/25/2016122654966Open ↗
▸BISSCHEDULE B - PLUMBING1
09/16/2008110343744Open ↗
▸BISSELF-CERT PLUMBING NOTICE1
11/10/2008110343744Open ↗
▸Safety & Tenant Protection2
▸BISTPP1: TENANT PROTECTION PLAN1
11/26/2021140982131Open ↗
▸DOB NOWTenant Protection Plan1
08/13/2026M00427194-I1Open ↗
▸Environmental & Asbestos10
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
09/03/2026M00518505-I1Open ↗
08/13/2026M00518540-P1Open ↗
08/13/2026M00518540-S2Open ↗
Showing 3 of 7 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
11/20/2020140982131Open ↗
01/25/2016122654966Open ↗
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
09/16/2008110343744Open ↗
▸Energy Compliance6
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
11/27/2020140982131Open ↗
11/20/2020140982131Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS2
01/05/2018122654966Open ↗
01/25/2016122654966Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
11/20/2020140982131Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
01/05/2018122654966Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
11/27/2020140982131Open ↗
11/20/2020140982131Open ↗
▸Approvals, Objections & Sign-offs2
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
01/05/2018122654966Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
09/16/2008110343744Open ↗
▸Cost, Insurance & Ownership7
▸BISCOST AFFIDAVIT6
11/20/2020140982131Open ↗
01/05/2018122654966Open ↗
06/29/2016122654966Open ↗
Showing 3 of 6 on file for this type
▸BISCIVIL PENALTY AFFIDAVIT/REQUEST1
09/16/2016122654966Open ↗
▸Filing & Intake Forms8
▸BISADDITIONAL INFORMATION3
11/17/2016122654966Open ↗
07/18/2016122654966Open ↗
06/16/2016122654966Open ↗
▸BISEFILING COVER SHEET3
01/25/2016122654966Open ↗
09/16/2008110343744Open ↗
09/16/2008110343744Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
11/20/2020140982131Open ↗
▸BISBOROUGH INTAKE FORM1
01/05/2018122654966Open ↗
▸Other Documents1
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
01/05/2018122654966Open ↗