| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 01/06/2025 | Signed-off | BG CONSTRUCTION NY INC | Ventilation Systems | Ventilation Dayton 56jn93 4,000 CFM · Exhaust Fan ×1 |
| 12/18/2023 | Permit Issued | PIONEER GENERAL CONSTRUCT | Heating and Air Conditioning Systems | Heat / Cool Cooper & Hunter CH-24MASTWM-230VI 24,000 BTU · Split System ×1 CH-HPR24-230VO 24,000 BTU · Heat Pump Outdoor ×1 CHV-15WTU 15,400 BTU · Ptac ×1 CHV-18WTU 19,100 BTU · Ptac ×1 CHV6-36URBM 36,000 BTU · Vrf Outdoor ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/16/2025 | — | — | Gas, Water/Sanitary |
| 04/01/2025 | — | — | Water/Sanitary |
| 01/06/2025 | Permit Issued | ALL PRO PLBG & HTG INC | Water/Sanitary |
| 12/18/2023 | — | — | Water/Sanitary |
| 12/02/2022 | Permit Issued | ADVANCED P,MECH & SPR COR | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/21/2026 | Permit Issued | EMPIRE LIC ELECL CONTRS | General Wiring |
| 10/07/2025 | Permit Issued | SNB ELECTRICAL CONTNG COR | General Wiring |
| 07/31/2025 | Complete | AL-LECTRIC ELECT'L CONTRG | General Wiring |
| 07/11/2025 | Complete | E D ELECTRICAL INC | General Wiring |
| 07/07/2025 | Permit Issued | ACCURATE ELEC'L CORP. | General Wiring |
| 06/16/2025 | Permit Issued | ACCURATE ELEC'L CORP. | General Wiring |
| 05/31/2024 | Complete | LINA ELECTRIC, CORP | General Wiring |
| 01/20/2024 | Complete | TRIPLE D ELECTRIC INC | General Wiring |
| 03/08/2023 | Permit Issued | ANOTHER NYCER ELEC. CORP. | General Wiring |
| 05/12/2022 | Complete | KJK ELECTRIC INC | General Wiring |
| 05/02/2022 | Complete | AMSTERDAM ELECTRIC CORP | General Wiring |
| 05/03/2021 | Permit Issued | P.S. MARCATO ELEV. CO INC | — |
| 01/16/2019 | Complete | BALANCE ELEC CONT'G CORP. | General Wiring |
| 08/24/2018 | Complete | TOP SHELF ELECTRIC CORP | — |
| 08/01/2018 | Complete | GLENDALE ELECTL CONTNG IN | General Wiring, Lighting |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/15/2024 | Permit Issued | LAKE CONTRACTING LLC | 1 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/28/2026 | Permit Issued | CANIDO BASONAS CONST. COR | Suspended Scaffold (SC) |
| Owner | Filings | Most Recent |
|---|---|---|
| AKAM ASSOCIATES | 39 | 09/13/2026 |
| CANIDO BASONAS CONSTRUCTION | 6 | 07/08/2026 |
| 333 TENANTS CORP. | 9 | 03/22/2026 |
| ROUND M NYC INC | 9 | 03/22/2026 |
| MURRAY HILL MEWS OWNER'S CORP. | 131 | 03/22/2026 |
| NY INC BG CONSTRUCTION | 1 | 03/22/2026 |
| OWNER OF 560 3 AVE | 2 | 03/22/2026 |
| OWNER OF PREMISES 560 3 A | 1 | 03/22/2026 |
| THE OWNER OF | 1 | 03/22/2026 |
| OWNER OF VIA VIA RESTAURA | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| SUSTAINABLE DESIGN ENGINEERING PLLC | 2 | 12/12/2025 |
| INM ARCHITECTS PC | 2 | 10/16/2025 |
| GLICKMAN SCHLESINGER ARCHITECTS | 9 | 10/07/2025 |
| MAGO ARCHITECTURE, PLLC | 1 | 09/11/2025 |
| KITSU ARCHITECT PLLC | 1 | 06/17/2025 |
| DAVID JIMENEZ, RA | 2 | 04/01/2025 |
| AYALA ENGINEERING PC | 2 | 01/06/2025 |
| HAMANN ENGINEERING, PLLC | 3 | 09/21/2024 |
| HOWARD L ZIMMERMAN ARCH & ENG DPC | 1 | 08/15/2024 |
| CONCESSI ENGINEERING, P.C. | 2 | 12/18/2023 |
| MIRELLA BOSELLI ARCHITECT | 1 | 03/27/2023 |
| CONSTANT AND BROWN ENGINEERING DPC | 8 | 01/18/2023 |
| SI DESIGN | 2 | 12/02/2022 |
| KAREN BRENNER | 1 | 10/13/2022 |
| MATTHEW RUOPOLI, AIA | 1 | 02/05/2021 |
| ARCHITECTURE WORKSHOP PC | 1 | 11/09/2020 |
| BAILEYS ENGINEERING PC | 1 | 08/24/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| AYE CONSULTING GROUP | 16 | 03/21/2026 |
| BIG ORANGE EXPEDITING | 4 | 03/21/2026 |
| YOUBER DESIGN | 4 | 03/21/2026 |
| SUN | 2 | 03/21/2026 |
| JAM CONSULTANTS, INC. | 9 | 03/21/2026 |
| MP DESIGN AND CONSTRUCTION | 4 | 03/21/2026 |
| HLZAE | 1 | 03/21/2026 |
| NEXUS CONSULTING NYC, INC | 2 | 03/21/2026 |
| MUNICIPAL BUILDING CONSULTANTS | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| FREEDOM GS INC | General Contractor | 6 | 07/08/2026 |
| ROUND M NYC INC | General Contractor | 6 | 03/21/2026 |
| JBKS CONSTRUCTION LLC | General Contractor | 6 | 07/08/2026 |
| PIONEER GENERAL CONSTRUCT | General Contractor | 3 | 03/21/2026 |
| DA CONSTRUCTION INC | General Contractor | 3 | 03/21/2026 |
| BG CONSTRUCTION NY INC | General Contractor | 3 | 03/21/2026 |
| E D ELECTRICAL INC | Electrical | 2 | 03/22/2026 |
| ACCURATE MECHANICAL INC | Plumbing | 2 | 07/08/2026 |
| ANGELOS'S HOME IMPROVEMEN | General Contractor | 2 | 03/21/2026 |
| SPIRE SCAFFOLDING & HOIST | General Contractor | 2 | 07/08/2026 |
| BIG APPLE DESIGNS AND ENV | General Contractor | 1 | 04/09/2026 |
| CYC GENERAL CONTRACTING | General Contractor | 1 | 07/08/2026 |
| LAKE CONTRACTING LLC | General Contractor | 1 | 04/09/2026 |
| ADVANCED PLUMBING MECH | Plumbing | 1 | 07/08/2026 |
| ALL PRO PLBG & HTG INC | Plumbing | 1 | 06/28/2026 |
| AQUEDUCT MECHANICAL CORP | Plumbing | 1 | 07/08/2026 |
| ARK-POL PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| BUDGET PLBG & HTG LLC | Plumbing | 1 | 07/08/2026 |
| ROCK E SMALL PLBG&HTG INC | Plumbing | 1 | 07/08/2026 |
| BALANCE ELEC CONT'G CORP. | Electrical | 1 | 03/22/2026 |
| WASOFF PLBG & UTILITY CO | Plumbing | 1 | 07/08/2026 |
| BENJAMIN DREBIN | Electrical | 1 | 03/21/2026 |
| DUDLEY JAMAL | Electrical | 1 | 03/21/2026 |
| HAROLD MCGUIRE | Electrical | 1 | 03/21/2026 |
| HEMNAUTH, SUDESH | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| GEORGE J. XERAKIAS, PE | 1658 | 1 | 05/28/2026 |
| SUSTAINABLE DESIGN ENGINE | 1404 | 1 | 12/12/2025 |
| GLICKMAN SCHLESINGER ARCH | 6768 | 9 | 10/07/2025 |
| INTERNATIONAL GEOTEHCNICA | 1795 | 1 | 09/11/2025 |
| INM ARCHITECT, P.C. | 3351 | 1 | 06/19/2025 |
| CROSSCHECK INSPECTION SER | 544 | 1 | 05/02/2025 |
| OUTSOURCE SPECIAL INSPECT | 2827 | 2 | 04/01/2025 |
| A&B WORLD CONSULTING, INC | 5704 | 1 | 01/06/2025 |
| AYALA ENGINEERING P.C. | 9207 | 2 | 01/06/2025 |
| HAMANN ENGINEERING, PLLC | 4949 | 3 | 09/21/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Suspended Scaffold | Permit Issued | CANIDO BASONAS CONST. COR | 06/08/2026 |
| DOB NOW | Structural | Permit Issued | LAKE CONTRACTING LLC | 04/07/2026 |
| DOB NOW | Plumbing | Permit Issued | BUDGET PLBG & HTG LLC | 02/06/2026 |
| DOB NOW | General Construction | Permit Issued | BIG APPLE DESIGNS AND ENV | 02/05/2026 |
| DOB NOW | General Construction | Signed-off | JBKS CONSTRUCTION LLC | 11/26/2025 |
| DOB NOW | General Construction | Permit Issued | ROUND M NYC INC | 10/24/2025 |
| DOB NOW | General Construction | Signed-off | ABCAT ASSOCIATES INC | 07/09/2025 |
| DOB NOW | General Construction | Permit Issued | ROUND M NYC INC | 07/08/2025 |
| DOB NOW | Plumbing | Permit Issued | ALL PRO PLBG & HTG INC | 05/30/2025 |
| DOB NOW | General Construction | Signed-off | FREEDOM GS | 05/16/2025 |
| DOB NOW | General Construction | Signed-off | BG CONSTRUCTION NY INC | 01/21/2025 |
| DOB NOW | Plumbing | Signed-off | ANTHONY DISABATO | 11/13/2024 |
| DOB NOW | General Construction | Signed-off | FREEDOM GS | 11/08/2024 |
| DOB NOW | General Construction | Signed-off | FREEDOM GS | 10/29/2024 |
| DOB NOW | General Construction | Signed-off | JBKS CONSTRUCTION LLC | 10/21/2024 |
| DOB NOW | Plumbing | Signed-off | ARK-POL PLUMBING CORP | 09/26/2024 |
| DOB NOW | Plumbing | Signed-off | ANTHONY DISABATO | 08/27/2024 |
| DOB NOW | General Construction | Signed-off | FREEDOM GS | 08/14/2024 |
| DOB NOW | General Construction | Signed-off | JBKS CONSTRUCTION LLC | 04/26/2024 |
| DOB NOW | General Construction | Permit Issued | PIONEER GENERAL CONSTRUCT | 01/17/2024 |
| DOB NOW | Plumbing | Permit Issued | ADVANCED PLUMBING MECH | 12/14/2022 |
| DOB NOW | General Construction | Permit Issued | DA CONSTRUCTION INC | 11/30/2022 |
| DOB NOW | General Construction | Signed-off | JBKS CONSTRUCTION LLC | 11/03/2022 |
| DOB NOW | General Construction | Signed-off | FREEDOM GS | 08/18/2022 |
| DOB NOW | Plumbing | Signed-off | ROCK E SMALL PLBG&HTG INC | 07/12/2022 |
| DOB NOW | Plumbing | Signed-off | WASOFF PLBG & UTILITY CO | 12/17/2021 |
| DOB NOW | General Construction | Signed-off | CYC GENERAL CONTRACTING | 12/03/2021 |
| DOB NOW | General Construction | Signed-off | ANGELOSS HOME IMPROVEMEN | 03/15/2021 |
| DOB NOW | Plumbing | Signed-off | AQUEDUCT MECHANICAL CORP | 12/04/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | SPIRE SCAFFOLDING & HOIST | 04/18/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | SPIRE SCAFFOLDING & HOIST | 08/29/2018 |
| BIS | OT | ISSUED | EDDY'S GENERAL CONSTRUCT | 12/18/2020 |
| BIS | OT | ISSUED | JBKS CONSTRUCTION LLC | 02/25/2020 |
| BIS | OT | ISSUED | CANIDO BASONAS CONST SVC | 04/10/2019 |
| BIS | PL | ISSUED | TRUE NORTH MECHANICAL LLC | 03/20/2019 |
| BIS | OT | ISSUED | JBKS CONSTRUCTION LLC | 02/19/2019 |
| BIS | PL | ISSUED | ARK-POL PLUMBING CORP | 10/12/2018 |
| BIS | OT | ISSUED | CANIDO BASONAS CONST SVC | 09/24/2018 |
| BIS | PL | ISSUED | PREMIER FLOW PLBG AND HTG | 08/15/2018 |
| BIS | OT | ISSUED | S. ZEZULA RENOVATION INC | 07/30/2018 |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/21/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/13/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/22/2026 | Pass-Final PL - Underground | Pass | View ↗ |
| 04/28/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/22/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/02/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 02/26/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/27/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/07/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/23/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/11/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/18/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 06/18/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/16/2025 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 06/09/2025 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 03/07/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/20/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/11/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/25/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/14/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/09/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/03/2023 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 01/26/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/28/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/25/2022 | Pass-Final PL - More than 10 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/26/2026 | Post-installed Anchors | George Xerakias | special |
| 05/26/2026 | Post-installed anchors in masonry | George Xerakias | special |
| 05/26/2026 | Alternative Materials - OTCR Buildings Bulletin Number | George Xerakias | special |
| 10/08/2025 | Fire-Resistant Penetrations and Joints | Adam Glickman | special |
| 10/03/2025 | Fire-Resistant Penetrations and Joints | Adam Glickman | special |
| 08/08/2025 | Tenant Protection Plan Compliance | — | special |
| 08/05/2025 | Fire-Resistant Penetrations and Joints | Adam Glickman | special |
| 06/19/2025 | Tenant Protection Plan Compliance | Nikola Martinovic | special |
| 06/16/2025 | Fire-Resistant Penetrations and Joints | Nikola Martinovic | special |
| 06/16/2025 | Final | Nikola Martinovic | progress |
| 06/06/2025 | Final | Chia-Yi Huang | progress |
| 05/02/2025 | Tenant Protection Plan Compliance | EUGENE BIFULCO | special |
| 04/25/2025 | Energy Code Compliance Inspections | Lauren Schlesinger | progress |
| 04/25/2025 | Fire-Resistant Penetrations and Joints | Lauren Schlesinger | special |
| 04/25/2025 | Lighting in dwelling units | Lauren Schlesinger | energy_progress |
| 04/25/2025 | Lighting controls | Lauren Schlesinger | energy_progress |
| 04/25/2025 | Fire-Resistance Rated Construction | Lauren Schlesinger | progress |
| 04/25/2025 | Final | Lauren Schlesinger | progress |
| 03/26/2025 | Tenant Protection Plan Compliance | JONAR MADRIAGA | special |
| 03/26/2025 | Tenant Protection Plan Compliance | JONAR MADRIAGA | special |
| 01/27/2025 | Final | David Jimenez | progress |
| 01/27/2025 | Lighting controls | David Jimenez | energy_progress |
| 01/27/2025 | Interior lighting power | David Jimenez | energy_progress |
| 12/26/2024 | Fire-Resistant Penetrations and Joints | Pablo Ayala | special |
| 12/26/2024 | Tenant Protection Plan Compliance | Pablo Ayala | special |