| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 10/10/2025 | $2.0M | — | Private party → Private party | $393/sf building |
| 01/25/2016 | $1.5M | — | Private party → Private party | $289/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| SYNERGIC DESIGN ARCHITECTS | 2 | 10/30/2025 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| THOMAS KELLY | Electrical | 1 | 03/21/2026 |
| TRAVALJA, SILVANO | Electrical | 1 | 03/21/2026 |
| WIDE FLANGE INC | Electrical | 1 | 03/21/2026 |
| ACCORD POWER INC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SYNERGIC DESIGN LLC | 8561 | 2 | 10/30/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | ACCORD POWER INC | 11/03/2025 |
| BIS | OT | ISSUED | C KELLY INC | 07/16/2020 |
| BIS | OT | ISSUED | DARINE GENERAL DESIGN COR | 04/13/2016 |
| BIS | OT | ISSUED | N/A | 10/05/2015 |
| BIS | — | ISSUED | Z.J.W. CONSTRUCTION, INC | 02/25/2003 |
| BIS | PL | ISSUED | ORBIT PLBG & HTG INC | 02/21/2003 |
| BIS | PL | ISSUED | ORBIT PLBG & HTG INC | 10/15/2002 |
| BIS | — | ISSUED | DENNIS ADAMS CONTRACTOR, INC. | 09/16/2002 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/03/2025 | Complete | ACCORD POWER ELECTRIC LLC | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/30/2025 | Fire-Resistant Penetrations and Joints | Malathi Ananthakrishnan | special |
| 10/30/2025 | Structural Stability – Alterations of existing buildings | Malathi Ananthakrishnan | special |
| 10/30/2025 | Energy Code Compliance Inspections | Malathi Ananthakrishnan | progress |
| 10/30/2025 | Final | Malathi Ananthakrishnan | progress |
| 10/30/2025 | Air barrier - visual inspection | Malathi Ananthakrishnan | energy_progress |
| 10/27/2025 | Fire-Resistant Penetrations and Joints | Malathi Ananthakrishnan | special |
| 10/27/2025 | Structural Stability – Alterations of existing buildings | Malathi Ananthakrishnan | special |
| 10/27/2025 | Energy Code Compliance Inspections | Malathi Ananthakrishnan | progress |
| 10/27/2025 | Final | Malathi Ananthakrishnan | progress |
| 10/27/2025 | Air barrier - visual inspection | Malathi Ananthakrishnan | energy_progress |