| Owner | Filings | Most Recent |
|---|---|---|
| KSTM EXPEDIRING SERVICES | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ARCHITECTURE DESIGN, PLLC | 11 | 04/06/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| DKG DESIGN SPACE PLANNING | 10 | 03/21/2026 |
| KSTM EXPEDIRING SERVICES | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| GARDEN STATE OF NJ DATA* | General Contractor | 9 | 03/21/2026 |
| DONE RIGHT KITCHEN EXHAUS | General Contractor | 3 | 03/21/2026 |
| DOUG'S PLBG & HTG SERV CO | Plumbing | 2 | 07/08/2026 |
| CONTROL SPEC ELECL SYSTEM | Electrical | 1 | 03/22/2026 |
| M & M PIPING AND HEATING | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AA BUILDING & INSPECTION | 1519 | 11 | 04/06/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | GARDEN STATE OF NJ DATA* | 05/09/2025 |
| DOB NOW | Plumbing | Permit Issued | M & M PIPING AND HEATING | 08/14/2024 |
| DOB NOW | General Construction | Signed-off | GARDEN STATE OF NJ DATA* | 08/07/2024 |
| DOB NOW | Mechanical Systems | Signed-off | DONE RIGHT KITCHEN EXHAUS | 11/22/2021 |
| DOB NOW | Plumbing | Signed-off | DOUG'S PLBG & HTG SERV CO | 11/05/2021 |
| DOB NOW | Plumbing | Signed-off | DOUG'S PLBG & HTG SERV CO | 08/05/2021 |
| DOB NOW | Mechanical Systems | Signed-off | GARDEN STATE OF NJ DATA* | 06/07/2021 |
| BIS | OT | ISSUED | EKRA BUILDERS & CONSTRUCT | 03/08/2019 |
| BIS | FP | RE-ISSUED | IDEAL FIRE CONTROL, INC | 05/19/2000 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 04/06/2025 | Signed-off | GARDEN STATE OF NJ DATA* | Heating and Air Conditioning Systems | Heat / Cool Daikin MAKE: DAIKIN INDUSTRIES, LTD | MODEL# 4MXS36WMVJU9 36,000 BTU · Condensing Unit ×1 MAKE: DAIKIN INDUSTRIES, LTD | MODEL# FTXS09WVJU9 9,000 BTU · Fan Coil Indoor ×1 MODEL: DAIKIN INDUSTRIES, LTD | MODEL# FTXS09WVJU9 9,000 BTU · Fan Coil Indoor ×1 MODEL: DAIKIN INDUSTRIES, LTD | MODEL# FTXS18WVJU9 18,000 BTU · Fan Coil Indoor ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/06/2025 | Permit Issued | M & M PIPING AND HEATING | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/23/2025 | Complete | CONTROL SPEC ELECL SYSTEM | General Wiring |
| 07/30/2021 | Permit Issued | GMJ ELECTRIC CORP | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/15/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/19/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 02/13/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/03/2025 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 11/25/2024 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 09/24/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/18/2025 | Energy Code Compliance Inspections | Younes Abouyaala | progress |
| 04/18/2025 | Energy Code Compliance Inspections | Younes Abouyaala | progress |
| 04/18/2025 | Fire-Resistant Penetrations and Joints | Younes Abouyaala | special |
| 04/18/2025 | Final | NAVEEN KUMAR | progress |
| 04/18/2025 | Insulation placement and R values | Younes Abouyaala | energy_progress |
| 04/18/2025 | Fire-Resistant Penetrations and Joints | Younes Abouyaala | special |
| 04/18/2025 | HVAC-R and service water piping design and insulation | Younes Abouyaala | energy_progress |
| 04/05/2025 | Insulation placement and R values | Younes Abouyaala | energy_progress |
| 04/05/2025 | Fire-Resistant Penetrations and Joints | Younes Abouyaala | special |
| 04/05/2025 | Energy Code Compliance Inspections | Younes Abouyaala | progress |
| 04/05/2025 | HVAC-R and service water piping design and insulation | Younes Abouyaala | energy_progress |
| 04/05/2025 | Fire-Resistant Penetrations and Joints | Younes Abouyaala | special |
| 04/05/2025 | Energy Code Compliance Inspections | Younes Abouyaala | progress |
| 04/05/2025 | Final | NAVEEN KUMAR | progress |
| 11/14/2022 | HVAC insulation and sealing | Younes Abouyaala | energy_progress |
| 11/14/2022 | Fire-Resistant Penetrations and Joints | Younes Abouyaala | special |
| 11/14/2022 | Energy Code Compliance Inspections | Younes Abouyaala | progress |
| 11/08/2022 | Energy Code Compliance Inspections | Younes Abouyaala | progress |
| 11/08/2022 | HVAC insulation and sealing | Younes Abouyaala | energy_progress |
| 11/08/2022 | Fire-Resistant Penetrations and Joints | Younes Abouyaala | special |
| 08/07/2021 | HVAC insulation and sealing | Younes Abouyaala | energy_progress |
| 08/07/2021 | Fire-Resistant Penetrations and Joints | Younes Abouyaala | special |
| 08/07/2021 | Mechanical Systems | Younes Abouyaala | special |
| 08/07/2021 | Structural Stability – Alterations of existing buildings | Younes Abouyaala | special |
| 08/07/2021 | Energy Code Compliance Inspections | Younes Abouyaala | progress |