1951Year Built
1Stories
K1Building Class
R4Zoning
6,129 sfGross Floor Area
6Units
0 Open Violations
One story retail building · Owner of record: SJLG RIVERDALE PROPERTIES LP · 10,000 sf lot · 0.61 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbing
Roof1p · 1 filing · 12 docs
Floor 14p · 4 filings · 20 docs
Cellar8p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
SJLG103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
COLOMBO ARCHITECTURAL STUDIO PC1108/20/2024
KDV DESIGNS ARCHITECTS LLC211/08/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
LLOYD NOEL BUILDING CONSULTANT103/21/2026
TBC & ASSOC.403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MONARCH PLUMB & HTG LLCPlumbing907/08/2026
ERLAND CONTRACTING, LLCGeneral Contractor807/08/2026
A&S SHEET METAL CORPGeneral Contractor303/21/2026
EVS ELECTRIC CORPElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
COLOMBO ARCHITECTURAL STU4930608/20/2024
SY ENGINEERING PLLC5149211/08/2021
Building Lifecycle
All (75)Filed (13)Permit Issued (9)Signed Off (6)Violation (9)Inspection (8)Special Inspection (30)
12/05/2025
Signed off — Alteration
APPLICATION FILED TO COMBINE AND RENOVATE EXISTING STORES. NO CHANGE IN USE, EGRESS AND OCCUPANCY.
X01097875-S1
11/14/2025
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/05/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
01/14/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
01/10/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
01/05/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
09/11/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
09/04/2024
Permit issued — Plumbing
X01097875-S1-PL
08/22/2024
Permit issued — General Construction
X01097875-I1-GC-CX
08/20/2024
Filed — Alteration
APPLICATION FILED TO COMBINE AND RENOVATE EXISTING STORES. NO CHANGE IN USE, EGRESS AND OCCUPANCY.
X01097875-S1
08/20/2024
Filed — Alteration
APPLICATION FILED TO COMBINE AND RENOVATE EXISTING STORES. NO CHANGE IN USE, EGRESS AND OCCUPANCY.
X01097875-I1
08/17/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Yahaira Volquez Colombo
08/17/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Yahaira Volquez Colombo
08/17/2024
Special inspection requirement — Mechanical Systems
Yahaira Volquez Colombo
08/17/2024
Special inspection requirement — Final
Yahaira Volquez Colombo
08/17/2024
Special inspection requirement — Interior lighting power
Yahaira Volquez Colombo
08/17/2024
Special inspection requirement — Lighting controls
Yahaira Volquez Colombo
08/17/2024
Special inspection requirement — HVAC-R and service water heating system controls
Yahaira Volquez Colombo
08/17/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
Yahaira Volquez Colombo
08/17/2024
Special inspection requirement — HVAC-R and service water heating equipment
Yahaira Volquez Colombo
06/20/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
09/27/2022
Signed off — Alteration
Installation of plumbing fixtures as per plans in connection with general construction application. No change in use, egress or occupancy.
X00576490-I1
09/27/2022
Signed off — Alteration
Installation of plumbing fixtures as per plans in connection with general construction application. No change in use, egress or occupancy.
X00576490-S1
02/10/2022
Special inspection requirement — Maintenance information
Yahaira Volquez Colombo
02/10/2022
Special inspection requirement — Lighting controls
Yahaira Volquez Colombo
02/10/2022
Special inspection requirement — Final
Yahaira Volquez Colombo
02/10/2022
Special inspection requirement — Interior lighting power
Yahaira Volquez Colombo
02/04/2022
Filed — Alteration
Installation of plumbing fixtures as per plans in connection with general construction application. No change in use, egress or occupancy.
X00576490-P3
02/02/2022
Special inspection requirement — Interior lighting power
Yahaira Volquez Colombo
02/02/2022
Special inspection requirement — Maintenance information
Yahaira Volquez Colombo
02/02/2022
Special inspection requirement — Lighting controls
Yahaira Volquez Colombo
02/02/2022
Special inspection requirement — Final
Yahaira Volquez Colombo
01/11/2022
Filed — Alteration
Installation of plumbing fixtures as per plans in connection with general construction application. No change in use, egress or occupancy.
X00576490-P2
01/04/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/03/2022
Special inspection requirement — Maintenance information
Yahaira Volquez Colombo
01/03/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
Yahaira Volquez Colombo
01/03/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Yahaira Volquez Colombo
01/03/2022
Special inspection requirement — HVAC-R and service water heating system controls
Yahaira Volquez Colombo
01/03/2022
Special inspection requirement — HVAC-R and service water heating equipment
Yahaira Volquez Colombo
11/30/2021
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
11/09/2021
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
11/08/2021
Filed — Alteration
INSTALLING NEW ROOFTOP HVAC UNIT AND ASSOCIATED DUCT WORK AT PROPOSED NEW RESTAURANT. NO OTHER WORK TO BE DONE. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
X00600741-S1
11/08/2021
Special inspection requirement — Energy Code Compliance Inspections
DAVIDSON CHRISTMAS
11/01/2021
Special inspection requirement — HVAC-R and service water heating equipment
SUNGBOM YI
11/01/2021
Special inspection requirement — Maintenance information
SUNGBOM YI
11/01/2021
Special inspection requirement — Final
DAVIDSON CHRISTMAS
11/01/2021
Special inspection requirement — Mechanical Systems
SUNGBOM YI
11/01/2021
Special inspection requirement — Duct leakage testing, insulation and design
SUNGBOM YI
10/29/2021
Filed — Alteration
Installation of plumbing fixtures as per plans in connection with general construction application. No change in use, egress or occupancy.
X00576490-P1
10/29/2021
Special inspection requirement — Maintenance information
Yahaira Volquez Colombo
10/29/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
Yahaira Volquez Colombo
10/19/2021
Signed off — Alteration
X00581466-I1
10/18/2021
Permit issued — General Construction
X00581466-I1-GC
10/18/2021
Permit issued — General Construction
X00576490-I1-GC
10/07/2021
Permit issued — Mechanical Systems
X00600741-I1-MS
09/29/2021
Filed — Alteration
INSTALLING NEW ROOFTOP HVAC UNIT AND ASSOCIATED DUCT WORK AT PROPOSED NEW RESTAURANT. NO OTHER WORK TO BE DONE. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
X00600741-I1
09/16/2021
Filed — Alteration
X00581466-I1
09/14/2021
Permit issued — Plumbing
X00576490-S1-PL
09/09/2021
Permit issued — General Construction
X00576490-I1-GC
09/08/2021
Filed — Alteration
Installation of plumbing fixtures as per plans in connection with general construction application. No change in use, egress or occupancy.
X00576490-S1
Latest 60 of 75 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offMONARCH PLUMB & HTG LLC09/04/2024
DOB NOWGeneral ConstructionPermit IssuedERLAND CONTRACTING08/22/2024
DOB NOWGeneral ConstructionSigned-offERLAND CONTRACTING10/18/2021
DOB NOWGeneral ConstructionSigned-offERLAND CONTRACTING10/18/2021
DOB NOWMechanical SystemsPermit IssuedA&S SHEET METAL CORP10/07/2021
DOB NOWPlumbingSigned-offMONARCH PLUMB & HTG LLC09/14/2021
DOB NOWGeneral ConstructionSigned-offERLAND CONTRACTING09/09/2021
DOB NOWPlumbingSigned-offMONARCH PLUMB & HTG LLC04/28/2021
DOB NOWGeneral ConstructionSigned-offERLAND CONTRACTING04/13/2021
BISPLISSUEDHARON PLUMBING & HEATING04/06/2005
BISMHISSUEDCOTTAM HEATING & AIR CONDIT.03/15/2005
BISPLISSUEDHARON PLUMBING & HEATING12/28/2004
BISOTISSUEDMETRO INTERIOR REMODELING CORP08/26/2003
BISFBISSUEDCOMBIND OIL CORP01/08/2002
BISSPISSUEDC.R.U. MECHAN & HEATIN IN08/28/2001
BISOTISSUEDJMW SERVICES INC04/23/1999
BIS—ISSUEDSERVICE SIGN ERECTORS, CO.11/24/1995
BIS—ISSUEDRGC ASSOCIATES06/09/1993
2 projects · most recent 08/20/2024
Heating and Air Conditioning Systems Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
08/20/2024Permit IssuedERLAND CONTRACTING, LLCHeating and Air Conditioning Systems
Heat / Cool
Trane 2TTB0036A1000AA (Existing to remain) 36,000 BTU · Condensing Unit ×1
11/08/2021Permit IssuedA&S SHEET METAL CORPAir Conditioning Systems, Ventilation Systems
Cooling
Daikin DBG090VH00001S 8 tons · Rooftop Unit ×2
Ventilation
Captiveaire NCA18FA 4,000 CFM · Kitchen Exhaust ×3
1 project · most recent 08/20/2024
Water/Sanitary
FiledStatusContractorScope
08/20/2024Signed-offMONARCH PLUMB & HTG LLCWater/Sanitary
2 projects · most recent 04/02/2024
General Wiring
FiledStatusContractorScope
04/02/2024CompleteEVS ELECTRIC CORPGeneral Wiring
05/13/2021CompleteEVS ELECTRIC CORPGeneral Wiring
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
02/05/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
01/14/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/10/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
01/05/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/11/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/04/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/30/2021Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/09/2021Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 39
DateRequirementInspectorRole
08/17/2024Fire-Resistant Penetrations and JointsYahaira Volquez Colombospecial
08/17/2024Fire-Resistant Penetrations and JointsYahaira Volquez Colombospecial
08/17/2024Mechanical SystemsYahaira Volquez Colombospecial
08/17/2024FinalYahaira Volquez Colomboprogress
08/17/2024Interior lighting powerYahaira Volquez Colomboenergy_progress
08/17/2024Lighting controlsYahaira Volquez Colomboenergy_progress
08/17/2024HVAC-R and service water heating system controlsYahaira Volquez Colomboenergy_progress
08/17/2024HVAC-R and service water piping design and insulationYahaira Volquez Colomboenergy_progress
08/17/2024HVAC-R and service water heating equipmentYahaira Volquez Colomboenergy_progress
02/10/2022Maintenance informationYahaira Volquez Colomboenergy_progress
02/10/2022Lighting controlsYahaira Volquez Colomboenergy_progress
02/10/2022FinalYahaira Volquez Colomboprogress
02/10/2022Interior lighting powerYahaira Volquez Colomboenergy_progress
02/02/2022Interior lighting powerYahaira Volquez Colomboenergy_progress
02/02/2022Maintenance informationYahaira Volquez Colomboenergy_progress
02/02/2022Lighting controlsYahaira Volquez Colomboenergy_progress
02/02/2022FinalYahaira Volquez Colomboprogress
01/03/2022Maintenance informationYahaira Volquez Colomboenergy_progress
01/03/2022HVAC-R and service water piping design and insulationYahaira Volquez Colomboenergy_progress
01/03/2022Fire-Resistant Penetrations and JointsYahaira Volquez Colombospecial
01/03/2022HVAC-R and service water heating system controlsYahaira Volquez Colomboenergy_progress
01/03/2022HVAC-R and service water heating equipmentYahaira Volquez Colomboenergy_progress
11/08/2021Energy Code Compliance InspectionsDAVIDSON CHRISTMASprogress
11/01/2021HVAC-R and service water heating equipmentSUNGBOM YIenergy_progress
11/01/2021Maintenance informationSUNGBOM YIenergy_progress
Latest 25 of 39.
▾Documents — 68 on file (BIS + DOB NOW)
▸Plans & Drawings13
▸DOB NOWPlans/Sketch13
08/25/2026X00495508-I1Request digital key ↗
08/25/2026X00495508-S1Request digital key ↗
08/25/2026X00495508-P1Request digital key ↗
Showing 3 of 13 on file for this type
▸Seals & Professional Certifications37
▸DOB NOWProgress Inspector Seal & Signature19
09/20/2026X01097875-I1Open ↗
09/20/2026X01097875-I1Open ↗
08/30/2026X00495508-S1Open ↗
Showing 3 of 19 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature13
08/25/2026X00495508-I1Open ↗
08/25/2026X00495508-S1Open ↗
08/25/2026X00495508-P1Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
09/20/2026X01097875-I1Open ↗
08/30/2026X00600741-S1Open ↗
08/25/2026X01097875-S1Open ↗
Showing 3 of 5 on file for this type
▸Environmental & Asbestos13
▸DOB NOWDEP ACP-5: Asbestos Assessment Report13
08/25/2026X00495508-I1Open ↗
08/25/2026X00495508-S1Open ↗
08/25/2026X00495508-P1Open ↗
Showing 3 of 13 on file for this type
▸Energy Compliance5
▸DOB NOWEN2: As Built Energy Analysis.5
08/13/2026X00576490-I1Open ↗
08/13/2026X00576490-S1Open ↗
08/13/2026X00581466-I1Open ↗
Showing 3 of 5 on file for this type