← Back
Three families
575 MACON STREET
BROOKLYN · BIN 3046618
💬 Discuss this project
1899Year Built
3Stories
C0Building Class
R6BZoning
—Gross Floor Area
3Units
2 Open Violations ▸FDNY Report ↗
Three families · 1.76 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralPlumbing
Permit Issued — active, not yet Signed-off
RoofUnder Construction1p · 1 filing · 20 docs
Floor 3Under Construction16p · 1 filing · 20 docs
Floor 2Under Construction16p · 1 filing · 20 docs
Floor 1Under Construction31p · 1 filing · 20 docs
CellarUnder Construction31p · 1 filing · 20 docs
BasementUnder Construction31p · 1 filing · 20 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NTD ENGINEERING CONSULTANT LLC308/17/2026
NASH WATERS ARCHITECT205/11/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
LLOYD NOEL BUILDING CONSULTANT103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SIMONSAYS CORPGeneral Contractor208/16/2026
CHRISTOPHER STABILEElectrical103/21/2026
STABILE CHRISTOPHERElectrical103/21/2026
A.M.N. CORPORATIONPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MOHAMMAD AHEAD - PROFESSI9286408/17/2026
AG ENGINEERING PLLC8899205/11/2026
Building Lifecycle
All (70)Filed (5)Permit Issued (3)Violation (4)Objection (28)Special Inspection (30)
08/17/2026
Filed — Alteration CO
Convert a (2) family into a (1) Family. New Enlargement at the rear of the building. installation of partitions, wall and floor finishes with new windows and doors as per plan.
B01345631-P1
08/14/2026
Permit issued — Structural
B01345631-S2-ST
08/14/2026
Special inspection requirement — Final
ARIEL GOLSHAN
08/14/2026
Special inspection requirement — Subgrade Inspections
MOHAMMAD AHEAD
08/14/2026
Special inspection requirement — Concrete - Cast-In-Place
MOHAMMAD AHEAD
08/14/2026
Special inspection requirement — Footing and Foundation
MOHAMMAD AHEAD
08/07/2026
Violation issued (ECB, open)
Construction
07/06/2026
Permit issued — Plumbing
B01345631-S3-PL
07/02/2026
Permit issued — General Construction
B01345631-I1-GC
06/18/2026
Objection resolved — Addressed
06/18/2026
Objection resolved — Addressed
06/18/2026
Objection resolved — Addressed
06/16/2026
Objection raised — Other
06/16/2026
Objection raised — Other
06/16/2026
Objection raised — Other
06/09/2026
Objection resolved — Addressed
06/04/2026
Filed — Alteration CO
Convert a (2) family into a (1) Family. New Enlargement at the rear of the building. installation of partitions, wall and floor finishes with new windows and doors as per plan.
B01345631-S4
06/04/2026
Objection resolved — Addressed
06/04/2026
Objection resolved — Addressed
06/04/2026
Objection resolved — Addressed
06/04/2026
Special inspection requirement — Structural Wood Frame
MOHAMMAD AHEAD
06/01/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
MOHAMMAD AHEAD
05/19/2026
Objection raised — Cost
05/19/2026
Objection raised — Other
05/19/2026
Objection raised — Other
05/19/2026
Objection raised — Other
05/13/2026
Filed — Alteration CO
Convert a (2) family into a (1) Family. New Enlargement at the rear of the building. installation of partitions, wall and floor finishes with new windows and doors as per plan.
B01345631-S2
05/11/2026
Filed — Alteration CO
Convert a (2) family into a (1) Family. New Enlargement at the rear of the building. installation of partitions, wall and floor finishes with new windows and doors as per plan.
B01345631-S3
05/07/2026
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
MOHAMMAD AHEAD
05/06/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
ARIEL GOLSHAN
05/06/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
ARIEL GOLSHAN
05/06/2026
Special inspection requirement — Energy Code Compliance Inspections
ARIEL GOLSHAN
05/01/2026
Special inspection requirement — Post-installed Anchors
MOHAMMAD AHEAD
05/01/2026
Special inspection requirement — Structural Steel - Welding
MOHAMMAD AHEAD
05/01/2026
Special inspection requirement — Structural Steel - Details
MOHAMMAD AHEAD
05/01/2026
Special inspection requirement — Final
ARIEL GOLSHAN
05/01/2026
Special inspection requirement — Concrete - Cast-In-Place
MOHAMMAD AHEAD
05/01/2026
Special inspection requirement — Structural Steel - High Strength Bolting
MOHAMMAD AHEAD
05/01/2026
Special inspection requirement — Structural Cold-Formed Steel
MOHAMMAD AHEAD
04/17/2026
Objection resolved — Resolved
04/17/2026
Objection resolved — Resolved
04/17/2026
Objection resolved — Resolved
04/17/2026
Objection resolved — Resolved
04/17/2026
Objection resolved — Resolved
04/17/2026
Objection resolved — Resolved
04/17/2026
Objection resolved — Resolved
04/17/2026
Special inspection requirement — Maintenance information
ARIEL GOLSHAN
04/17/2026
Special inspection requirement — Lighting controls
ARIEL GOLSHAN
04/17/2026
Special inspection requirement — Metering
ARIEL GOLSHAN
04/17/2026
Special inspection requirement — Permanent certificate
ARIEL GOLSHAN
03/24/2026
Objection raised — Fire_Protection
03/19/2026
Objection raised — Energy
03/19/2026
Objection raised — Admin
03/19/2026
Objection raised — Cost
03/19/2026
Objection raised — Zoning
03/19/2026
Objection raised — Zoning
03/19/2026
Objection raised — Mechanical
03/09/2026
Filed — Alteration CO
Convert a (2) family into a (1) Family. New Enlargement at the rear of the building. installation of partitions, wall and floor finishes with new windows and doors as per plan.
B01345631-I1
02/26/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
ARIEL GOLSHAN
02/26/2026
Special inspection requirement — Fenestration areas
ARIEL GOLSHAN
Latest 60 of 70 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWStructuralPermit IssuedSIMONSAYS CORP08/14/2026
DOB NOWPlumbingPermit IssuedA.M.N. CORPORATION07/06/2026
DOB NOWGeneral ConstructionPermit IssuedSIMONSAYS CORP07/02/2026
BISOTISSUEDL & H GENERAL CONSTRUCTIO01/31/2023
BISEQISSUEDL & H GENERAL CONSTRUCTIO01/31/2023
BISPLISSUEDNOPHIER PLUMBING & HTG IN09/23/2022
BISPLISSUEDPETER MICELI PLUMBING12/04/2014
BISMHISSUEDJUSTIN KELLY11/14/2014
BISOTISSUEDJUSTIN KELLY11/14/2014
BISEQISSUEDJUSTIN KELLY11/14/2014
1 project · most recent 08/14/2026
General Wiring
FiledStatusContractorScope
08/14/2026Permit IssuedBERGER QUALITY ELEC'L CONGeneral Wiring
1 project · most recent 08/17/2026
Steel Concrete
FiledStatusContractorScope
08/17/2026Permit IssuedSIMONSAYS CORPSteel, Concrete
▾Special Inspection Requirements (DOB NOW) — 32
DateRequirementInspectorRole
08/14/2026FinalARIEL GOLSHANprogress
08/14/2026Subgrade InspectionsMOHAMMAD AHEADspecial
08/14/2026Concrete - Cast-In-PlaceMOHAMMAD AHEADspecial
08/14/2026Footing and FoundationMOHAMMAD AHEADprogress
06/04/2026Structural Wood FrameMOHAMMAD AHEADprogress
06/01/2026Structural Stability – Alterations of existing buildingsMOHAMMAD AHEADspecial
05/07/2026Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationMOHAMMAD AHEADspecial
05/06/2026HVAC-R and service water piping design and insulationARIEL GOLSHANenergy_progress
05/06/2026Fire-Resistant Penetrations and JointsARIEL GOLSHANspecial
05/06/2026Energy Code Compliance InspectionsARIEL GOLSHANprogress
05/01/2026Post-installed AnchorsMOHAMMAD AHEADspecial
05/01/2026Structural Steel - WeldingMOHAMMAD AHEADspecial
05/01/2026Structural Steel - DetailsMOHAMMAD AHEADspecial
05/01/2026FinalARIEL GOLSHANprogress
05/01/2026Concrete - Cast-In-PlaceMOHAMMAD AHEADspecial
05/01/2026Structural Steel - High Strength BoltingMOHAMMAD AHEADspecial
05/01/2026Structural Cold-Formed SteelMOHAMMAD AHEADspecial
04/17/2026Maintenance informationARIEL GOLSHANenergy_progress
04/17/2026Lighting controlsARIEL GOLSHANenergy_progress
04/17/2026MeteringARIEL GOLSHANenergy_progress
04/17/2026Permanent certificateARIEL GOLSHANenergy_progress
02/26/2026Fenestration and door U-factor and product ratingsARIEL GOLSHANenergy_progress
02/26/2026Fenestration areasARIEL GOLSHANenergy_progress
02/26/2026Insulation placement and R valuesARIEL GOLSHANenergy_progress
02/26/2026Air barrier - visual inspectionARIEL GOLSHANenergy_progress
Latest 25 of 32.
▾Documents — 81 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
08/16/2026B01345631-I1Request digital key ↗
08/16/2026B01345631-S3Request digital key ↗
08/16/2026B01345631-P1Request digital key ↗
Showing 3 of 5 on file for this type
▸Applications & Permits17
▸BISPLAN / WORK APPROVAL APPLICATION12
06/28/2023321217937Open ↗
06/16/2023321217937Open ↗
12/05/2022321217937Open ↗
Showing 3 of 12 on file for this type
▸BISWORK PERMIT APPLICATION5
02/01/2023321217937Open ↗
02/01/2023321217937Open ↗
09/27/2022321217937Open ↗
Showing 3 of 5 on file for this type
▸Zoning, Tax Lot & Property Records3
▸DOB NOWZD1: DOB Zoning Diagram2
08/16/2026B01345631-I1Open ↗
08/13/2026B01345631-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)1
08/13/2026B01345631-I1Open ↗
▸Seals & Professional Certifications17
▸DOB NOWProgress Inspector Seal & Signature7
09/21/2026B01345631-P1Open ↗
08/27/2026B01345631-S2Open ↗
08/27/2026B01345631-S2Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/16/2026B01345631-S4Open ↗
08/16/2026B01345631-S2Open ↗
08/16/2026B01345631-S3Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
09/21/2026B01345631-P1Open ↗
08/27/2026B01345631-S2Open ↗
08/26/2026B01345631-S3Open ↗
Showing 3 of 5 on file for this type
▸Trade Schedules & Equipment5
▸BISSCHEDULE B - PLUMBING3
11/14/2022321217937Open ↗
04/25/2022321217937Open ↗
04/12/2022321217937Open ↗
▸BISEQUIPMENT USE PERMITS1
07/07/2023321217937Open ↗
▸BISEQUIPMENT USE APPLICATION/PERMIT1
07/07/2023321217937Open ↗
▸Safety & Tenant Protection1
▸DOB NOWStreet Tree Checklist1
08/13/2026B01345631-I1Open ↗
▸Environmental & Asbestos6
▸DOB NOWDEP ACP-5: Asbestos Assessment Report5
08/16/2026B01345631-S3Open ↗
08/16/2026B01345631-P1Open ↗
08/15/2026B01345631-S2Open ↗
Showing 3 of 5 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
11/19/2014321217937Open ↗
▸Energy Compliance4
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
07/07/2023321217937Open ↗
04/20/2022321217937Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
11/19/2014321217937Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
07/07/2023321217937Open ↗
▸Inspections & Test Reports5
▸BISTECHNICAL REPORT: RESPONSIBILITY5
07/07/2023321217937Open ↗
07/07/2023321217937Open ↗
07/07/2023321217937Open ↗
Showing 3 of 5 on file for this type
▸Approvals, Objections & Sign-offs3
▸BISSUPERSEDING LETTER2
02/01/2023321217937Open ↗
09/27/2022321217937Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
07/13/2023321217937Open ↗
▸Cost, Insurance & Ownership3
▸BISCOST AFFIDAVIT3
07/07/2023321217937Open ↗
07/07/2023321217937Open ↗
11/19/2014321217937Open ↗
▸Filing & Intake Forms5
▸BISADDITIONAL INFORMATION4
06/28/2023321217937Open ↗
08/16/2022321217937Open ↗
08/10/2022321217937Open ↗
Showing 3 of 4 on file for this type
▸BISBOROUGH INTAKE FORM1
09/27/2022321217937Open ↗
▸Other Documents7
▸DOB NOWPlot Diagram3
08/16/2026B01345631-P1Open ↗
08/15/2026B01345631-S4Open ↗
08/13/2026B01345631-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/16/2026B01345631-I1Open ↗
08/13/2026B01345631-I1Open ↗
▸DOB NOWProperty Ownership Certification1
08/16/2026B01345631-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/13/2026B01345631-I1Open ↗