1930Year Built
3Stories
K4Building Class
R6BZoning
11,400 sfGross Floor Area
7Units
Rent Stabilized0 Open ViolationsFDNY Report ↗
Predominantly retail with other uses · Owner of record: CWB PROPERTIES, LLC, A NY LIMITED LIABIL ITY CO · 5,260 sf lot · 2.17 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingCivil
Permit Issued — active, not yet Signed-off
Floor 3Under Construction13p · 1 filing · 20 docs
Floor 2Under Construction16p · 1 filing · 20 docs
Floor 1
CellarUnder Construction5p · 1 filing · 20 docs
Site & exteriorUnder Construction19p · 3 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
CWB PROPERTIES, LLC, A NY LIMITED LIABIL ITY CO103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
05/04/2022$3.1M—Private party → CWB PROPERTIES, LLC, A NY LIMITED LIABILITY CO$276/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
BEST ENGINEERING TECHNOLOGY DESIGN708/20/2026
ASHRAF CORP103/18/2025
GINO O. LONGO, ARCHITECT102/24/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ANTHONY TRANCHINA GENERAL CONTGeneral Contractor403/21/2026
DYNAMIX SCAFFOLD GROUP LLGeneral Contractor403/21/2026
BONIM REMODELING INCGeneral Contractor204/09/2026
PETER MICELI PLUMBINGPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CNA BUILDERS AND CONSULTA2898608/20/2026
HRF SERVICES CORP5616102/24/2025
Building Lifecycle
All (78)Filed (9)Permit Issued (7)Violation (21)Inspection (3)Objection (20)Special Inspection (18)
08/20/2026
Filed — Alteration
BOILER INSTALLATION
Q01200131-P2
08/20/2026
Filed — Alteration
BOILER INSTALLATION
Q01200131-P3
06/15/2026
Special inspection requirement — Fire-Resistance Rated Construction
Choudhry Yusaf
06/15/2026
Special inspection requirement — Energy Code Compliance Inspections
Choudhry Yusaf
06/15/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Choudhry Yusaf
05/22/2026
Filed — Alteration
BOILER INSTALLATION
Q01200131-P1
04/28/2026
Special inspection requirement — Energy Code Compliance Inspections
Choudhry Yusaf
04/28/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Choudhry Yusaf
12/16/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
12/12/2025
Objection resolved — Addressed
12/12/2025
Objection resolved — Addressed
12/12/2025
Objection resolved — Addressed
12/11/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
11/24/2025
Objection raised — Mechanical
11/24/2025
Objection raised — Mechanical
11/24/2025
Objection raised — Plumbing
11/06/2025
Filed — Alteration
BOILER INSTALLATION
Q01200131-S3
11/06/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
11/06/2025
Special inspection requirement — Heating Systems
10/07/2025
Permit issued — Plumbing
Q01200131-S1-PL
08/27/2025
Objection resolved — Addressed
08/27/2025
Objection resolved — Addressed
08/25/2025
Permit issued — General Construction
Q01200131-I1-GC
08/25/2025
Permit issued — Mechanical Systems
Q01200131-S2-MS
08/21/2025
Objection raised — Admin
08/21/2025
Objection raised — Cost
08/14/2025
Objection resolved — Addressed
08/11/2025
Objection resolved — Addressed
08/08/2025
Objection raised — Admin
08/08/2025
Objection raised — Scope
07/29/2025
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
07/23/2025
Filed — Alteration
BOILER INSTALLATION
Q01200131-I1
07/23/2025
Filed — Alteration
BOILER INSTALLATION
Q01200131-S2
07/23/2025
Filed — Alteration
BOILER INSTALLATION
Q01200131-S1
07/23/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Choudhry Yusaf
07/23/2025
Special inspection requirement — HVAC-R and service water heating system controls
Choudhry Yusaf
07/23/2025
Special inspection requirement — HVAC-R and service water heating equipment
Choudhry Yusaf
06/03/2025
Special inspection requirement — Energy Code Compliance Inspections
Choudhry Yusaf
06/03/2025
Special inspection requirement — Final
Choudhry Yusaf
06/03/2025
Special inspection requirement — Mechanical Systems
Choudhry Yusaf
06/03/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Choudhry Yusaf
06/03/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Choudhry Yusaf
05/29/2025
Permit issued — Structural
Q01170136-I1-GC-CX
03/27/2025
Permit issued — Structural
Q01170136-I1-GC-CX
03/19/2025
Permit issued — Supported Scaffold
Q01189505-I1-SF
03/19/2025
Permit issued — Supported Scaffold
Q01189505-I1-SH
03/18/2025
Filed — Alteration
INSTALL OF HEAVY DUTY SIDEWALK SHED AND PIPE SCAFFOLD AS PER PLANS IN COMPLIANCE WITH CHAPTER 33 NYCBC. NO CHANGE IN USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
Q01189505-I1
03/10/2025
Objection resolved — Addressed
03/10/2025
Objection resolved — Addressed
03/10/2025
Objection resolved — Addressed
03/06/2025
Objection raised — Cost
03/06/2025
Objection raised — Other
03/06/2025
Objection raised — Other
02/24/2025
Filed — Alteration
APPLICATION HEREWITH FILED FOR PROPOSED FACADE RENOVATION. NO CHANGE IN OCCUPANCY, USE, EGRESS, OR BULK.
Q01170136-I1
01/22/2025
Special inspection requirement — Masonry
FAHAD FATEH
01/22/2025
Special inspection requirement — Final
FAHAD FATEH
01/22/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
FAHAD FATEH
10/17/2024
Violation issued (ECB, closed)
Boilers
09/23/2024
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/30/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
Latest 60 of 78 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedPETER MICELI PLUMBING10/07/2025
DOB NOWGeneral ConstructionSigned-offBONIM REMODELING INC08/25/2025
DOB NOWMechanical SystemsPermit IssuedBONIM REMODELING INC08/25/2025
DOB NOWStructuralSigned-offANTHONY TRANCHINA GENERAL05/29/2025
DOB NOWStructuralSigned-offANTHONY TRANCHINA GENERAL03/27/2025
DOB NOWSupported ScaffoldPermit IssuedDYNAMIX SCAFFOLD GROUP LL03/19/2025
DOB NOWSupported ScaffoldPermit IssuedDYNAMIX SCAFFOLD GROUP LL03/19/2025
1 project · most recent 08/20/2026
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
08/20/2026Permit IssuedBONIM REMODELING INCHeating and Air Conditioning Systems
Heat / Cool
Mitsubishi Electric MXZ-4C42NA3-U1 25,000 BTU · Split System ×1
1 project · most recent 08/20/2026
Gas Water/Sanitary
FiledStatusContractorScope
08/20/2026Permit IssuedPETER MICELI PLUMBINGGas, Water/Sanitary
2 projects · most recent 04/17/2025
General Wiring
FiledStatusContractorScope
04/17/2025CompleteBROOKYLN SOLARWORKS, LLC—
07/29/2022Permit IssuedRIVIERA ELECTRIC CORPGeneral Wiring
1 project · most recent 02/24/2025
Masonry
FiledStatusContractorScope
02/24/2025Signed-offANTHONY TRANCHINA GENERALMasonry
1 project · most recent 03/18/2025
Scaffold Sidewalk Shed
FiledStatusContractorScope
03/18/2025Permit IssuedDYNAMIX SCAFFOLD GROUP LLScaffold, Sidewalk Shed
1 project · most recent 08/20/2026
Tenant Protection Plan 72 Hour
FiledStatusContractorScope
08/20/2026Permit IssuedPETER MICELI PLUMBINGTenant Protection Plan 72 Hour
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
12/16/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
12/11/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
07/29/2025Pass-Final General Construction Non-Directive 14PassView ↗
▾Special Inspection Requirements (DOB NOW) — 18
DateRequirementInspectorRole
06/15/2026Fire-Resistance Rated ConstructionChoudhry Yusafprogress
06/15/2026Energy Code Compliance InspectionsChoudhry Yusafprogress
06/15/2026Fire-Resistant Penetrations and JointsChoudhry Yusafspecial
04/28/2026Energy Code Compliance InspectionsChoudhry Yusafprogress
04/28/2026Fire-Resistant Penetrations and JointsChoudhry Yusafspecial
11/06/2025Fire-Resistant Penetrations and Joints—special
11/06/2025Heating Systems—special
07/23/2025HVAC-R and service water piping design and insulationChoudhry Yusafenergy_progress
07/23/2025HVAC-R and service water heating system controlsChoudhry Yusafenergy_progress
07/23/2025HVAC-R and service water heating equipmentChoudhry Yusafenergy_progress
06/03/2025Energy Code Compliance InspectionsChoudhry Yusafprogress
06/03/2025FinalChoudhry Yusafprogress
06/03/2025Mechanical SystemsChoudhry Yusafspecial
06/03/2025Fire-Resistant Penetrations and JointsChoudhry Yusafspecial
06/03/2025Fire-Resistant Penetrations and JointsChoudhry Yusafspecial
01/22/2025MasonryFAHAD FATEHspecial
01/22/2025FinalFAHAD FATEHprogress
01/22/2025Structural Stability – Alterations of existing buildingsFAHAD FATEHspecial
▾Documents — 41 on file (BIS + DOB NOW)
▸Plans & Drawings9
▸DOB NOWPlans/Sketch9
08/20/2026Q01170136-I1Request digital key ↗
08/20/2026Q01189505-I1Request digital key ↗
08/16/2026Q01200131-P1Request digital key ↗
Showing 3 of 9 on file for this type
▸Seals & Professional Certifications24
▸DOB NOWDPL-1: Design Professional Seal & Signature9
08/20/2026Q01170136-I1Open ↗
08/20/2026Q01189505-I1Open ↗
08/16/2026Q01200131-P2Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWProgress Inspector Seal & Signature9
09/23/2026Q01200131-S2Open ↗
09/23/2026Q01200131-S2Open ↗
09/23/2026Q01200131-S2Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
09/23/2026Q01200131-S2Open ↗
09/23/2026Q01200131-S2Open ↗
08/28/2026Q01200131-I1Open ↗
Showing 3 of 6 on file for this type
▸Environmental & Asbestos8
▸DOB NOWDEP ACP-5: Asbestos Assessment Report8
08/20/2026Q01170136-I1Open ↗
08/16/2026Q01200131-P3Open ↗
08/16/2026Q01200131-P1Open ↗
Showing 3 of 8 on file for this type