| Owner | Filings | Most Recent |
|---|---|---|
| 551 39TH STREET | 8 | 07/08/2026 |
| PM2 CONSTRUCTION CORP | 2 | 03/22/2026 |
| PMZ CONSTRUCTION | 1 | 03/22/2026 |
| METRO CONTRACTING NY | 4 | 03/21/2026 |
| SOUTH SLOPE DEVELOPERS | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| CL ENGINEERING P.C. | 1 | 06/08/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| METRO DESIGN CONSULTANTS INC | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HENRY MYERS PLUMBING & H | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CL ENGINEERING P.C. | 6781 | 1 | 06/08/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Signed-off | HENRY MYERS PLUMBING H | 06/15/2022 |
| BIS | — | ISSUED | PMZ CONSTRUCTION CORP | 04/18/2019 |
| BIS | PL | ISSUED | HENRY MYERS P & H, INC | 10/18/2018 |
| BIS | SP | ISSUED | KG SPRINKLER CORP | 06/29/2018 |
| BIS | — | ISSUED | PMZ CONSTRUCTION CORP | 10/17/2017 |
| BIS | PL | ISSUED | HENRY MYERS P & H, INC | 10/09/2017 |
| BIS | SP | ISSUED | KG SPRINKLER CORP | 06/30/2017 |
| BIS | EQ | ISSUED | METRO CONTRACTING NY, INC. | 04/25/2017 |
| BIS | — | ISSUED | PMZ CONSTRUCTION CORP | 10/06/2016 |
| BIS | PL | ISSUED | HENRY MYERS P & H, INC | 10/06/2016 |
| BIS | SP | ISSUED | KG SPRINKLER CORP | 06/28/2016 |
| BIS | EQ | ISSUED | METRO CONTRACTING NY, INC. | 04/27/2016 |
| BIS | EQ | ISSUED | PMZ CONSTRUCTION CORP | 11/05/2015 |
| BIS | OT | ISSUED | PMZ CONSTRUCTION CORP | 11/05/2015 |
| BIS | PL | ISSUED | JOHN HLAD P & H CO., INC | 07/22/2011 |
| BIS | MH | ISSUED | JOSEPH RIZZUTI | 07/08/2011 |
| BIS | — | ISSUED | ANTHONY GALLINA HEAT&MECH | 12/26/2008 |
| BIS | PL | ISSUED | ANTHONY GALLINA H&M CORP | 12/19/2008 |
| BIS | EQ | ISSUED | ANTHONY GALLINA HEAT&MECH | 12/24/2007 |
| BIS | — | ISSUED | ANTHONY GALLINA HEAT&MECH | 07/03/2007 |
| BIS | — | ISSUED | ANTHONY GALLINA HEAT&MECH | 05/23/2007 |
| BIS | EQ | ISSUED | ANTHONY GALLINA HEAT&MECH | 05/23/2007 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/07/2022 | Concrete - Cast-In-Place | CHRISTIAN LOZADA | special |
| 06/07/2022 | Fire-Resistant Penetrations and Joints | CHRISTIAN LOZADA | special |
| 06/07/2022 | Masonry | CHRISTIAN LOZADA | special |
| 06/07/2022 | Structural Steel - Details | CHRISTIAN LOZADA | special |
| 06/07/2022 | Structural Steel - Welding | CHRISTIAN LOZADA | special |
| 06/07/2022 | Structural Stability – Alterations of existing buildings | CHRISTIAN LOZADA | special |
| 05/09/2022 | Final | CHRISTIAN LOZADA | progress |