Elevator apt, fireproof with stores
The Westline
622 11 AVENUE · BIN 1091827
💬 Discuss this project
2024Year Built
14Stories
D6Building Class
R8AZoning
100,233 sfGross Floor Area
51Units
0 Open Violations
Elevator apt, fireproof with stores · Owner of record: ELEVEN W46 REALTY LLC · 8,242 sf lot · 12.16 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionEquipmentGeneral
Roof13p · 2 filings · 20 docs
Floor 713p · 1 filing · 20 docs
Floor 613p · 2 filings · 20 docs
Floor 513p · 1 filing · 20 docs
Floor 413p · 1 filing · 20 docs
Floor 313p · 1 filing · 20 docs
Floor 213p · 1 filing · 20 docs
Floor 113p · 1 filing · 20 docs
Cellar13p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
CHESS BUILDERS4907/08/2026
OWNERS REP1407/08/2026
ELEVEN W46 REALTY LLC503/22/2026
B CONTRACTORS GROUP103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
03/21/2024$33.2M—616 11TH AVENUE LLC → ELEVEN W46 REALTY LLC$331/sf building
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
AE DESIGN SOLUTION1803/21/2026
EXPEDITING 4 U1603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
B CONTRACTORS GROUP LLCGeneral Contractor1807/08/2026
CORE SCAFFOLD SYSTEMS INC.General Contractor1007/08/2026
HIVOLTS ELECTRICAL INC 004090General Contractor403/22/2026
S WIEDER ARCHITECT P CGeneral Contractor403/22/2026
DENALI ELECTRIC CORP 004505General Contractor103/22/2026
PRIME PIPING & HEATING INFire Protection107/08/2026
MPI PLUMBING CORPPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
REGIONAL TESTING CORP.3941401/06/2026
LEO Y LEE ASSOCIATES2481202/21/2025
Building Lifecycle
All (111)Filed (24)Permit Issued (14)Signed Off (14)Violation (1)Inspection (9)Objection (16)Special Inspection (30)Tax Incentive (3)
02/19/2026
Signed off — New Building
SUBSEQUENT SITE CONNECTION PLUMBING SLEEVE APPLICATION FILED HEREWITH.
M01039403-I1
01/13/2026
Signed off — Alteration
M01328606-I1
01/08/2026
Permit issued — Mechanical Systems
M01328606-I1-MS
01/06/2026
Filed — Alteration
M01328606-I1
09/05/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY ROOF PROTECTION AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01148144-I1
07/31/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01148120-I1
07/31/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY NEEDLE BEAM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01148134-I1
07/31/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01148114-I1
06/11/2025
Signed off — New Building
SUBSEQUENT SITE CONNECTION PLUMBING SLEEVE APPLICATION FILED HEREWITH.
M01039403-S5
06/11/2025
Signed off — Alteration
M01105740-I1
06/11/2025
Signed off — New Building
SUBSEQUENT SITE CONNECTION PLUMBING SLEEVE APPLICATION FILED HEREWITH.
M01039403-S6
06/09/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
06/05/2025
Signed off — New Building
SUBSEQUENT SITE CONNECTION PLUMBING SLEEVE APPLICATION FILED HEREWITH.
M01039403-S3
06/04/2025
Signed off — New Building
SUBSEQUENT SITE CONNECTION PLUMBING SLEEVE APPLICATION FILED HEREWITH.
M01039403-S4
06/04/2025
Inspection — Certified Sprinkler (SP) - Booster Pump Test
Certified
View inspection ↗
06/04/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
05/29/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
05/29/2025
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
05/13/2025
Special inspection requirement — HVAC-R and service water heating equipment
Paul Raymond
05/13/2025
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
Paul Raymond
05/13/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Paul Raymond
05/13/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Paul Raymond
05/13/2025
Special inspection requirement — Maintenance information
Paul Raymond
05/13/2025
Special inspection requirement — HVAC-R and service water heating system controls
Paul Raymond
05/06/2025
Filed — New Building
SUBSEQUENT SITE CONNECTION PLUMBING SLEEVE APPLICATION FILED HEREWITH.
M01039403-P4
05/01/2025
Special inspection requirement — Post-installed Anchors
Paul Raymond
05/01/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Paul Raymond
05/01/2025
Special inspection requirement — Sprinkler Systems
Paul Raymond
04/30/2025
485-x construction completed
04/29/2025
Special inspection requirement — Fenestration air leakage
Paul Raymond
04/29/2025
Special inspection requirement — Maintenance information
Paul Raymond
04/29/2025
Special inspection requirement — Metering
Paul Raymond
04/29/2025
Special inspection requirement — Exterior lighting power
Paul Raymond
04/29/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
Paul Raymond
04/29/2025
Special inspection requirement — Fire-Resistance Rated Construction
Paul Raymond
04/29/2025
Special inspection requirement — Insulation placement and R values
Paul Raymond
04/29/2025
Special inspection requirement — Lighting in dwelling units
Paul Raymond
04/29/2025
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
Paul Raymond
04/29/2025
Special inspection requirement — Interior lighting power
Paul Raymond
04/29/2025
Special inspection requirement — Fenestration areas
Paul Raymond
04/29/2025
Special inspection requirement — Electrical motors and elevators
Paul Raymond
04/29/2025
Special inspection requirement — Energy Code Compliance Inspections
Paul Raymond
04/29/2025
Special inspection requirement — Protection of exposed foundation insulation
Paul Raymond
04/29/2025
Special inspection requirement — Air barrier continuity plan testing
Paul Raymond
04/29/2025
Special inspection requirement — Air barrier - visual inspection
Paul Raymond
04/29/2025
Special inspection requirement — Lighting controls
Paul Raymond
04/29/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Paul Raymond
04/24/2025
Filed — New Building
SUBSEQUENT SITE CONNECTION PLUMBING SLEEVE APPLICATION FILED HEREWITH.
M01039403-P5
04/21/2025
Signed off — New Building
SUBSEQUENT SITE CONNECTION PLUMBING SLEEVE APPLICATION FILED HEREWITH.
M01039403-S7
04/21/2025
Signed off — New Building
SUBSEQUENT SITE CONNECTION PLUMBING SLEEVE APPLICATION FILED HEREWITH.
M01039403-S2
03/04/2025
Special inspection requirement — Post-installed Anchors
Leo Lee
02/26/2025
Filed — New Building
SUBSEQUENT SITE CONNECTION PLUMBING SLEEVE APPLICATION FILED HEREWITH.
M01039403-S8
02/25/2025
Signed off — New Building
SUBSEQUENT SITE CONNECTION PLUMBING SLEEVE APPLICATION FILED HEREWITH.
M01039403-S1
02/21/2025
Filed — Alteration
INSTALLATION OF TEMPORARY NEEDLE BEAM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01148134-P1
02/21/2025
Filed — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01148120-P1
02/21/2025
Special inspection requirement — Post-installed Anchors
Leo Lee
02/13/2025
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
02/06/2025
Filed — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01148114-P1
01/16/2025
Filed — Alteration
INSTALLATION OF TEMPORARY ROOF PROTECTION AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01148144-P1
01/16/2025
Permit issued — Protection and Mechanical Methods
M01148134-I1-PMM
Latest 60 of 111 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offB CONTRACTORS GROUP LLC01/08/2026
DOB NOWProtection and Mechanical MethodsSigned-offCORE SCAFFOLD SYSTEMS INC01/16/2025
DOB NOWMechanical SystemsSigned-offB CONTRACTORS GROUP LLC01/13/2025
DOB NOWSprinklersSigned-offA M B MECHANICAL INC12/03/2024
DOB NOWSupported ScaffoldSigned-offCORE SCAFFOLD SYSTEMS INC11/27/2024
DOB NOWSidewalk ShedSigned-offCORE SCAFFOLD SYSTEMS INC11/27/2024
DOB NOWProtection and Mechanical MethodsSigned-offCORE SCAFFOLD SYSTEMS INC11/27/2024
DOB NOWPlumbingSigned-offYG SERVICES INC11/18/2024
DOB NOWConstruction FenceSigned-offB CONTRACTORS GROUP LLC10/15/2024
DOB NOWGeneral ConstructionPermit IssuedB CONTRACTORS GROUP LLC08/26/2024
DOB NOWSupport of ExcavationSigned-offB CONTRACTORS GROUP LLC08/12/2024
DOB NOWStructuralSigned-offB CONTRACTORS GROUP LLC08/12/2024
DOB NOWFoundationSigned-offB CONTRACTORS GROUP LLC08/12/2024
DOB NOWFoundationSigned-offB CONTRACTORS GROUP LLC08/12/2024
1 project · most recent 05/06/2025
Air Conditioning Systems Heating and Air Conditioning Systems Heating Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
05/06/2025Signed-offB CONTRACTORS GROUP LLCAir Conditioning Systems, Heating and Air Conditioning Systems, Heating Systems, Ventilation Systems
Cooling
Daikin RXF18AXVJU 18,100 BTU · Condensing Unit ×5
Heat / Cool
Daikin 4MXS36WMVJU9 2 tons · Condensing Unit ×35
RMXS48LVJU 4 tons · Condensing Unit ×13
3MXL24WMVJU9 2 tons · Condensing Unit ×5
RXTQ36TAVJ9A 4 tons · Vrf Outdoor ×2
RXTQ48TAVJ9A 4 tons · Vrf Outdoor ×2
Heating
Daikin RXF18AXVJU 21,600 BTU · Condensing Unit ×5
Ventilation
Greenheck CUE-099-VG 500 CFM · Exhaust Fan ×1
ECV-20P-H 800 CFM · Exhaust Fan ×1
Nutone AEN110 50 CFM · Exhaust Fan ×1
QTXE110150DC 100 CFM · Kitchen Exhaust ×1
1 project · most recent 05/06/2025
Sprinkler System
FiledStatusContractorScope
05/06/2025Signed-offPRIME PIPING & HEATING INSprinkler System
1 project · most recent 05/06/2025
Storm Water/Sanitary
FiledStatusContractorScope
05/06/2025Signed-offMPI PLUMBING CORPStorm, Water/Sanitary
4 projects · most recent 09/25/2025
General Wiring
FiledStatusContractorScope
09/25/2025CompleteDENALI ELECTRIC CORP—
07/07/2025CompleteHIVOLTS ELECTRICAL INC1 meters, 1 new_meters
06/10/2025CompleteHIVOLTS ELECTRICAL INCGeneral Wiring
12/20/2024CompleteSOLAS ELECTRICAL CORP—
1 project · most recent 05/06/2025
Concrete
FiledStatusContractorScope
05/06/2025Signed-offB CONTRACTORS GROUP LLCConcrete
1 project · most recent 05/06/2025
Earthwork
FiledStatusContractorScope
05/06/2025Signed-offB CONTRACTORS GROUP LLCEarthwork
▾Field Inspections (DOB CAP) — 9
DateTypeResultReport
06/09/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
06/04/2025Certified Sprinkler (SP) - Booster Pump TestCertifiedView ↗
06/04/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
05/29/2025Pass-Final CND-Occupancy InspectionPassView ↗
05/29/2025Pass-Final PL - Up to 9 Requested FloorsPassView ↗
02/13/2025Pass-Final PL - Up to 9 Requested FloorsPassView ↗
01/16/2025Fail-Final CND-Occupancy InspectionFailView ↗
12/06/2024Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
11/21/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 74
DateRequirementInspectorRole
05/13/2025HVAC-R and service water heating equipmentPaul Raymondenergy_progress
05/13/2025Fire-Resistant Penetrations and JointsPaul Raymondspecial
05/13/2025Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationPaul Raymondspecial
05/13/2025HVAC-R and service water piping design and insulationPaul Raymondenergy_progress
05/13/2025HVAC-R and service water heating system controlsPaul Raymondenergy_progress
05/13/2025Maintenance informationPaul Raymondenergy_progress
05/01/2025Fire-Resistant Penetrations and JointsPaul Raymondspecial
05/01/2025Sprinkler SystemsPaul Raymondspecial
05/01/2025Post-installed AnchorsPaul Raymondspecial
04/29/2025Air barrier continuity plan testingPaul Raymondenergy_progress
04/29/2025Protection of exposed foundation insulationPaul Raymondenergy_progress
04/29/2025Electrical motors and elevatorsPaul Raymondenergy_progress
04/29/2025Fire-Resistant Penetrations and JointsPaul Raymondspecial
04/29/2025Fire-Resistance Rated ConstructionPaul Raymondprogress
04/29/2025Energy Code Compliance InspectionsPaul Raymondprogress
04/29/2025Fenestration areasPaul Raymondenergy_progress
04/29/2025Maintenance informationPaul Raymondenergy_progress
04/29/2025Exterior lighting powerPaul Raymondenergy_progress
04/29/2025Air barrier - visual inspectionPaul Raymondenergy_progress
04/29/2025MeteringPaul Raymondenergy_progress
04/29/2025Insulation placement and R valuesPaul Raymondenergy_progress
04/29/2025Exterior Insulation and Finish Systems (EIFS)Paul Raymondspecial
04/29/2025Lighting in dwelling unitsPaul Raymondenergy_progress
04/29/2025Interior lighting powerPaul Raymondenergy_progress
04/29/2025Lighting controlsPaul Raymondenergy_progress
Latest 25 of 74.
▾Documents — 201 on file (BIS + DOB NOW)
▸Plans & Drawings25
▸DOB NOWPlans/Sketch25
09/06/2026M01113596-I1Request digital key ↗
08/26/2026M01105740-I1Request digital key ↗
08/25/2026M01148144-P1Request digital key ↗
Showing 3 of 25 on file for this type
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
11/04/2024141026459Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
11/04/2024141026459Open ↗
▸Zoning, Tax Lot & Property Records5
▸DOB NOWZD1: DOB Zoning Diagram2
08/13/2026M01039403-I1Open ↗
08/13/2026M01039403-P1Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/13/2026M01039403-I1Open ↗
08/13/2026M01039403-P1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026M01039403-I1Open ↗
▸Seals & Professional Certifications101
▸DOB NOWProgress Inspector Seal & Signature42
09/01/2026M01039403-S2Open ↗
09/01/2026M01039403-S2Open ↗
08/25/2026M01039403-P1Open ↗
Showing 3 of 42 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature32
09/01/2026M01039403-S2Open ↗
08/28/2026M01039403-S6Open ↗
08/28/2026M01039403-S6Open ↗
Showing 3 of 32 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature25
09/06/2026M01113596-I1Open ↗
08/26/2026M01105740-I1Open ↗
08/25/2026M01148144-I1Open ↗
Showing 3 of 25 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
10/30/2024141026459Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
10/30/2024141026459Open ↗
▸Trade Schedules & Equipment2
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)2
08/13/2026M01039403-P1Open ↗
08/13/2026M01039403-I1Open ↗
▸Safety & Tenant Protection10
▸DOB NOWStreet Tree Checklist2
08/13/2026M01039403-I1Open ↗
08/13/2026M01039403-P1Open ↗
▸DOB NOWHPD-2: Clinton Special District Anti-Harassment Checklist2
08/13/2026M01328606-I1Open ↗
08/13/2026M01039403-I1Open ↗
▸BISSTREET TREES: RECEIPT OF STREET TREES SITE PLAN1
02/10/2025141026459Open ↗
▸BISBPP: STREET TREES SITE PLAN1
02/10/2025141026459Open ↗
▸BISSTREET TREE CHECKLIST1
11/04/2024141026459Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026M01039403-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/13/2026M01039403-I1Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026M01039403-I1Open ↗
▸Environmental & Asbestos35
▸DOB NOWOER: Notice to Proceed21
08/13/2026M01039403-I1Open ↗
08/13/2026M01039403-P1Open ↗
08/13/2026M01039403-P2Open ↗
Showing 3 of 21 on file for this type
▸DOB NOWOER: Notice of Satisfaction12
08/13/2026M01039403-I1Open ↗
08/13/2026M01039403-I1Open ↗
08/13/2026M01039403-S2Open ↗
Showing 3 of 12 on file for this type
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE OF SATISFACTION1
09/10/2025141026459Open ↗
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE TO PROCEED1
11/06/2024141026459Open ↗
▸Inspections & Test Reports6
▸DOB NOWSOIL REPORT4
08/13/2026M01039403-S1Open ↗
08/13/2026M01039403-P3Open ↗
08/13/2026M01039403-S7Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWTR4 Test Report and Plot Diagram2
08/13/2026M01039403-S1Open ↗
08/13/2026M01039403-S7Open ↗
▸Filing & Intake Forms4
▸BISADDITIONAL INFORMATION2
10/30/2024141026459Open ↗
10/30/2024141026459Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
10/30/2024141026459Open ↗
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
11/04/2024141026459Open ↗
▸Other Documents11
▸DOB NOWEvaluation of Adjacent Building Report (BC 1817.3)2
08/13/2026M01039403-P3Open ↗
08/13/2026M01039403-S7Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026M01039403-I1Open ↗
08/13/2026M01039403-P1Open ↗
▸DOB NOWAdjoining Owners Notification2
08/13/2026M01039403-S1Open ↗
08/13/2026M01039403-S2Open ↗
▸DOB NOWSite Survey: Initial2
08/13/2026M01039403-P1Open ↗
08/13/2026M01039403-I1Open ↗
▸DOB NOWProperty Ownership Certification2
08/23/2026M01039403-P1Open ↗
08/23/2026M01039403-I1Open ↗
▸DOB NOWFinal Survey1
08/13/2026M01039403-I1Open ↗