← Back
One family attached or semi-detached
58-55 197 STREET
QUEENS · BIN 4128660
💬 Discuss this project
1960Year Built
1Stories
A5Building Class
R3-2Zoning
828 sfGross Floor Area
1Units
One family attached or semi-detached · 2,657 sf lot · 0.31 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralGeneral
Roof4p · 1 filing · 20 docs
Basement3p · 1 filing · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
09/24/2025$768K—Private party → Private party$928/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TAN ARCHITECT P.C303/05/2026
Building Lifecycle
All (61)Filed (3)Objection (29)Special Inspection (29)
08/13/2026
Objection resolved — Resolved
08/13/2026
Objection resolved — Resolved
06/05/2026
Objection raised — Zoning
04/20/2026
Objection resolved — Resolved
04/20/2026
Objection resolved — Resolved
04/20/2026
Objection resolved — Addressed
04/15/2026
Objection raised — Scope
04/09/2026
Objection raised — Structural
04/09/2026
Objection raised — Zoning
03/05/2026
Filed — ALT-CO - New Building with Existing Elements to Remain
PROPOSED CONVERSION FROM ONE-FAMILY TO TWO-FAMILY RESIDENCE WITH HORIZONTAL AND VERTICAL ENLARGEMENT.
Q01325642-S2
03/04/2026
Special inspection requirement — Air barrier — testing
03/04/2026
Special inspection requirement — Fenestration air leakage
03/04/2026
Special inspection requirement — Air barrier - visual inspection
03/04/2026
Special inspection requirement — Permanent certificate
03/04/2026
Special inspection requirement — Insulation placement and R values
03/04/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
03/04/2026
Special inspection requirement — Fenestration areas
02/24/2026
Objection resolved — Addressed
02/24/2026
Special inspection requirement — Maintenance information
02/09/2026
Objection resolved — Resolved
02/09/2026
Objection resolved — Addressed
02/09/2026
Objection resolved — Addressed
02/09/2026
Objection resolved — Addressed
02/02/2026
Objection raised — Scope
02/02/2026
Objection raised — Energy
02/02/2026
Objection raised — Plumbing
02/02/2026
Objection raised — Other
02/02/2026
Objection resolved — Addressed
01/30/2026
Objection resolved — Addressed
01/20/2026
Objection raised — Zoning
01/20/2026
Objection raised — Cost
01/20/2026
Objection raised — Zoning
01/20/2026
Objection raised — Fire_Protection
01/20/2026
Objection raised — Admin
01/20/2026
Objection raised — Inspections
01/20/2026
Objection raised — Admin
01/20/2026
Objection raised — Structural
01/20/2026
Objection raised — Energy
01/19/2026
Filed — ALT-CO - New Building with Existing Elements to Remain
PROPOSED CONVERSION FROM ONE-FAMILY TO TWO-FAMILY RESIDENCE WITH HORIZONTAL AND VERTICAL ENLARGEMENT.
Q01325642-S1
01/19/2026
Special inspection requirement — HVAC-R and service water heating equipment
01/19/2026
Special inspection requirement — HVAC-R and service water heating system controls
01/19/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
01/19/2026
Special inspection requirement — Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities
01/19/2026
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
01/19/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
01/16/2026
Special inspection requirement — Final
01/16/2026
Special inspection requirement — Footing and Foundation
12/19/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
PROPOSED CONVERSION FROM ONE-FAMILY TO TWO-FAMILY RESIDENCE WITH HORIZONTAL AND VERTICAL ENLARGEMENT.
Q01325642-I1
12/19/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
12/19/2025
Special inspection requirement — Air barrier - visual inspection
12/19/2025
Special inspection requirement — Fenestration areas
12/19/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
12/19/2025
Special inspection requirement — Fenestration air leakage
12/19/2025
Special inspection requirement — Electric vehicle service equipment requirements
12/19/2025
Special inspection requirement — Air barrier — testing
12/19/2025
Special inspection requirement — Metering
12/19/2025
Special inspection requirement — Permanent certificate
12/19/2025
Special inspection requirement — Interior lighting power
12/19/2025
Special inspection requirement — Insulation placement and R values
12/19/2025
Special inspection requirement — Fire-Resistance Rated Construction
Latest 60 of 61 events.
Nothing on file for this building.
1 project · most recent 03/05/2026
Gas Storm Water/Sanitary
FiledStatusContractorScope
03/05/2026——Gas, Storm, Water/Sanitary
1 project · most recent 03/05/2026
Wood
FiledStatusContractorScope
03/05/2026——Wood
▾Special Inspection Requirements (DOB NOW) — 29
DateRequirementInspectorRole
03/04/2026Air barrier — testing —energy_progress
03/04/2026Fenestration air leakage—energy_progress
03/04/2026Air barrier - visual inspection—energy_progress
03/04/2026Permanent certificate—energy_progress
03/04/2026Insulation placement and R values—energy_progress
03/04/2026Fenestration and door U-factor and product ratings—energy_progress
03/04/2026Fenestration areas—energy_progress
02/24/2026Maintenance information—energy_progress
01/19/2026HVAC-R and service water heating equipment—energy_progress
01/19/2026HVAC-R and service water heating system controls—energy_progress
01/19/2026Fire-Resistant Penetrations and Joints—special
01/19/2026Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities—special
01/19/2026Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation—special
01/19/2026HVAC-R and service water piping design and insulation—energy_progress
01/16/2026Final—progress
01/16/2026Footing and Foundation—progress
12/19/2025Fire-Resistant Penetrations and Joints—special
12/19/2025Air barrier - visual inspection—energy_progress
12/19/2025Fenestration areas—energy_progress
12/19/2025Fenestration and door U-factor and product ratings—energy_progress
12/19/2025Fenestration air leakage—energy_progress
12/19/2025Electric vehicle service equipment requirements—energy_progress
12/19/2025Air barrier — testing —energy_progress
12/19/2025Metering—energy_progress
12/19/2025Permanent certificate—energy_progress
Latest 25 of 29.
▾Documents — 18 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/17/2026Q01325642-I1Request digital key ↗
08/17/2026Q01325642-S2Request digital key ↗
08/15/2026Q01325642-S1Request digital key ↗
▸Zoning, Tax Lot & Property Records3
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/14/2026Q01325642-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)1
08/14/2026Q01325642-I1Open ↗
▸DOB NOWZD1: DOB Zoning Diagram1
08/17/2026Q01325642-I1Open ↗
▸Seals & Professional Certifications3
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/17/2026Q01325642-I1Open ↗
08/17/2026Q01325642-S1Open ↗
08/17/2026Q01325642-S2Open ↗
▸Safety & Tenant Protection1
▸DOB NOWStreet Tree Checklist1
08/14/2026Q01325642-I1Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/17/2026Q01325642-S2Open ↗
08/15/2026Q01325642-S1Open ↗
08/14/2026Q01325642-I1Open ↗
▸Other Documents5
▸DOB NOWSite Survey: Initial2
08/17/2026Q01325642-S2Open ↗
08/14/2026Q01325642-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/17/2026Q01325642-S2Open ↗
08/14/2026Q01325642-I1Open ↗
▸DOB NOWProperty Ownership Certification1
08/14/2026Q01325642-I1Open ↗