| Owner | Filings | Most Recent |
|---|---|---|
| ZG 2ND PLACE | 30 | 07/08/2026 |
| TUMEN | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/04/2025 | $2.9M | — | — → — | $611/sf building |
| 01/31/2019 | $2.0M | — | — → — | $439/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| ERIC SAFYAN ARCHITECT PC | 11 | 10/22/2025 |
| CPENGINEERING PC | 5 | 12/15/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| JOSEPH FELLNER | 11 | 03/21/2026 |
| CASA GROUP | 10 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| INNOVATIVE VENTURES TEAM | General Contractor | 7 | 07/08/2026 |
| WCK ELECTRIC CORP. | Electrical | 2 | 03/22/2026 |
| LIBERTY FABRICATION INC | Electrical | 1 | 03/21/2026 |
| K.M.D MECHANICAL 1443 LLC | Fire Protection | 1 | 07/08/2026 |
| A&H EXPRESS PLBG&HTG CORP | Plumbing | 1 | 07/08/2026 |
| BALZOFIORE, F | Electrical | 1 | 03/21/2026 |
| K.M.D MECHANICAL 1443 LLC | Plumbing | 1 | 07/08/2026 |
| KUWAILID, MOHAMED | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ERIC SAFYAN ARCHITECTPC | 3248 | 8 | 10/22/2025 |
| PSI AGENCY INC. | 254 | 6 | 12/15/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | K.M.D MECHANICAL 1443 LLC | 02/25/2025 |
| DOB NOW | General Construction | Permit Issued | INNOVATIVE VENTURES TEAM | 11/26/2024 |
| DOB NOW | Mechanical Systems | Signed-off | INNOVATIVE VENTURES TEAM | 08/06/2024 |
| DOB NOW | Plumbing | Signed-off | A&H EXPRESS PLBG&HTG CORP | 04/26/2024 |
| DOB NOW | Sprinklers | Signed-off | K.M.D MECHANICAL 1443 LLC | 03/06/2024 |
| DOB NOW | General Construction | Permit Issued | INNOVATIVE VENTURES TEAM | 10/18/2023 |
| BIS | OT | ISSUED | TUMEN, INC | 06/26/2020 |
| BIS | OT | ISSUED | TUMEN, INC | 03/27/2020 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 10/22/2025 | Permit Issued | INNOVATIVE VENTURES TEAM | Heating and Air Conditioning Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/22/2025 | Signed-off | A&H EXPRESS PLBG&HTG CORP | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/05/2025 | Complete | WCK ELECTRIC CORP. | General Wiring |
| 11/10/2025 | Complete | WCK ELECTRIC CORP. | General Wiring |
| 09/22/2025 | Complete | WCK ELECTRIC CORP. | General Wiring |
| 09/22/2025 | Complete | WCK ELECTRIC CORP. | General Wiring |
| 08/12/2025 | Complete | WCK ELECTRIC CORP. | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/20/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/08/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/30/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/24/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/13/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/15/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/12/2025 | Certified Sprinkler (PL)-Sprinkler-Hydro | Certified | View ↗ |
| 05/12/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/07/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/06/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/02/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/22/2025 | Fenestration areas | Eric Safyan | energy_progress |
| 10/22/2025 | Fenestration and door U-factor and product ratings | Eric Safyan | energy_progress |
| 10/22/2025 | Metering | Eric Safyan | energy_progress |
| 10/22/2025 | Air barrier - visual inspection | Eric Safyan | energy_progress |
| 10/22/2025 | Fenestration air leakage | Eric Safyan | energy_progress |
| 10/22/2025 | Insulation placement and R values | Eric Safyan | energy_progress |
| 10/22/2025 | Lighting in dwelling units | Eric Safyan | energy_progress |
| 10/22/2025 | Fire-Resistant Penetrations and Joints | Eric Safyan | special |
| 10/22/2025 | Energy Code Compliance Inspections | Eric Safyan | progress |
| 10/22/2025 | Fire-Resistance Rated Construction | Eric Safyan | progress |
| 04/28/2025 | HVAC-R and service water piping design and insulation | Eric Safyan | energy_progress |
| 04/28/2025 | Maintenance information | Eric Safyan | energy_progress |
| 04/28/2025 | HVAC-R and service water heating system controls | Eric Safyan | energy_progress |
| 04/28/2025 | Final | Eric Safyan | progress |
| 04/28/2025 | Energy Code Compliance Inspections | Eric Safyan | progress |
| 04/28/2025 | Mechanical Systems | Eric Safyan | special |
| 04/28/2025 | HVAC-R and service water heating equipment | Eric Safyan | energy_progress |
| 03/27/2025 | Maintenance information | Eric Safyan | energy_progress |
| 03/27/2025 | Fire-Resistant Penetrations and Joints | Eric Safyan | special |
| 03/27/2025 | Fenestration and door U-factor and product ratings | Eric Safyan | energy_progress |
| 03/27/2025 | Air barrier - visual inspection | Eric Safyan | energy_progress |
| 03/27/2025 | Lighting in dwelling units | Eric Safyan | energy_progress |
| 03/27/2025 | Insulation placement and R values | Eric Safyan | energy_progress |
| 03/27/2025 | Metering | Eric Safyan | energy_progress |
| 03/27/2025 | Fenestration areas | Eric Safyan | energy_progress |