| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 06/24/2021 | $1.1M | — | — → — | $469/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| Mei Architect | 5 | 03/13/2023 |
| Mehdi Ghazi, P.E | 1 | 03/13/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| Ibuild Consulting | 10 | 03/21/2026 |
| Mei Architect | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| David Constructing NY | General Contractor | 3 | 03/21/2026 |
| L&L Construction Development | General Contractor | 3 | 03/21/2026 |
| David Constructing NY | Scaffold | 1 | 07/08/2026 |
| John Fitzgerald Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Mehdi Ghazi, P.E | 7129 | 4 | 03/13/2023 |
| Triangle Inspection & Tes | 7495 | 2 | 03/06/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | L&L Construction Development | 03/21/2023 |
| DOB NOW | Plumbing | Signed-off | John Fitzgerald Plumbing & Heating | 06/28/2022 |
| DOB NOW | Structural | Permit Issued | David Constructing NY | 03/18/2022 |
| DOB NOW | Construction Fence | Signed-off | David Constructing NY | 03/09/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 03/13/2023 | Permit Issued | David Constructing NY | Heating Systems | Heating Navien NCB-150E 120,000 BTU · Boiler ×3 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/05/2022 | Complete | AL-Lectric Elect'l Contracting | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/13/2023 | Permit Issued | David Constructing NY | Steel, Concrete, Wood |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/15/2023 | HVAC-R and service water heating system controls | MEHDI GHAZI | energy_progress |
| 03/15/2023 | Insulation placement and R values | MEHDI GHAZI | energy_progress |
| 03/15/2023 | Shutoff dampers | MEHDI GHAZI | energy_progress |
| 03/15/2023 | HVAC-R and service water heating equipment | MEHDI GHAZI | energy_progress |
| 03/15/2023 | Fenestration and door U-factor and product ratings | MEHDI GHAZI | energy_progress |
| 03/15/2023 | Maintenance information | MEHDI GHAZI | energy_progress |
| 03/15/2023 | Fenestration areas | MEHDI GHAZI | energy_progress |
| 03/15/2023 | Mechanical Systems | MEHDI GHAZI | special |
| 03/15/2023 | Structural Stability – Alterations of existing buildings | MEHDI GHAZI | special |
| 03/15/2023 | Heating Systems | MEHDI GHAZI | special |
| 03/15/2023 | Fire-Resistant Penetrations and Joints | MEHDI GHAZI | special |
| 03/15/2023 | Excavations - Sheeting, Shoring, and Bracing | MEHDI GHAZI | special |
| 03/15/2023 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | MEHDI GHAZI | special |
| 03/15/2023 | Structural Steel - Welding | MEHDI GHAZI | special |
| 03/15/2023 | Structural Steel - High Strength Bolting | MEHDI GHAZI | special |
| 03/15/2023 | Subgrade Inspections | MEHDI GHAZI | special |
| 03/15/2023 | Masonry | MEHDI GHAZI | special |
| 03/15/2023 | Structural Steel - Details | MEHDI GHAZI | special |
| 03/15/2023 | Subsurface Investigations (Borings/Test Pits) | Rajasekhar Sakhamuri | special |
| 03/15/2023 | Concrete - Cast-In-Place | MEHDI GHAZI | special |
| 03/15/2023 | Fire-Resistance Rated Construction | MEHDI GHAZI | progress |
| 03/15/2023 | Energy Code Compliance Inspections | MEHDI GHAZI | progress |
| 03/15/2023 | Final | MEHDI GHAZI | progress |
| 03/15/2023 | Footing and Foundation | MEHDI GHAZI | progress |
| 03/15/2023 | Structural Wood Frame | MEHDI GHAZI | progress |