| Owner | Filings | Most Recent |
|---|---|---|
| 1357 ASSOCIATES | 23 | 07/08/2026 |
| 578 ASSOCIATES LLC | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/08/2018 | $220K | — | — → — | $93/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| JIM KUSI PE | 8 | 12/03/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| DOCKERY ASSOCIATES | 16 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| C JAMES PLBG & HTG INC | Plumbing | 3 | 07/08/2026 |
| PONCE CONSTRUCTION INC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| JIM KUSI, PE | 3757 | 4 | 12/03/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Boiler Equipment | Signed-off | C JAMES PLBG & HTG INC | 12/17/2024 |
| DOB NOW | Boiler Equipment | Signed-off | C JAMES PLBG & HTG INC | 09/20/2024 |
| DOB NOW | Plumbing | Signed-off | C JAMES PLBG & HTG INC | 08/07/2023 |
| DOB NOW | General Construction | Permit Issued | PONCE CONSTRUCTION INC | 06/28/2023 |
| BIS | EQ | ISSUED | ROCKLEDGE SCAFFOLD CORP | 10/09/2001 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/30/2024 | Signed-off | C JAMES PLBG & HTG INC | Gas |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/03/2024 | Complete | E.T. ELEC'L CONTR CO INC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/20/2024 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 11/06/2024 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 06/28/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/18/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/08/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 09/08/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/08/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/09/2024 | HVAC-R and service water heating equipment | Jim Kusi | energy_progress |
| 12/09/2024 | HVAC-R and service water piping design and insulation | Jim Kusi | energy_progress |
| 12/09/2024 | HVAC-R and service water heating system controls | Jim Kusi | energy_progress |
| 11/26/2024 | Heating Systems | Jim Kusi | special |
| 05/20/2024 | Fire-Resistant Penetrations and Joints | Jim Kusi | special |
| 05/14/2024 | Fire-Resistant Penetrations and Joints | Jim Kusi | special |
| 05/08/2024 | Final | Jim Kusi | progress |
| 04/23/2024 | Fire-Resistant Penetrations and Joints | Jim Kusi | special |
| 04/23/2024 | Final | Jim Kusi | progress |