| Owner | Filings | Most Recent |
|---|---|---|
| Woodside Landmark Realty | 26 | 10/13/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Gerald Caliendo Architects | 9 | 07/07/2026 |
| Ras PE Consulting Engineers | 2 | 10/21/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| Caliendo Architects | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Impact Builders | General Contractor | 6 | 07/08/2026 |
| RM Electric Co | Electrical | 1 | 03/21/2026 |
| McQueen Eusebio | Electrical | 1 | 03/21/2026 |
| Hydro Mechanical | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| World Design Architecture | 9323 | 6 | 07/07/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Permit Issued | Impact Builders | 04/16/2026 |
| DOB NOW | Earth Work | Permit Issued | Impact Builders | 04/16/2026 |
| DOB NOW | General Construction | Permit Issued | Impact Builders | 04/16/2026 |
| DOB NOW | Plumbing | Permit Issued | Hydro Mechanical | 10/28/2025 |
| DOB NOW | Earth Work | Permit Issued | Impact Builders | 04/24/2025 |
| DOB NOW | General Construction | Permit Issued | Impact Builders | 04/14/2025 |
| DOB NOW | Structural | Permit Issued | Impact Builders | 04/11/2025 |
| BIS | OT | ISSUED | A&A Building Consultants | 12/13/2010 |
| BIS | MH | ISSUED | Ronesin Construction | 12/03/2008 |
| BIS | OT | ISSUED | WJ Contracting | 11/13/2008 |
| BIS | FP | ISSUED | N.Y. Business Fire System | 03/22/2006 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/07/2026 | Permit Issued | Hydro Mechanical | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/16/2025 | Complete | Limitless Electric Resources | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/07/2026 | Permit Issued | Impact Builders | Steel |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/07/2026 | Permit Issued | Impact Builders | Earthwork |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/29/2026 | Fire-Resistant Penetrations and Joints | William Alicea | special |
| 06/29/2026 | Energy Code Compliance Inspections | William Alicea | progress |
| 06/23/2026 | Fire-Resistance Rated Construction | William Alicea | progress |
| 01/22/2026 | Public Assembly Emergency Lighting | William Alicea | progress |
| 08/28/2025 | Fire-Resistance Rated Construction | William Alicea | progress |
| 01/26/2024 | Concrete - Cast-In-Place | William Alicea | special |
| 01/26/2024 | Structural Stability – Alterations of existing buildings | William Alicea | special |
| 10/06/2023 | Final | William Alicea | progress |
| 10/06/2023 | Footing and Foundation | William Alicea | progress |