← Back
Two stories - detached, small or mid-size
56-12 135 STREET
QUEENS · Queensboro Hill · BIN 4115273
💬 Discuss this project
1920Year Built
2Stories
A1Building Class
R4-1Zoning
1,636 sfGross Floor Area
1Units
0 Open Violations
Two stories - detached, small or mid-size · 4,000 sf lot · 0.41 FAR built · Flood zone X
Locations of Work
Architecture
Cellar1p · 1 filing · 15 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
CELTIC WAY CONSULTING LLC708/22/2026
DOWN TO EARTH ENGINEERING204/02/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
FULIN CONSTRUCTION NYGeneral Contractor108/14/2026
Building Lifecycle
All (77)Filed (9)Permit Issued (2)Signed Off (1)Violation (11)Objection (24)Special Inspection (30)
08/22/2026
Filed — New Building
INSTALL 10' DROP CURB WITH 1'-6" SPLAYS BOTH SIDE
Q01416679-S6
08/22/2026
Objection resolved — Resolved
08/22/2026
Objection resolved — Resolved
08/22/2026
Objection resolved — Resolved
08/22/2026
Objection resolved — Resolved
08/22/2026
Objection resolved — Resolved
08/22/2026
Objection resolved — Resolved
08/22/2026
Objection resolved — Resolved
08/22/2026
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
08/19/2026
Filed — New Building
INSTALL 10' DROP CURB WITH 1'-6" SPLAYS BOTH SIDE
Q01416679-S4
08/19/2026
Objection resolved — Resolved
08/19/2026
Objection resolved — Resolved
08/13/2026
Permit issued — Construction Fence
Q01416682-I1-FN
07/24/2026
Objection raised — Structural
07/24/2026
Objection raised — Other
07/24/2026
Objection raised — Scope
07/24/2026
Objection raised — Structural
07/24/2026
Objection raised — Structural
07/24/2026
Objection raised — Other
07/24/2026
Objection raised — Structural
07/24/2026
Objection raised — Other
07/24/2026
Objection resolved — Addressed
07/17/2026
Objection resolved — Addressed
07/17/2026
Objection resolved — Addressed
07/09/2026
Objection raised — Other
06/28/2026
Objection raised — Other
06/26/2026
Objection raised — Other
06/26/2026
Objection raised — Other
06/18/2026
Filed — New Building
INSTALL 10' DROP CURB WITH 1'-6" SPLAYS BOTH SIDE
Q01416679-S1
06/18/2026
Filed — New Building
INSTALL 10' DROP CURB WITH 1'-6" SPLAYS BOTH SIDE
Q01416679-S3
06/18/2026
Filed — Alteration
Q01416682-I1
06/18/2026
Filed — New Building
INSTALL 10' DROP CURB WITH 1'-6" SPLAYS BOTH SIDE
Q01416679-S5
06/18/2026
Filed — New Building
INSTALL 10' DROP CURB WITH 1'-6" SPLAYS BOTH SIDE
Q01416679-I1
06/18/2026
Special inspection requirement — Sprinkler Systems
06/14/2026
Special inspection requirement — Heating Systems
06/14/2026
Special inspection requirement — Structural Steel - High Strength Bolting
06/14/2026
Special inspection requirement — Structural Steel - Welding
06/14/2026
Special inspection requirement — Subgrade Inspections
06/14/2026
Special inspection requirement — Mechanical Systems
06/14/2026
Special inspection requirement — Masonry
06/14/2026
Special inspection requirement — Structural Steel - Details
06/14/2026
Special inspection requirement — Energy Code Compliance Inspections
06/14/2026
Special inspection requirement — Fire-Resistance Rated Construction
06/14/2026
Special inspection requirement — Final
06/14/2026
Special inspection requirement — Footing and Foundation
06/14/2026
Special inspection requirement — HVAC-R and service water heating system controls
06/14/2026
Special inspection requirement — Maintenance information
06/14/2026
Special inspection requirement — Fenestration air leakage
06/14/2026
Special inspection requirement — Concrete - Cast-In-Place
06/14/2026
Special inspection requirement — Metering
06/14/2026
Special inspection requirement — Insulation placement and R values
06/14/2026
Special inspection requirement — Duct leakage testing, insulation and design
06/14/2026
Special inspection requirement — Air barrier — testing
06/14/2026
Special inspection requirement — Permanent certificate
06/14/2026
Special inspection requirement — Air barrier - visual inspection
06/14/2026
Special inspection requirement — Ventilation and air distribution system
06/14/2026
Special inspection requirement — HVAC-R and service water heating equipment
06/14/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
06/14/2026
Special inspection requirement — Fenestration areas
06/14/2026
Special inspection requirement — Lighting controls
Latest 60 of 77 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWConstruction FencePermit IssuedFULIN CONSTRUCTION NY INC08/13/2026
DOB NOWGeneral ConstructionSigned-offNot Applicable03/25/2026
BISOTISSUEDA&A BUILDING CONSULTANTS05/18/2015
BISOTISSUEDA&A BUILDING CONSULTANTS01/29/2015
1 project · most recent 08/22/2026
Storm Water/Sanitary
FiledStatusContractorScope
08/22/2026——Storm, Water/Sanitary
1 project · most recent 08/22/2026
FiledStatusContractorScope
08/22/2026——1 scope_items
▾Special Inspection Requirements (DOB NOW) — 34
DateRequirementInspectorRole
08/22/2026Subsurface Investigations (Borings/Test Pits)—special
06/18/2026Sprinkler Systems—special
06/14/2026Heating Systems—special
06/14/2026Structural Steel - High Strength Bolting—special
06/14/2026Structural Steel - Welding—special
06/14/2026Subgrade Inspections—special
06/14/2026Mechanical Systems—special
06/14/2026Masonry—special
06/14/2026Structural Steel - Details—special
06/14/2026Energy Code Compliance Inspections—progress
06/14/2026Fire-Resistance Rated Construction—progress
06/14/2026Final—progress
06/14/2026Footing and Foundation—progress
06/14/2026HVAC-R and service water heating system controls—energy_progress
06/14/2026Maintenance information—energy_progress
06/14/2026Fenestration air leakage—energy_progress
06/14/2026Concrete - Cast-In-Place—special
06/14/2026Metering—energy_progress
06/14/2026Insulation placement and R values—energy_progress
06/14/2026Duct leakage testing, insulation and design—energy_progress
06/14/2026Air barrier — testing —energy_progress
06/14/2026Permanent certificate—energy_progress
06/14/2026Air barrier - visual inspection—energy_progress
06/14/2026Ventilation and air distribution system—energy_progress
06/14/2026HVAC-R and service water heating equipment—energy_progress
Latest 25 of 34.
▾Documents — 51 on file (BIS + DOB NOW)
▸Plans & Drawings8
▸DOB NOWPlans/Sketch8
08/17/2026Q01278903-P1Request digital key ↗
08/17/2026Q01278903-I1Request digital key ↗
08/16/2026Q01416682-I1Request digital key ↗
Showing 3 of 8 on file for this type
▸Applications & Permits4
▸BISPLAN / WORK APPROVAL APPLICATION2
05/14/2015440219700Open ↗
02/05/2015421077630Open ↗
▸BISWORK PERMIT APPLICATION2
05/14/2015440219700Open ↗
02/06/2015421077630Open ↗
▸Zoning, Tax Lot & Property Records3
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/15/2026Q01416679-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)1
08/15/2026Q01416679-I1Open ↗
▸DOB NOWZD1: DOB Zoning Diagram1
08/15/2026Q01416679-I1Open ↗
▸Seals & Professional Certifications17
▸DOB NOWDPL-1: Design Professional Seal & Signature8
08/17/2026Q01278903-I1Open ↗
08/17/2026Q01278903-P1Open ↗
08/16/2026Q01416682-I1Open ↗
Showing 3 of 8 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT2
05/14/2015440219700Open ↗
02/05/2015421077630Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
12/29/2015440219700Open ↗
02/05/2015421077630Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/24/2026Q01278903-I1Open ↗
08/24/2026Q01278903-P1Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
02/05/2015421077630Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
05/14/2015440219700Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
05/14/2015440219700Open ↗
▸Safety & Tenant Protection1
▸DOB NOWStreet Tree Checklist1
08/15/2026Q01416679-I1Open ↗
▸Environmental & Asbestos2
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)1
02/06/2015421077630Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
05/14/2015440219700Open ↗
▸Energy Compliance5
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS2
12/29/2015440219700Open ↗
02/05/2015421077630Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
05/14/2015440219700Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
12/29/2015440219700Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
05/14/2015440219700Open ↗
▸Approvals, Objections & Sign-offs3
▸BISLETTERS - SUPPORTING DOCUMENTATION2
12/29/2015440219700Open ↗
12/29/2015440219700Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
12/29/2015440219700Open ↗
▸Cost, Insurance & Ownership3
▸BISCOST AFFIDAVIT2
12/29/2015440219700Open ↗
02/05/2015421077630Open ↗
▸BISCIVIL PENALTY AFFADAVIT/REQUEST1
05/18/2015440219700Open ↗
▸Filing & Intake Forms2
▸BISEFILING COVER SHEET1
02/05/2015421077630Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
05/14/2015440219700Open ↗
▸Other Documents3
▸DOB NOWProperty Ownership Certification1
08/15/2026Q01416679-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/15/2026Q01416679-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/15/2026Q01416679-I1Open ↗