1884Year Built
2Stories
C0Building Class
R6BZoning
2,220 sfGross Floor Area
3Units
Rent Stabilized0 Open Violations
Three families · Owner of record: 563 HALSEY INVESTOR LLC · 1,667 sf lot · 1.33 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbing
Roof1p · 1 filing · 15 docs
Floor 21p · 1 filing · 15 docs
Floor 1
Cellar5p · 3 filings · 20 docs
Basement1p · 1 filing · 12 docs
1 job · most recent 03/20/2024
General Wiring
FiledStatusContractorScope
03/20/2024CompleteV&B ELECTRICAL CONTNG INCGeneral Wiring
Building Lifecycle
All (52)Filed (9)Permit Issued (13)Signed Off (4)Violation (1)Inspection (5)Special Inspection (20)
04/02/2025
Signed off — Alteration
ALTERATION FILED FOR RENOVATION OF EXISTING APARTMENTS GENERAL CONSTRUCTION AND MECHANICAL. ALL OTHER RELATED WORK AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY
B08029340-I1
03/28/2025
Filed — Alteration
ALTERATION FILED FOR RENOVATION OF EXISTING APARTMENTS GENERAL CONSTRUCTION AND MECHANICAL. ALL OTHER RELATED WORK AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY
B08029340-P2
03/27/2025
Special inspection requirement — Air barrier - visual inspection
Giuseppe Anzalone
03/27/2025
Special inspection requirement — Lighting controls
Giuseppe Anzalone
03/27/2025
Special inspection requirement — HVAC-R and service water heating system controls
Giuseppe Anzalone
03/27/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Giuseppe Anzalone
03/27/2025
Special inspection requirement — Mechanical Systems
Giuseppe Anzalone
03/27/2025
Special inspection requirement — Energy Code Compliance Inspections
Giuseppe Anzalone
03/27/2025
Special inspection requirement — Final
Giuseppe Anzalone
03/27/2025
Special inspection requirement — Fire-Resistance Rated Construction
Giuseppe Anzalone
03/27/2025
Special inspection requirement — Insulation placement and R values
Giuseppe Anzalone
03/27/2025
Special inspection requirement — Maintenance information
Giuseppe Anzalone
03/27/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Giuseppe Anzalone
03/27/2025
Special inspection requirement — HVAC-R and service water heating equipment
Giuseppe Anzalone
03/27/2025
Special inspection requirement — Exterior lighting power
Giuseppe Anzalone
03/27/2025
Special inspection requirement — Interior lighting power
Giuseppe Anzalone
12/03/2024
Permit issued — General Construction
B08029340-I1-MS
11/15/2024
Signed off — Alteration
Application is filed for plumbing renovation of existing apartments, and all others related work as per filed herewith . No change in use egress, or occupancy.
B08030909-I1
11/12/2024
Signed off — Alteration
Temporary construction fence. No change to use , egress , or occupancy.
B07997912-I1
11/08/2024
Signed off — Alteration
ALTERATION FILED FOR INTERIOR REMOVAL OF EXISTING INTERIOR NON-LOAD BEARING WALLS, FLOOR, CEILING, AND WALL FINISHES AND WOOD JOIST REPAIRS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
B00736742-I1
11/07/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
10/24/2024
Filed — Alteration
Application is filed for plumbing renovation of existing apartments, and all others related work as per filed herewith . No change in use egress, or occupancy.
B08030909-P2
10/24/2024
Filed — Alteration
ALTERATION FILED FOR RENOVATION OF EXISTING APARTMENTS GENERAL CONSTRUCTION AND MECHANICAL. ALL OTHER RELATED WORK AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY
B08029340-P1
09/16/2024
Permit issued — General Construction
B08029340-I1-GC
08/25/2024
Inspection — Certified Storm Drainage-ST-Fixtures-Finish
Certified
View inspection ↗
08/25/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
05/23/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
04/26/2024
Filed — Alteration
Application is filed for plumbing renovation of existing apartments, and all others related work as per filed herewith . No change in use egress, or occupancy.
B08030909-P1
04/08/2024
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
03/01/2024
Permit issued — Plumbing
B08030909-I1-PL
02/01/2024
Permit issued — Mechanical Systems
B08029340-I1-GC
02/01/2024
Permit issued — General Construction
B00736742-I1-GC
02/01/2024
Permit issued — Construction Fence
B07997912-I1-FN
01/31/2024
Permit issued — Mechanical Systems
B08029340-I1-MS
11/16/2023
Filed — Alteration
Application is filed for plumbing renovation of existing apartments, and all others related work as per filed herewith . No change in use egress, or occupancy.
B08030909-I1
10/06/2023
Permit issued — Mechanical Systems
B08029340-I1-GC
07/10/2023
Permit issued — General Construction
B08029340-I1-MS
06/20/2023
Permit issued — Mechanical Systems
B08029340-I1-GC
04/24/2023
Filed — Alteration
ALTERATION FILED FOR RENOVATION OF EXISTING APARTMENTS GENERAL CONSTRUCTION AND MECHANICAL. ALL OTHER RELATED WORK AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY
B08029340-I1
03/23/2023
Violation issued (HPD, closed)
A
10/06/2022
Permit issued — General Construction
B00736742-I1-GC
10/05/2022
Permit issued — Construction Fence
B07997912-I1-FN
09/28/2022
Filed — Alteration
Temporary construction fence. No change to use , egress , or occupancy.
B07997912-I1
09/21/2022
Filed — Alteration
ALTERATION FILED FOR INTERIOR REMOVAL OF EXISTING INTERIOR NON-LOAD BEARING WALLS, FLOOR, CEILING, AND WALL FINISHES AND WOOD JOIST REPAIRS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
B00736742-P1
09/21/2022
Special inspection requirement — Final
Giuseppe Anzalone
09/21/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Giuseppe Anzalone
09/21/2022
Special inspection requirement — Structural Stability – Alterations of existing buildings
REZA KHAMCY
09/02/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Giuseppe Anzalone
09/02/2022
Special inspection requirement — Final
Giuseppe Anzalone
09/02/2022
Special inspection requirement — Structural Stability – Alterations of existing buildings
REZA KHAMCY
06/08/2022
Permit issued — General Construction
B00736742-I1-GC
06/01/2022
Filed — Alteration
ALTERATION FILED FOR INTERIOR REMOVAL OF EXISTING INTERIOR NON-LOAD BEARING WALLS, FLOOR, CEILING, AND WALL FINISHES AND WOOD JOIST REPAIRS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
B00736742-I1
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
563 HALSEY INVESTOR LLC103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
04/18/2019$1.3M—— → —$599/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NEW YORK DESIGN ARCHITECTS, LLP903/28/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
NEW YORK DESIGN ARCHITECTS1803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
E. CASTILLO CONSTR. CORPGeneral Contractor2107/08/2026
MFB MECHANICAL CORPGeneral Contractor707/08/2026
CROWN PLUMBING INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AKS ARCHITECTURAL & ENGIN1957503/28/2025
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offMFB MECHANICAL CORP12/03/2024
DOB NOWGeneral ConstructionSigned-offE. CASTILLO CONSTR. CORP09/16/2024
DOB NOWPlumbingSigned-offCROWN PLUMBING INC03/01/2024
DOB NOWMechanical SystemsSigned-offE. CASTILLO CONSTR. CORP02/01/2024
DOB NOWGeneral ConstructionSigned-offE. CASTILLO CONSTR. CORP02/01/2024
DOB NOWConstruction FenceSigned-offE. CASTILLO CONSTR. CORP02/01/2024
DOB NOWMechanical SystemsSigned-offMFB MECHANICAL CORP01/31/2024
DOB NOWMechanical SystemsSigned-offE. CASTILLO CONSTR. CORP10/06/2023
DOB NOWGeneral ConstructionSigned-offMFB MECHANICAL CORP07/10/2023
DOB NOWMechanical SystemsSigned-offE. CASTILLO CONSTR. CORP06/20/2023
DOB NOWGeneral ConstructionSigned-offE. CASTILLO CONSTR. CORP10/06/2022
DOB NOWConstruction FenceSigned-offE. CASTILLO CONSTR. CORP10/05/2022
DOB NOWGeneral ConstructionSigned-offE. CASTILLO CONSTR. CORP06/08/2022
BISPLISSUEDMCMILLAN PLUMBING & HTG01/12/2007
BISPLISSUEDRIGID PLUMBING CONT INC10/13/2005
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
11/07/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/25/2024Certified Storm Drainage-ST-Fixtures-FinishCertifiedView ↗
08/25/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
05/23/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/08/2024Pass-Final PL - UndergroundPassView ↗
▾Special Inspection Requirements (DOB NOW) — 20
DateRequirementInspectorRole
03/27/2025Air barrier - visual inspectionGiuseppe Anzaloneenergy_progress
03/27/2025Lighting controlsGiuseppe Anzaloneenergy_progress
03/27/2025HVAC-R and service water heating system controlsGiuseppe Anzaloneenergy_progress
03/27/2025Fire-Resistant Penetrations and JointsGiuseppe Anzalonespecial
03/27/2025Mechanical SystemsGiuseppe Anzalonespecial
03/27/2025Energy Code Compliance InspectionsGiuseppe Anzaloneprogress
03/27/2025FinalGiuseppe Anzaloneprogress
03/27/2025Fire-Resistance Rated ConstructionGiuseppe Anzaloneprogress
03/27/2025Insulation placement and R valuesGiuseppe Anzaloneenergy_progress
03/27/2025Maintenance informationGiuseppe Anzaloneenergy_progress
03/27/2025HVAC-R and service water piping design and insulationGiuseppe Anzaloneenergy_progress
03/27/2025HVAC-R and service water heating equipmentGiuseppe Anzaloneenergy_progress
03/27/2025Exterior lighting powerGiuseppe Anzaloneenergy_progress
03/27/2025Interior lighting powerGiuseppe Anzaloneenergy_progress
09/21/2022FinalGiuseppe Anzaloneprogress
09/21/2022Fire-Resistant Penetrations and JointsGiuseppe Anzalonespecial
09/21/2022Structural Stability – Alterations of existing buildingsREZA KHAMCYspecial
09/02/2022Fire-Resistant Penetrations and JointsGiuseppe Anzalonespecial
09/02/2022FinalGiuseppe Anzaloneprogress
09/02/2022Structural Stability – Alterations of existing buildingsREZA KHAMCYspecial
▾Documents — 43 on file (BIS + DOB NOW)
▸Plans & Drawings9
▸DOB NOWPlans/Sketch9
08/29/2026B00736742-I1Request digital key ↗
08/29/2026B00736742-P1Request digital key ↗
08/28/2026B07997912-I1Request digital key ↗
Showing 3 of 9 on file for this type
▸Applications & Permits8
▸DOB NOWLPC Approval/Permit8
08/29/2026B00736742-P1Open ↗
08/29/2026B00736742-I1Open ↗
08/13/2026B08029340-P1Open ↗
Showing 3 of 8 on file for this type
▸Seals & Professional Certifications18
▸DOB NOWDPL-1: Design Professional Seal & Signature9
08/29/2026B00736742-P1Open ↗
08/29/2026B00736742-I1Open ↗
08/28/2026B07997912-I1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
09/01/2026B00736742-P1Open ↗
09/01/2026B00736742-P1Open ↗
08/23/2026B08029340-P2Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
09/01/2026B00736742-P1Open ↗
08/23/2026B08029340-P2Open ↗
08/23/2026B08029340-P2Open ↗
Showing 3 of 4 on file for this type
▸Environmental & Asbestos8
▸DOB NOWDEP ACP-5: Asbestos Assessment Report8
08/29/2026B00736742-I1Open ↗
08/29/2026B00736742-P1Open ↗
08/27/2026B08029340-I1Open ↗
Showing 3 of 8 on file for this type