← Back
BuildNYC
One story retail building
Mosholu Avenue Primary Care Center
5626 MOSHOLU AVENUE · BIN 2084796
💬 Discuss this project
1951Year Built
1Stories
K1Building Class
R4Zoning
6,129 sfGross Floor Area
6Units
0 Active Violations
One story retail building · Owner of record: SJLG Riverdale Properties · 10,000 sf lot · 0.61 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbing
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofEmiliano Gourmet Market LLC1p · 1 filing · 12 docs
Floor 1Earlybird Coffee25p · 5 filings · 20 docs
CellarEmiliano Gourmet Market LLC22p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
SJLG103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Colombo Architectural Studio1108/20/2024
KDV Designs Architects211/08/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Lloyd Noel Building Consultant103/21/2026
TBC & Associates403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Monarch Plumbing & HeatingPlumbing907/08/2026
Erland ContractingGeneral Contractor807/08/2026
A&S Sheet Metalspecialty_contractor303/21/2026
Evs ElectricElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Colombo Architectural Stu4930608/20/2024
SY Engineering5149211/08/2021
Building Lifecycle
All (75)Filed (13)Permit Issued (9)Signed Off (6)Violation (9)Inspection (8)Special Inspection (30)
12/05/2025
Signed off — Alteration
APPLICATION FILED TO COMBINE AND RENOVATE EXISTING STORES. NO CHANGE IN USE, EGRESS AND OCCUPANCY.
X01097875-S1
11/14/2025
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/05/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
01/14/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
01/10/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
01/05/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
09/11/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
09/04/2024
Permit issued — Plumbing
X01097875-S1-PL
08/22/2024
Permit issued — General Construction
X01097875-I1-GC-CX
08/20/2024
Filed — Alteration
APPLICATION FILED TO COMBINE AND RENOVATE EXISTING STORES. NO CHANGE IN USE, EGRESS AND OCCUPANCY.
X01097875-S1
08/20/2024
Filed — Alteration
APPLICATION FILED TO COMBINE AND RENOVATE EXISTING STORES. NO CHANGE IN USE, EGRESS AND OCCUPANCY.
X01097875-I1
08/17/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Yahaira Volquez Colombo
08/17/2024
Special inspection requirement — Mechanical Systems
Yahaira Volquez Colombo
08/17/2024
Special inspection requirement — Final
Yahaira Volquez Colombo
08/17/2024
Special inspection requirement — Interior lighting power
Yahaira Volquez Colombo
08/17/2024
Special inspection requirement — Lighting controls
Yahaira Volquez Colombo
08/17/2024
Special inspection requirement — HVAC-R and service water heating system controls
Yahaira Volquez Colombo
08/17/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
Yahaira Volquez Colombo
08/17/2024
Special inspection requirement — HVAC-R and service water heating equipment
Yahaira Volquez Colombo
08/17/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Yahaira Volquez Colombo
06/20/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
09/27/2022
Signed off — Alteration
Installation of plumbing fixtures as per plans in connection with general construction application. No change in use, egress or occupancy.
X00576490-S1
09/27/2022
Signed off — Alteration
Installation of plumbing fixtures as per plans in connection with general construction application. No change in use, egress or occupancy.
X00576490-I1
02/10/2022
Special inspection requirement — Final
Yahaira Volquez Colombo
02/10/2022
Special inspection requirement — Interior lighting power
Yahaira Volquez Colombo
02/10/2022
Special inspection requirement — Maintenance information
Yahaira Volquez Colombo
02/10/2022
Special inspection requirement — Lighting controls
Yahaira Volquez Colombo
02/04/2022
Filed — Alteration
Installation of plumbing fixtures as per plans in connection with general construction application. No change in use, egress or occupancy.
X00576490-P3
02/02/2022
Special inspection requirement — Final
Yahaira Volquez Colombo
02/02/2022
Special inspection requirement — Maintenance information
Yahaira Volquez Colombo
02/02/2022
Special inspection requirement — Lighting controls
Yahaira Volquez Colombo
02/02/2022
Special inspection requirement — Interior lighting power
Yahaira Volquez Colombo
01/11/2022
Filed — Alteration
Installation of plumbing fixtures as per plans in connection with general construction application. No change in use, egress or occupancy.
X00576490-P2
01/04/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/03/2022
Special inspection requirement — HVAC-R and service water heating system controls
Yahaira Volquez Colombo
01/03/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
Yahaira Volquez Colombo
01/03/2022
Special inspection requirement — Maintenance information
Yahaira Volquez Colombo
01/03/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Yahaira Volquez Colombo
01/03/2022
Special inspection requirement — HVAC-R and service water heating equipment
Yahaira Volquez Colombo
11/30/2021
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
11/09/2021
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
11/08/2021
Filed — Alteration
INSTALLING NEW ROOFTOP HVAC UNIT AND ASSOCIATED DUCT WORK AT PROPOSED NEW RESTAURANT. NO OTHER WORK TO BE DONE. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
X00600741-S1
11/08/2021
Special inspection requirement — Energy Code Compliance Inspections
DAVIDSON CHRISTMAS
11/01/2021
Special inspection requirement — Mechanical Systems
SUNGBOM YI
11/01/2021
Special inspection requirement — Final
DAVIDSON CHRISTMAS
11/01/2021
Special inspection requirement — Maintenance information
SUNGBOM YI
11/01/2021
Special inspection requirement — HVAC-R and service water heating equipment
SUNGBOM YI
11/01/2021
Special inspection requirement — Duct leakage testing, insulation and design
SUNGBOM YI
10/29/2021
Filed — Alteration
Installation of plumbing fixtures as per plans in connection with general construction application. No change in use, egress or occupancy.
X00576490-P1
10/29/2021
Special inspection requirement — Maintenance information
Yahaira Volquez Colombo
10/29/2021
Special inspection requirement — HVAC-R and service water piping design and insulation
Yahaira Volquez Colombo
10/19/2021
Signed off — Alteration
X00581466-I1
10/18/2021
Permit issued — General Construction
X00576490-I1-GC
10/18/2021
Permit issued — General Construction
X00581466-I1-GC
10/07/2021
Permit issued — Mechanical Systems
X00600741-I1-MS
09/29/2021
Filed — Alteration
INSTALLING NEW ROOFTOP HVAC UNIT AND ASSOCIATED DUCT WORK AT PROPOSED NEW RESTAURANT. NO OTHER WORK TO BE DONE. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
X00600741-I1
09/16/2021
Filed — Alteration
X00581466-I1
09/14/2021
Permit issued — Plumbing
X00576490-S1-PL
09/09/2021
Permit issued — General Construction
X00576490-I1-GC
09/08/2021
Filed — Alteration
Installation of plumbing fixtures as per plans in connection with general construction application. No change in use, egress or occupancy.
X00576490-S1
Latest 60 of 75 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offMonarch Plumbing & Heating09/04/2024
DOB NOWGeneral ConstructionPermit IssuedErland Contracting08/22/2024
DOB NOWGeneral ConstructionSigned-offErland Contracting10/18/2021
DOB NOWGeneral ConstructionSigned-offErland Contracting10/18/2021
DOB NOWMechanical SystemsPermit IssuedA&S Sheet Metal10/07/2021
DOB NOWPlumbingSigned-offMonarch Plumbing & Heating09/14/2021
DOB NOWGeneral ConstructionSigned-offErland Contracting09/09/2021
DOB NOWPlumbingSigned-offMonarch Plumbing & Heating04/28/2021
DOB NOWGeneral ConstructionSigned-offErland Contracting04/13/2021
BISPLISSUEDHaron Plumbing & Heating04/06/2005
BISMHISSUEDCottam Heating & Air Condit03/15/2005
BISPLISSUEDHaron Plumbing & Heating12/28/2004
BISOTISSUEDMetro Interior Remodeling08/26/2003
BISFBISSUEDCombind Oil01/08/2002
BISSPISSUEDC.R.U. Mechan & Heating08/28/2001
BISOTISSUEDJMW Services04/23/1999
BIS—ISSUEDService Sign Erectors, Co11/24/1995
BIS—ISSUEDRGC Associates06/09/1993
2 projects · most recent 08/20/2024
Heating and Air Conditioning Systems Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
08/20/2024Permit IssuedErland ContractingHeating and Air Conditioning Systems
Heat / Cool
Trane 2TTB0036A1000AA (Existing to remain) 36,000 BTU · Condensing Unit ×1
11/08/2021Permit IssuedA&S Sheet MetalAir Conditioning Systems, Ventilation Systems
Cooling
Daikin DBG090VH00001S 8 tons · Rooftop Unit ×2
Ventilation
Captiveaire NCA18FA 4,000 CFM · Kitchen Exhaust ×3
1 project · most recent 08/20/2024
Water/Sanitary
FiledStatusContractorScope
08/20/2024Signed-offMonarch Plumbing & HeatingWater/Sanitary
2 projects · most recent 04/02/2024
General Wiring
FiledStatusContractorScope
04/02/2024CompleteEvs ElectricGeneral Wiring
05/13/2021CompleteEvs ElectricGeneral Wiring
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
02/05/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
01/14/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/10/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
01/05/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/11/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/04/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/30/2021Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/09/2021Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 39
DateRequirementInspectorRole
08/17/2024Fire-Resistant Penetrations and JointsYahaira Volquez Colombospecial
08/17/2024Mechanical SystemsYahaira Volquez Colombospecial
08/17/2024FinalYahaira Volquez Colomboprogress
08/17/2024Interior lighting powerYahaira Volquez Colomboenergy_progress
08/17/2024Lighting controlsYahaira Volquez Colomboenergy_progress
08/17/2024HVAC-R and service water heating system controlsYahaira Volquez Colomboenergy_progress
08/17/2024HVAC-R and service water piping design and insulationYahaira Volquez Colomboenergy_progress
08/17/2024HVAC-R and service water heating equipmentYahaira Volquez Colomboenergy_progress
08/17/2024Fire-Resistant Penetrations and JointsYahaira Volquez Colombospecial
02/10/2022FinalYahaira Volquez Colomboprogress
02/10/2022Interior lighting powerYahaira Volquez Colomboenergy_progress
02/10/2022Maintenance informationYahaira Volquez Colomboenergy_progress
02/10/2022Lighting controlsYahaira Volquez Colomboenergy_progress
02/02/2022FinalYahaira Volquez Colomboprogress
02/02/2022Maintenance informationYahaira Volquez Colomboenergy_progress
02/02/2022Lighting controlsYahaira Volquez Colomboenergy_progress
02/02/2022Interior lighting powerYahaira Volquez Colomboenergy_progress
01/03/2022HVAC-R and service water heating system controlsYahaira Volquez Colomboenergy_progress
01/03/2022HVAC-R and service water piping design and insulationYahaira Volquez Colomboenergy_progress
01/03/2022Maintenance informationYahaira Volquez Colomboenergy_progress
01/03/2022Fire-Resistant Penetrations and JointsYahaira Volquez Colombospecial
01/03/2022HVAC-R and service water heating equipmentYahaira Volquez Colomboenergy_progress
11/08/2021Energy Code Compliance InspectionsDAVIDSON CHRISTMASprogress
11/01/2021Mechanical SystemsSUNGBOM YIspecial
11/01/2021FinalDAVIDSON CHRISTMASprogress
Latest 25 of 39.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Earlybird CoffeeRestaurant / Food ServiceFloor 1
Project X00495508 Alteration · LOC Issued · 04/05/2021
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 68 on file (BIS + DOB NOW)
▸Plans & Drawings13
▸DOB NOWPlans/Sketch13
08/25/2026X00495508-I1Request digital key ↗
08/25/2026X00495508-S1Request digital key ↗
08/25/2026X00495508-P1Request digital key ↗
Showing 3 of 13 on file for this type
▸Seals & Professional Certifications37
▸DOB NOWProgress Inspector Seal & Signature19
09/20/2026X01097875-I1Open ↗
09/20/2026X01097875-I1Open ↗
08/30/2026X00495508-S1Open ↗
Showing 3 of 19 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature13
08/25/2026X00495508-I1Open ↗
08/25/2026X00495508-S1Open ↗
08/25/2026X00495508-P1Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
09/20/2026X01097875-I1Open ↗
08/30/2026X00600741-S1Open ↗
08/25/2026X01097875-S1Open ↗
Showing 3 of 5 on file for this type
▸Environmental & Asbestos13
▸DOB NOWDEP ACP-5: Asbestos Assessment Report13
08/25/2026X00495508-I1Open ↗
08/25/2026X00495508-S1Open ↗
08/25/2026X00495508-P1Open ↗
Showing 3 of 13 on file for this type
▸Energy Compliance5
▸DOB NOWEN2: As Built Energy Analysis.5
08/13/2026X00576490-I1Open ↗
08/13/2026X00576490-S1Open ↗
08/13/2026X00495508-S1Open ↗
Showing 3 of 5 on file for this type