1999Year Built
6Stories
Z4Building Class
R10Zoning
27,400 sfGross Floor Area
1Units
LL97 Covered0 Open ViolationsFDNY Report ↗
Foreign government · Owner of record: AMERICAN-SCANDINAVIAN FOUNDATION · 4,710 sf lot · 5.82 FAR built · Flood zone X
Locations of Work
ArchitectureMechanical
Roof3p · 2 filings · 12 docs
Floor 61p · 1 filing · 6 docs
Floor 51p · 1 filing · 6 docs
Floor 41p · 1 filing · 6 docs
Floor 31p · 1 filing · 6 docs
Floor 21p · 1 filing · 6 docs
Floor 1
1 job · most recent 03/25/2026
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
03/25/2026——Heating and Air Conditioning Systems
Heat / Cool
Mitsubishi Electric MITSUBISHI - TPEFYP054MA1M0A 600,000 BTU · Vrf Indoor ×9
MISTUBISHI - TUHYE1203AMM0AN 10 tons · Condensing Unit ×5
MISTUBISHI - TPLFYP036EM1M0A 40,000 BTU · Vrf Indoor ×1
MITSUBISHI - TPEFYP036MA1M0A 40,000 BTU · Vrf Indoor ×1
MITSUBISHI - TPLFYP048EM1M0A 54,000 BTU · Fan Coil Indoor ×1
2 jobs · most recent 01/19/2024
FiledStatusContractorScope
01/19/2024Permit IssuedOMD ELECTRICAL CORP1 meters, 1 new_meters
01/03/2024CompleteAURORA ELECL CONTG INC—
Building Lifecycle
All (19)Filed (9)Permit Issued (5)Signed Off (5)
03/25/2026
Filed — Alteration
REPLACE EXISTING SPLIT AIR CONDITIONING SYSTEMS WITH VRF SYSTEMS AS PER PLANS. HUMIDIFICATION FOR 3RD FL. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
M01372027-I1
09/19/2025
Signed off — Alteration
Installation of a temporarily Material hoist per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M00993334-I1
11/13/2024
Signed off — Alteration
Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M00939249-I1
11/11/2024
Signed off — Alteration
Installation of suspended scaffold for facade inspection /repair
M00985929-I1
10/30/2024
Signed off — Alteration
Roof replacement and limited facade repairs as per drawings. No change in use, egress or occupancy is involved under this application.
M00822955-I1
09/24/2024
Signed off — Alteration
M00939246-I1
05/30/2024
Filed — Alteration
Engineered enclosure system per 3309.17
M01058683-I1
04/26/2024
Filed — Alteration
Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M00939249-P2
01/22/2024
Permit issued — Protection and Mechanical Methods
M00993334-I1-PMM
01/19/2024
Filed — Alteration
Installation of a temporarily Material hoist per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M00993334-I1
01/18/2024
Filed — Alteration
Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M00939249-P1
01/08/2024
Permit issued — Suspended Scaffold
M00985929-I1-SC
01/05/2024
Filed — Alteration
Installation of suspended scaffold for facade inspection /repair
M00985929-I1
09/29/2023
Permit issued — Supported Scaffold
M00939249-I1-SF
09/29/2023
Permit issued — Sidewalk Shed
M00939246-I1-SH
09/28/2023
Filed — Alteration
Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M00939249-I1
09/28/2023
Filed — Alteration
M00939246-I1
09/15/2023
Permit issued — General Construction
M00822955-I1-GC
03/14/2023
Filed — Alteration
Roof replacement and limited facade repairs as per drawings. No change in use, egress or occupancy is involved under this application.
M00822955-I1
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
QUANTUM DESIGN103/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Rigid Structural Design, LLC503/21/2026
SYNERGY BUILDING CONSULTANTS103/21/2026
BOYD CONSULTING203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
INTERSYSTEMS INSTAL S&SGeneral Contractor407/08/2026
M&A PROJECTS RESTORATION*General Contractor207/08/2026
AURORA ELECL CONTG INCElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
IP PROF. ENG. PC9709103/25/2026
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWProtection and Mechanical MethodsSigned-offM&A PROJECTS RESTORATION*01/22/2024
DOB NOWSuspended ScaffoldSigned-offM & A PROJECTS INC01/08/2024
DOB NOWSupported ScaffoldSigned-offINTERSYSTEMS INSTAL S&S09/29/2023
DOB NOWSidewalk ShedSigned-offINTERSYSTEMS INSTAL S&S09/29/2023
DOB NOWGeneral ConstructionSigned-offM&A PROJECTS RESTORATION*09/15/2023
BISEQISSUEDBREEZE NATIONAL INC02/08/1999
BISEQISSUEDBREEZE NATIONAL INC02/04/1999
BIS—ISSUEDBREEZE NATIONAL INC02/04/1999
BISEQISSUEDSPRING SCAFFOLDING INC01/22/1999
▾Special Inspection Requirements (DOB NOW) — 7
DateRequirementInspectorRole
03/13/2026Mechanical SystemsEric Nixonspecial
03/13/2026Energy Code Compliance InspectionsEric Nixonprogress
03/13/2026FinalEric Nixonprogress
05/29/2024Post-installed Anchors—special
02/02/2023FinalRobert Batesprogress
02/02/2023Insulation placement and R valuesRobert Batesenergy_progress
02/02/2023Air barrier - visual inspectionRobert Batesenergy_progress
▾Documents — 27 on file (BIS + DOB NOW)
▸Plans & Drawings9
▸DOB NOWPlans/Sketch9
08/31/2026M00822955-I1Request digital key ↗
08/29/2026M00939246-I1Request digital key ↗
08/28/2026M00985929-I1Request digital key ↗
Showing 3 of 9 on file for this type
▸Seals & Professional Certifications13
▸DOB NOWDPL-1: Design Professional Seal & Signature8
08/29/2026M00939246-I1Open ↗
08/28/2026M00939249-P2Open ↗
08/28/2026M00939249-P1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
09/01/2026M01372027-I1Open ↗
08/26/2026M00822955-I1Open ↗
08/26/2026M00822955-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature1
09/01/2026M01372027-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/15/2026M01372027-I1Open ↗
▸Approvals, Objections & Sign-offs2
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter2
08/13/2026M00822955-I1Open ↗
08/13/2026M00993334-I1Open ↗
▸Other Documents2
▸DOB NOWCalculations1
08/13/2026M00985929-I1Open ↗
▸DOB NOWManufacturer's Specifications1
08/13/2026M00985929-I1Open ↗