Four families
56 JORALEMON STREET
BROOKLYN · Brooklyn Heights · BIN 3002326
💬 Discuss this project
1849Year Built
3Stories
C3Building Class
R6Zoning
3,300 sfGross Floor Area
4Units
Rent Stabilized11 Open Violations ▸
Four families · 1,497 sf lot · 2.2 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire Protection
Permit Issued — active, not yet Signed-off
RoofUnder Construction2p · 1 filing · 20 docs
Floor 3Under Construction19p · 1 filing · 20 docs
Floor 2Under Construction17p · 1 filing · 20 docs
Floor 1Under Construction22p · 1 filing · 20 docs
CellarUnder Construction18p · 1 filing · 20 docs
BasementUnder Construction18p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
A MALEK CONTRACTING103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
10/15/2024$4.0M—Private party → Private party$1,212/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
E4P CONSULTING ENGINEERING PLLC605/12/2026
JIM BROWNING, AIA207/30/2025
STRUCTURAL ENGINEERING INTEGRATED107/30/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
BIG ORANGE EXPEDITING1403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ANDREJ RINKOVSKYGeneral Contractor507/08/2026
AMN FIRE CORPFire Protection107/08/2026
QUALITY CONTROL MECH LLCGeneral Contractor104/09/2026
A.M.N. CORPORATIONPlumbing107/04/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HT ENGINEERING, PLLC6274805/12/2026
STRUCT. ENGINEERING INTEG4174107/30/2025
Building Lifecycle
All (110)Filed (9)Permit Issued (7)Violation (31)Inspection (10)Objection (23)Special Inspection (30)
07/07/2026
Special inspection requirement — Interior lighting power
07/07/2026
Special inspection requirement — Lighting controls
07/01/2026
Special inspection requirement — Lighting in dwelling units
06/11/2026
Objection raised — Scope
06/07/2026
Special inspection requirement — Maintenance information
06/07/2026
Special inspection requirement — Permanent certificate
05/28/2026
Special inspection requirement — Sprinkler Systems
HENRY TORRES
05/28/2026
Special inspection requirement — HVAC-R and service water heating equipment
HENRY TORRES
05/28/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
HENRY TORRES
05/28/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
HENRY TORRES
05/28/2026
Special inspection requirement — HVAC-R and service water heating system controls
HENRY TORRES
05/28/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
HENRY TORRES
05/28/2026
Special inspection requirement — Maintenance information
HENRY TORRES
05/12/2026
Filed — Alteration CO
INSTALLATION OF HVAC SYSTEM AND ENERGY RECOVERY VENTILATION SYSTEM AS PER PLANS ATTACHED HEREWITH, NO CHANGE IN USE, EGRESS AND OCCUPANCY.
B01166507-P4
05/12/2026
Filed — Alteration CO
INSTALLATION OF HVAC SYSTEM AND ENERGY RECOVERY VENTILATION SYSTEM AS PER PLANS ATTACHED HEREWITH, NO CHANGE IN USE, EGRESS AND OCCUPANCY.
B01166507-P3
05/11/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
HENRY TORRES
05/11/2026
Special inspection requirement — Sprinkler Systems
HENRY TORRES
05/05/2026
Violation issued (HPD, open)
A
03/17/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
03/10/2026
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
03/05/2026
Filed — Alteration CO
INSTALLATION OF HVAC SYSTEM AND ENERGY RECOVERY VENTILATION SYSTEM AS PER PLANS ATTACHED HEREWITH, NO CHANGE IN USE, EGRESS AND OCCUPANCY.
B01166507-P2
02/18/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
HENRY TORRES
02/18/2026
Special inspection requirement — Sprinkler Systems
HENRY TORRES
01/22/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/16/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
12/01/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
11/28/2025
Permit issued — Mechanical Systems
B01166507-S1-MS
11/18/2025
Violation issued (HPD, open)
I
11/14/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
11/14/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
11/08/2025
Special inspection requirement — Air barrier - visual inspection
11/06/2025
Permit issued — Sprinklers
B01166507-S3-EW-SP
11/05/2025
Permit issued — Structural
B01166507-S4-ST
10/31/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
10/31/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
10/31/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
10/29/2025
Permit issued — General Construction
B01166507-I1-GC
10/27/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
09/12/2025
Permit issued — General Construction
B01166507-I1-GC
09/09/2025
Objection resolved — Resolved
08/28/2025
Objection resolved — Addressed
08/26/2025
Special inspection requirement — Fenestration air leakage
08/20/2025
Objection resolved — Addressed
08/19/2025
Permit issued — Plumbing
B01166507-S2-PL
08/08/2025
Objection resolved — Addressed
08/07/2025
Objection raised — Structural
08/07/2025
Objection raised — Structural
08/07/2025
Objection raised — Admin
08/06/2025
Objection raised — Scope
07/30/2025
Filed — Alteration CO
INSTALLATION OF HVAC SYSTEM AND ENERGY RECOVERY VENTILATION SYSTEM AS PER PLANS ATTACHED HEREWITH, NO CHANGE IN USE, EGRESS AND OCCUPANCY.
B01166507-S4
07/30/2025
Filed — Alteration CO
INSTALLATION OF HVAC SYSTEM AND ENERGY RECOVERY VENTILATION SYSTEM AS PER PLANS ATTACHED HEREWITH, NO CHANGE IN USE, EGRESS AND OCCUPANCY.
B01166507-P1
07/30/2025
Special inspection requirement — Structural Steel - Welding
Chris Yiu
07/30/2025
Special inspection requirement — Structural Steel - Details
Chris Yiu
07/30/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Chris Yiu
07/30/2025
Special inspection requirement — Post-installed Anchors
Chris Yiu
07/29/2025
Special inspection requirement — Insulation placement and R values
07/29/2025
Special inspection requirement — Fenestration areas
07/15/2025
Special inspection requirement — Final
Chris Yiu
07/10/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
HENRY TORRES
06/20/2025
Special inspection requirement — Duct leakage testing, insulation and design
HENRY TORRES
Latest 60 of 110 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedQUALITY CONTROL MECH LLC11/28/2025
DOB NOWSprinklersPermit IssuedAMN FIRE CORP11/06/2025
DOB NOWStructuralPermit IssuedANDREJ RINKOVSKY11/05/2025
DOB NOWGeneral ConstructionPermit IssuedANDREJ RINKOVSKY10/29/2025
DOB NOWGeneral ConstructionPermit IssuedANDREJ RINKOVSKY09/12/2025
DOB NOWPlumbingPermit IssuedA.M.N. CORPORATION08/19/2025
DOB NOWGeneral ConstructionPermit IssuedANDREJ RINKOVSKY05/28/2025
BISOTISSUEDDSENY BUILDING SERV. INC05/26/2005
1 project · most recent 05/12/2026
Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
05/12/2026Permit IssuedQUALITY CONTROL MECH LLCHeating and Air Conditioning Systems, Ventilation Systems
Heat / Cool
Mitsubishi Electric MXZ-SM48NAMHZ-U1 4 tons · Condensing Unit ×2
MXZ-SM60NAM2-U1 5 tons · Condensing Unit ×1
1 project · most recent 05/12/2026
Sprinkler System
FiledStatusContractorScope
05/12/2026Permit IssuedAMN FIRE CORPSprinkler System
1 project · most recent 05/12/2026
Gas Water/Sanitary
FiledStatusContractorScope
05/12/2026Permit IssuedK.O.S. PLUMBING&HEATING,IGas, Water/Sanitary
2 projects · most recent 09/16/2025
General Wiring
FiledStatusContractorScope
09/16/2025Permit IssuedA & R ELEC'L CONTR'G INC.General Wiring
06/06/2025Permit IssuedA & R ELEC'L CONTR'G INC.—
1 project · most recent 05/12/2026
Steel
FiledStatusContractorScope
05/12/2026Permit IssuedQUALITY CONTROL MECH LLCSteel
▾Field Inspections (DOB CAP) — 10
DateTypeResultReport
03/17/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
03/10/2026Fail-Final PL - Up to 3 Requested FloorsFailView ↗
01/22/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/16/2026Pass-Final CND-Occupancy InspectionPassView ↗
12/01/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/14/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
11/14/2025Pass-Final CND-Occupancy InspectionPassView ↗
10/31/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
10/31/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/31/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 37
DateRequirementInspectorRole
07/07/2026Interior lighting power—energy_progress
07/07/2026Lighting controls—energy_progress
07/01/2026Lighting in dwelling units—energy_progress
06/07/2026Maintenance information—energy_progress
06/07/2026Permanent certificate—energy_progress
05/28/2026Sprinkler SystemsHENRY TORRESspecial
05/28/2026HVAC-R and service water heating equipmentHENRY TORRESenergy_progress
05/28/2026Fire-Resistant Penetrations and JointsHENRY TORRESspecial
05/28/2026Fire-Resistant Penetrations and JointsHENRY TORRESspecial
05/28/2026HVAC-R and service water heating system controlsHENRY TORRESenergy_progress
05/28/2026HVAC-R and service water piping design and insulationHENRY TORRESenergy_progress
05/28/2026Maintenance informationHENRY TORRESenergy_progress
05/11/2026Fire-Resistant Penetrations and JointsHENRY TORRESspecial
05/11/2026Sprinkler SystemsHENRY TORRESspecial
02/18/2026Fire-Resistant Penetrations and JointsHENRY TORRESspecial
02/18/2026Sprinkler SystemsHENRY TORRESspecial
11/08/2025Air barrier - visual inspection—energy_progress
10/27/2025Fenestration and door U-factor and product ratings—energy_progress
08/26/2025Fenestration air leakage—energy_progress
07/30/2025Structural Steel - WeldingChris Yiuspecial
07/30/2025Structural Steel - DetailsChris Yiuspecial
07/30/2025Structural Stability – Alterations of existing buildingsChris Yiuspecial
07/30/2025Post-installed AnchorsChris Yiuspecial
07/29/2025Insulation placement and R values—energy_progress
07/29/2025Fenestration areas—energy_progress
Latest 25 of 37.
▾Documents — 55 on file (BIS + DOB NOW)
▸Plans & Drawings9
▸DOB NOWPlans/Sketch9
08/22/2026B01166507-S2Request digital key ↗
08/22/2026B01166507-S1Request digital key ↗
08/22/2026B01166507-P4Request digital key ↗
Showing 3 of 9 on file for this type
▸Applications & Permits6
▸DOB NOWLPC Approval/Permit6
08/22/2026B01166507-S1Open ↗
08/22/2026B01166507-P3Open ↗
08/15/2026B01166507-I1Open ↗
Showing 3 of 6 on file for this type
▸Zoning, Tax Lot & Property Records2
▸DOB NOWHouse Number Verification: TOPO Stamp2
08/15/2026B01166507-I1Open ↗
08/14/2026B01166507-P1Open ↗
▸Seals & Professional Certifications25
▸DOB NOWSpecial Inspector Seal & Signature11
09/27/2026B01166507-P4Open ↗
09/02/2026B01166507-S4Open ↗
09/02/2026B01166507-S4Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature9
08/22/2026B01166507-S2Open ↗
08/22/2026B01166507-I1Open ↗
08/22/2026B01166507-S1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWProgress Inspector Seal & Signature5
09/02/2026B01166507-S4Open ↗
08/31/2026B01166507-I1Open ↗
08/28/2026B01166507-S2Open ↗
Showing 3 of 5 on file for this type
▸Safety & Tenant Protection2
▸DOB NOWStreet Tree Checklist2
08/15/2026B01166507-I1Open ↗
08/14/2026B01166507-P1Open ↗
▸Environmental & Asbestos9
▸DOB NOWDEP ACP-5: Asbestos Assessment Report9
08/22/2026B01166507-S1Open ↗
08/22/2026B01166507-P4Open ↗
08/22/2026B01166507-P3Open ↗
Showing 3 of 9 on file for this type
▸Other Documents2
▸DOB NOWProperty Ownership Certification2
08/15/2026B01166507-I1Open ↗
08/14/2026B01166507-P1Open ↗