| Owner | Filings | Most Recent |
|---|---|---|
| FEIL ORGANIZATION | 262 | 09/13/2026 |
| TOWER 570 C/O JEFFREY MGMT | 310 | 03/22/2026 |
| JEFFREY MANAGEMENT | 8 | 03/22/2026 |
| MERDIH COMPANY REALTY | 1 | 03/22/2026 |
| MENDIK REALTY | 58 | 03/22/2026 |
| 19 WEST 45 ST REALTY CO | 1 | 03/22/2026 |
| OWNER OF 566 LEXINGTON AV | 3 | 03/22/2026 |
| 570 LEXINGTON COMPANY | 8 | 03/22/2026 |
| KILROY METAL INC. | 1 | 03/22/2026 |
| TWOER 570 COMPANY LP | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| SYDNESS ARCHITECTS, PC | 36 | 07/27/2026 |
| GOLDMAN COPELAND ASSOCIATES | 96 | 06/03/2026 |
| BUILDING CONSULTING ENGINEERING | 2 | 06/01/2026 |
| MURRAY ENGINEERING PC | 4 | 02/24/2026 |
| FXCOLLABORATIVE ARCHITECTS LLP | 1 | 02/23/2026 |
| PATUXENT ENGINEERING LLC | 2 | 06/08/2021 |
| BRIAN T. O'CONNOR | 2 | 04/08/2021 |
| TOHFAZ UDDIN PE PC | 1 | 06/23/2020 |
| MITCHELL / GIURGOLA ARCHITECTS | 1 | 01/15/2020 |
| TECTONIC ENGINEERING | 1 | 09/10/2019 |
| FXFOWLE ARCHITECTS LLP | 1 | 01/28/2019 |
| JOEL PHAGOO P.E. PLLC | 1 | 07/13/2018 |
| BAILEYS ENGINEERING PC | 3 | 02/15/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| WILLIAM VITACCO ASSOCIATES | 247 | 03/21/2026 |
| AE DESIGN SOLUTION | 6 | 03/21/2026 |
| A1 EXPEDITING SERVICE | 2 | 03/21/2026 |
| CONSTRUCTION PERMIT SERVICES | 2 | 03/21/2026 |
| DIRECT ACCESS EXPEDITING, INC. | 2 | 03/21/2026 |
| PATUXENT ENGINEERING | 4 | 03/21/2026 |
| SMEP DESIGN & CONSULTATION LLC | 2 | 03/21/2026 |
| DVA Advisors | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| NUCOR CONSTRUCTION CORP | General Contractor | 24 | 07/08/2026 |
| ACCORD CONTR AND MGMT COR | General Contractor | 17 | 07/08/2026 |
| UNIVERSAL MGMT & CONT COR | General Contractor | 14 | 07/08/2026 |
| EVEREST SCAFFOLDING INC | General Contractor | 8 | 07/08/2026 |
| MANHATTAN D ENTERPRISES | General Contractor | 7 | 07/08/2026 |
| COMFORT ZONE MECHANICAL | General Contractor | 6 | 07/08/2026 |
| METROTECH MECHANICAL CORP | Plumbing | 5 | 07/08/2026 |
| JAM SERVICE CO., INC | Plumbing | 5 | 07/08/2026 |
| FMG GENERAL CONTRACTING * | General Contractor | 5 | 07/08/2026 |
| JAM SERVICE CO., INC | Fire Protection | 4 | 08/26/2026 |
| A&A PLUMBING CORP | Plumbing | 3 | 07/08/2026 |
| PATRIOT ELECTRIC CORP | Electrical | 3 | 03/22/2026 |
| REEM PLBG & HTG CORP | Fire Protection | 3 | 07/08/2026 |
| UNIVERSAL FIRE SPR LLC | Fire Protection | 3 | 07/08/2026 |
| SEAN COAKLEY P & H INC | Fire Protection | 3 | 07/08/2026 |
| PSI PARTNERS, LLC | Fire Protection | 3 | 07/08/2026 |
| ROCKLEDGE SCAFFOLD CORP | General Contractor | 2 | 03/21/2026 |
| WILLIAM C. GERAKARIS P&H | Plumbing | 2 | 07/08/2026 |
| KING HOIST & SCAFFOLDING | General Contractor | 2 | 03/21/2026 |
| FIVE BOROUGH NYC LLC | Fire Protection | 2 | 07/08/2026 |
| NEW EMPIRE BUILDER CORP | General Contractor | 2 | 07/08/2026 |
| BEDROCK MECHANICAL INC | Fire Protection | 2 | 07/08/2026 |
| CHAMPION INTERNATIONAL CO | General Contractor | 2 | 07/08/2026 |
| SKH MECHANICAL CORP | Fire Protection | 2 | 07/08/2026 |
| STEPHEN KOPEC | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| DOMANI INSPECTION SERVICE | 843 | 50 | 07/27/2026 |
| GOLDMAN COPELAND ASSOCIAT | 2826 | 65 | 06/03/2026 |
| BUILDING CONSULTING ENGIN | 1034 | 2 | 06/01/2026 |
| MURRAY ENGINEERING PC | 1434 | 1 | 02/24/2026 |
| TECTONIC ENGINEERING CONS | 106 | 1 | 09/10/2019 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | DPM CONTRACTING SER. INC | 08/14/2026 |
| DOB NOW | Mechanical Systems | Signed-off | NEW EMPIRE BUILDER CORP | 06/23/2026 |
| DOB NOW | General Construction | Signed-off | NEW EMPIRE BUILDER CORP | 06/03/2026 |
| DOB NOW | Sprinklers | Permit Issued | REEM PLBG & HTG CORP | 05/20/2026 |
| DOB NOW | Suspended Scaffold | Signed-off | STRUCTUAL PRESV SYSTEM | 05/19/2026 |
| DOB NOW | Standpipe | Permit Issued | JAM SERVICE CO., INC | 05/14/2026 |
| DOB NOW | Plumbing | Signed-off | METROTECH MECHANICAL CORP | 04/22/2026 |
| DOB NOW | General Construction | Permit Issued | UNIVERSAL MGMT & CONT COR | 04/14/2026 |
| DOB NOW | Sprinklers | Permit Issued | BEDROCK MECHANICAL INC | 04/01/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | NUCOR CONSTRUCTION CORP | 04/01/2026 |
| DOB NOW | General Construction | Permit Issued | NUCOR CONSTRUCTION CORP | 03/30/2026 |
| DOB NOW | Structural | Permit Issued | ACCORD CONTR MGMT COR | 03/04/2026 |
| DOB NOW | General Construction | Permit Issued | ACCORD CONTR MGMT COR | 03/04/2026 |
| DOB NOW | General Construction | Permit Issued | ACCORD CONTR MGMT COR | 03/02/2026 |
| DOB NOW | Sprinklers | Permit Issued | BEDROCK MECHANICAL INC | 02/26/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | ACCORD CONTR MGMT COR | 02/26/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | NUCOR CONSTRUCTION CORP | 02/25/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | ACCORD CONTR MGMT COR | 02/20/2026 |
| DOB NOW | Sprinklers | Permit Issued | FIVE BOROUGH NYC LLC | 02/19/2026 |
| DOB NOW | Plumbing | Permit Issued | WILLIAM C. GERAKARIS P&H | 02/19/2026 |
| DOB NOW | General Construction | Permit Issued | NUCOR CONSTRUCTION CORP | 02/17/2026 |
| DOB NOW | Sprinklers | Permit Issued | UNIVERSAL FIRE SPR LLC | 02/05/2026 |
| DOB NOW | General Construction | Permit Issued | ACCORD CONTR MGMT COR | 02/05/2026 |
| DOB NOW | Plumbing | Permit Issued | METROTECH MECHANICAL CORP | 02/05/2026 |
| DOB NOW | Plumbing | Signed-off | JAM SERVICE CO., INC | 01/25/2026 |
| DOB NOW | Standpipe | Permit Issued | JAM SERVICE CO., INC | 01/09/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | ACCORD CONTR MGMT COR | 01/09/2026 |
| DOB NOW | Sprinklers | Permit Issued | REEM PLBG & HTG CORP | 10/21/2025 |
| DOB NOW | Sprinklers | Signed-off | UNIVERSAL FIRE SPR LLC | 10/16/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | UNIVERSAL MGMT & CONT COR | 10/06/2025 |
| DOB NOW | General Construction | Signed-off | UNIVERSAL MGMT & CONT COR | 10/06/2025 |
| DOB NOW | Plumbing | Signed-off | METROTECH MECHANICAL CORP | 09/17/2025 |
| DOB NOW | General Construction | Permit Issued | ACCORD CONTR MGMT COR | 09/15/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | ACCORD CONTR AND MGMT COR | 09/10/2025 |
| DOB NOW | General Construction | Permit Issued | CHAMPION INTERNATIONAL CO | 08/29/2025 |
| DOB NOW | Sprinklers | Permit Issued | SEAN COAKLEY P & H INC | 08/19/2025 |
| DOB NOW | Sprinklers | Signed-off | FIVE BOROUGH NYC LLC | 08/13/2025 |
| DOB NOW | Plumbing | Signed-off | WILLIAM C. GERAKARIS P&H | 08/13/2025 |
| DOB NOW | Mechanical Systems | Signed-off | NUCOR CONSTRUCTION CORP | 08/13/2025 |
| DOB NOW | General Construction | Signed-off | NUCOR CONSTRUCTION CORP | 08/11/2025 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 01/06/2026 | Permit Issued | ACCORD CONTR AND MGMT COR | Air Conditioning Systems, Ventilation Systems | Ventilation N/A NA 600 CFM · Exhaust Fan ×3 |
| 09/30/2025 | Permit Issued | UNIVERSAL MGMT & CONT COR | Ventilation Systems | — |
| 09/08/2025 | Permit Issued | ACCORD CONTR AND MGMT COR | Air Conditioning Systems, Ventilation Systems | — |
| 07/14/2025 | Signed-off | NUCOR CONSTRUCTION CORP | Ventilation Systems | Ventilation Greenheck CSP-A200 140 CFM · Exhaust Fan ×1 SP-A200 140 CFM · Exhaust Fan ×1 SP-A510 400 CFM · Exhaust Fan ×1 |
| 07/22/2024 | Permit Issued | A.W. & S. CONSTRUCTION CO | Air Conditioning Systems | Cooling United Cool Air VARC10G3AHA-A 120,000 BTU · Split System ×4 VARC3G3AHA-A 35,000 BTU · Split System ×2 OSWV12G3ADFTA30-T 171,500 BTU ×3 OSWV6G3ADFTA15-T 83,400 BTU · Wshp ×3 VW3G3ASHA-A 35,500 BTU · Packaged Unit ×1 VW5G3ASHA-A 57,000 BTU ×3 EVSA10G3ATA-X, BW10G3ATA 118,000 BTU · Split System ×6 EVSA3G3ASTA-X, BW3GASNTA 35,000 BTU · Split System ×4 EVAS10G3ATA, BW10G3ATA 120,000 BTU · Split System ×2 VSW3G3ASTA 35,500 BTU ×2 |
| 08/23/2022 | — | — | Associated Ducts and Piping, Ventilation Systems | — |
| 05/31/2022 | Permit Issued | COMFORT ZONE MECHANICAL | Heating and Air Conditioning Systems | Heat / Cool International Enviro-Tec VDD20 1,920 tons · Ahu ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/03/2026 | Permit Issued | JAM SERVICE CO., INC | 3 outlets |
| 02/24/2026 | — | — | Sprinkler System |
| 01/06/2026 | Permit Issued | UNIVERSAL FIRE SPR LLC | Sprinkler System |
| 09/30/2025 | Permit Issued | REEM PLBG & HTG CORP | Sprinkler System |
| 07/17/2025 | Permit Issued | SEAN COAKLEY P & H INC | Sprinkler System |
| 07/14/2025 | Signed-off | FIVE BOROUGH NYC LLC | Sprinkler System |
| 01/09/2025 | Signed-off | REEM PLBG & HTG CORP | Sprinkler System |
| 06/28/2023 | — | — | — |
| 08/29/2022 | — | — | 127 heads |
| 08/23/2022 | — | — | — |
| 05/15/2020 | Signed-off | SIRINA FIRE PROT CORP | 8 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/03/2026 | Signed-off | JAM SERVICE CO., INC | Water/Sanitary |
| 01/06/2026 | Permit Issued | METROTECH MECHANICAL CORP | Water/Sanitary |
| 09/30/2025 | — | — | — |
| 09/08/2025 | Signed-off | METROTECH MECHANICAL CORP | Water/Sanitary |
| 07/17/2025 | — | — | — |
| 07/14/2025 | Signed-off | WILLIAM C. GERAKARIS P&H | Water/Sanitary |
| 04/15/2025 | Permit Issued | JAM SEWER CLEANING SVC | Water/Sanitary |
| 08/23/2022 | — | — | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/18/2026 | Permit Issued | NORLIN ELECL CONTRS INC | General Wiring |
| 08/17/2026 | Complete | NORLIN ELECL CONTRS INC | General Wiring |
| 03/02/2026 | Permit Issued | OFF SHORE ELECTRIC CORP | General Wiring |
| 01/07/2026 | Complete | NORLIN ELECL CONTRS INC | General Wiring |
| 10/23/2025 | Complete | M&T ELECTRICAL LLC | — |
| 09/18/2025 | Complete | M&T ELECTRICAL LLC | — |
| 09/09/2025 | Complete | NORLIN ELECL CONTRS INC | General Wiring |
| 02/18/2025 | Complete | M.O.S. ELEC'L CONTR'G COR | General Wiring |
| 09/16/2024 | Complete | NYCO ELECTRIC CORP | General Wiring |
| 02/08/2024 | Complete | PREMIER ELECTRIC, INC | General Wiring |
| 01/08/2024 | Complete | M&T ELECTRICAL LLC | — |
| 09/06/2023 | Complete | M&T ELECTRICAL LLC | — |
| 04/11/2023 | Complete | NORLIN ELECL CONTRS INC | General Wiring |
| 02/28/2023 | Complete | CENTENNIAL ELEVATOR INDUS | General Wiring |
| 03/29/2022 | Permit Issued | NORLIN ELECL CONTRS INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/24/2026 | Permit Issued | ACCORD CONTR AND MGMT COR | Steel |
| 10/20/2025 | Signed-off | COMFORT ZONE MECHANICAL | Steel |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/23/2020 | Permit Issued | KING HOIST & SCAFFOLDING | Scaffold |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/03/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/29/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 07/08/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/25/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/25/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/23/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/23/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/28/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/15/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/11/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/04/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/24/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/15/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 04/15/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/15/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 04/10/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/03/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/19/2026 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 03/17/2026 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 03/17/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/17/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/16/2026 | Pass-Final PL - Underground | Pass | View ↗ |
| 03/13/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/12/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/10/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/27/2026 | Fire-Resistant Penetrations and Joints | JOHN MCMONAGLE | special |
| 07/27/2026 | Mastic and Intumescent Fire-resistant Coatings | JOHN MCMONAGLE | special |
| 07/27/2026 | Final | Kenneth Sydness | progress |
| 07/21/2026 | Mastic and Intumescent Fire-resistant Coatings | JOHN MCMONAGLE | special |
| 07/21/2026 | Fire-Resistant Penetrations and Joints | JOHN MCMONAGLE | special |
| 07/21/2026 | Final | Kenneth Sydness | progress |
| 07/06/2026 | Mastic and Intumescent Fire-resistant Coatings | JOHN MCMONAGLE | special |
| 07/06/2026 | Fire-Resistant Penetrations and Joints | JOHN MCMONAGLE | special |
| 07/06/2026 | Fire-Resistant Penetrations and Joints | JOHN MCMONAGLE | special |
| 07/06/2026 | Final | Kenneth Sydness | progress |
| 07/06/2026 | Fire-Resistant Penetrations and Joints | JOHN MCMONAGLE | special |
| 07/06/2026 | Mastic and Intumescent Fire-resistant Coatings | JOHN MCMONAGLE | special |
| 07/06/2026 | Final | Kenneth Sydness | progress |
| 07/06/2026 | Final | Kenneth Sydness | progress |
| 06/04/2026 | Standpipe Systems | DANIEL COLOMBINI | special |
| 06/04/2026 | Fire-Resistant Penetrations and Joints | DANIEL COLOMBINI | special |
| 05/26/2026 | Fire-Resistant Penetrations and Joints | TONY ONYEAGORO | special |
| 05/08/2026 | Standpipe Systems | DANIEL COLOMBINI | special |
| 05/08/2026 | Fire-Resistant Penetrations and Joints | DANIEL COLOMBINI | special |
| 05/08/2026 | Final | TONY ONYEAGORO | progress |
| 02/24/2026 | Structural Steel - High Strength Bolting | Robert Murray | special |
| 02/17/2026 | Structural Steel - Details | Robert Murray | special |
| 02/17/2026 | Structural Stability – Alterations of existing buildings | Robert Murray | special |
| 02/17/2026 | Structural Steel - Welding | Robert Murray | special |
| 02/06/2026 | Fire-Resistant Penetrations and Joints | DANIEL COLOMBINI | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Wolf Popper | Office | Floor 19 | Project M01330182 |
| First Eagle Investments | Office | Floor 20 | Project M00674138 |
| Cornell SC Johnson College of Business | Office | Floor 7 | Project M00278524 Project M00278537 Project M00278545 Project M00280569 |