← Back
Miscellaneous one family
565 WEST 159 STREET
MANHATTAN · BIN 1062817
💬 Discuss this project
1910Year Built
3Stories
A9Building Class
R7-2Zoning
2,400 sfGross Floor Area
1Units
Rent Stabilized1 Open Violation ▸
Miscellaneous one family · 1,499 sf lot · 1.6 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalFire Protection
Roof6p · 2 filings · 20 docs
Floor 34p · 1 filing · 9 docs
Floor 24p · 1 filing · 9 docs
Floor 14p · 1 filing · 9 docs
Cellar5p · 2 filings · 20 docs
Basement4p · 1 filing · 9 docs
1 job · most recent 08/25/2020
General Wiring
FiledStatusContractorScope
08/25/2020CompleteGEDNEY ELECTRIC, LLCGeneral Wiring
Building Lifecycle
All (44)Filed (7)Permit Issued (4)Signed Off (3)Violation (11)Inspection (5)Special Inspection (14)
03/30/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
03/23/2023
Inspection — Pass-Final SP - Up to 3 Requested Floors
Pass
View inspection ↗
03/16/2023
Violation issued (HPD, closed)
A
02/16/2023
Signed off — Alteration
Sprinkler work in conjunction with ALT.1 application
M00437241-S2
01/17/2023
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
10/18/2022
Signed off — Alteration
Sprinkler work in conjunction with ALT.1 application
M00437241-S1
10/17/2022
Permit issued — General Construction
M00484792-I1-GC
05/16/2022
Signed off — Alteration
Sprinkler work in conjunction with ALT.1 application
M00437241-I1
02/16/2022
Violation issued (HPD, closed)
A
01/21/2022
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
01/12/2022
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
01/10/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Howard Bader
01/10/2022
Special inspection requirement — Sprinkler Systems
Howard Bader
12/08/2021
Filed — Alteration
Sprinkler work in conjunction with ALT.1 application
M00437241-P3
11/22/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
Howard Bader
11/22/2021
Special inspection requirement — Sprinkler Systems
Howard Bader
09/14/2021
Permit issued — Sprinklers
M00437241-I1-EW-SP
08/10/2021
Permit issued — Mechanical Systems
M00437241-S2-MS
07/06/2021
Special inspection requirement — Energy Code Compliance Inspections
Howard Bader
07/06/2021
Special inspection requirement — HVAC-R and service water piping design and insulation
Howard Bader
06/14/2021
Special inspection requirement — Final
Howard Bader
06/14/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
Howard Bader
06/14/2021
Special inspection requirement — Mechanical Systems
Howard Bader
06/07/2021
Filed — Alteration CO
M00484792-I1
06/02/2021
Filed — Alteration
Sprinkler work in conjunction with ALT.1 application
M00437241-P2
06/02/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
06/02/2021
Special inspection requirement — Final
06/02/2021
Special inspection requirement — Mechanical Systems
05/19/2021
Filed — Alteration
Sprinkler work in conjunction with ALT.1 application
M00437241-P1
05/17/2021
Special inspection requirement — HVAC-R and service water piping design and insulation
BALTU YORKOS
05/17/2021
Special inspection requirement — Energy Code Compliance Inspections
BALTU YORKOS
03/24/2021
Permit issued — Plumbing
M00437241-S1-PL
03/08/2021
Filed — Alteration
Sprinkler work in conjunction with ALT.1 application
M00437241-S2
01/21/2021
Filed — Alteration
Sprinkler work in conjunction with ALT.1 application
M00437241-S1
01/07/2021
Filed — Alteration
Sprinkler work in conjunction with ALT.1 application
M00437241-I1
10/10/2018
Violation issued (HPD, closed)
I
10/27/2016
Violation issued (HPD, closed)
I
10/02/2015
Violation issued (HPD, closed)
I
05/02/2001
Violation issued (HPD, closed)
A
08/29/1995
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/18/1994
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/18/1993
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
09/14/1991
Violation issued (ECB, closed)
Boilers
04/30/1981
Violation issued (HPD, open)
A
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
07/11/2019$950K—Private party → Private party$396/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
YORKOS ENGINEERING DESIGN CONSULT612/08/2021
FONTAN ARCHITECTURE PLLC106/07/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
AGOUTI CONSTRUCTION CONSULTING703/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CORNIEL CONSTRUCTION LLCGeneral Contractor303/21/2026
BIG APPLE FIRE SPRKL CO IFire Protection107/08/2026
GLENWOOD CONSTRUCTION CORGeneral Contractor107/08/2026
DYNAMIC CONTRACTING CORPPlumbing103/22/2026
HIGHLAND PLUMBING LLCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
H. A. BADER CONSULTANTS2332412/08/2021
INTEGRITY CONSULTING SERV666106/07/2021
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedGLENWOOD CONSTRUCTION COR10/17/2022
DOB NOWSprinklersSigned-offBIG APPLE FIRE SPRKL CO I09/14/2021
DOB NOWMechanical SystemsSigned-offCORNIEL CONSTRUCTION LLC08/10/2021
DOB NOWPlumbingSigned-offHIGHLAND PLUMBING LLC03/24/2021
BISOTISSUEDCORNIEL CONSTRUCTION LLC06/12/2020
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
03/30/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
03/23/2023Pass-Final SP - Up to 3 Requested FloorsPassView ↗
01/17/2023Pass-Final CND-Occupancy InspectionPassView ↗
01/21/2022Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
01/12/2022Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 14
DateRequirementInspectorRole
01/10/2022Fire-Resistant Penetrations and JointsHoward Baderspecial
01/10/2022Sprinkler SystemsHoward Baderspecial
11/22/2021Fire-Resistant Penetrations and JointsHoward Baderspecial
11/22/2021Sprinkler SystemsHoward Baderspecial
07/06/2021Energy Code Compliance InspectionsHoward Baderprogress
07/06/2021HVAC-R and service water piping design and insulationHoward Baderenergy_progress
06/14/2021FinalHoward Baderprogress
06/14/2021Fire-Resistant Penetrations and JointsHoward Baderspecial
06/14/2021Mechanical SystemsHoward Baderspecial
06/02/2021Fire-Resistant Penetrations and Joints—special
06/02/2021Final—progress
06/02/2021Mechanical Systems—special
05/17/2021HVAC-R and service water piping design and insulationBALTU YORKOSenergy_progress
05/17/2021Energy Code Compliance InspectionsBALTU YORKOSprogress
▾Documents — 69 on file (BIS + DOB NOW)
▸Plans & Drawings7
▸DOB NOWPlans/Sketch - Mechanical Systems2
09/03/2026M00437241-S2Request digital key ↗
08/15/2026M00437241-P2Request digital key ↗
▸DOB NOWPlans/Sketch - Sprinkler2
09/03/2026M00437241-I1Request digital key ↗
08/15/2026M00437241-P3Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing2
09/03/2026M00437241-S1Request digital key ↗
08/15/2026M00437241-P1Request digital key ↗
▸DOB NOWPlans/Sketch1
09/03/2026M00484792-I1Request digital key ↗
▸Applications & Permits7
▸BISPLAN / WORK APPROVAL APPLICATION6
10/13/2022121207746Open ↗
07/22/2020121207746Open ↗
07/16/2020121207746Open ↗
Showing 3 of 6 on file for this type
▸BISWORK PERMIT APPLICATION1
06/12/2020140890757Open ↗
▸Seals & Professional Certifications19
▸DOB NOWDPL-1: Design Professional Seal & Signature7
09/03/2026M00484792-I1Open ↗
09/03/2026M00437241-P3Open ↗
09/03/2026M00437241-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWProgress Inspector Seal & Signature5
09/01/2026M00437241-S1Open ↗
09/01/2026M00437241-S1Open ↗
08/28/2026M00437241-P1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
08/29/2026M00437241-I1Open ↗
08/27/2026M00437241-P3Open ↗
08/23/2026M00437241-S2Open ↗
Showing 3 of 4 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
03/17/2020140890757Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
03/17/2020140890757Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
03/17/2020140890757Open ↗
▸Safety & Tenant Protection15
▸DOB NOWHPD-3: Single Room Occupancy Multiple Dwelling (SRO MD) Anti-Harassment Checklist7
08/13/2026M00437241-P3Open ↗
08/13/2026M00437241-P2Open ↗
08/13/2026M00437241-P1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWTenant Protection Plan2
08/13/2026M00437241-P3Open ↗
08/13/2026M00437241-I1Open ↗
▸BISSTREET TREE CHECKLIST1
06/29/2020121207746Open ↗
▸BISSRO MD ANTI-HARASSMENT CHECKLIST1
03/17/2020140890757Open ↗
▸DOB NOWStreet Tree Checklist1
09/03/2026M00484792-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026M00484792-I1Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026M00484792-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/13/2026M00484792-I1Open ↗
▸Environmental & Asbestos8
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
09/03/2026M00484792-I1Open ↗
09/03/2026M00437241-P1Open ↗
09/03/2026M00437241-P2Open ↗
Showing 3 of 7 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
03/17/2020140890757Open ↗
▸Energy Compliance5
▸DOB NOWEN2: As Built Energy Analysis.2
08/13/2026M00437241-S1Open ↗
08/13/2026M00484792-I1Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
03/17/2020140890757Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
03/17/2020140890757Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
10/12/2022140890757Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
06/12/2020140890757Open ↗
03/17/2020140890757Open ↗
▸Approvals, Objections & Sign-offs3
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
10/13/2022140890757Open ↗
▸BISSCHEDULE A - OCCUPANCY / USE1
05/28/2020121207746Open ↗
▸BISFINAL1
10/12/2022140890757Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT1
03/17/2020140890757Open ↗
▸BISCOST AFFIDAVIT (FINAL): PW31
10/12/2022140890757Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
03/17/2020140890757Open ↗