← Back
BuildNYC
Banking facility, with or without parking
58 BOWERY
MANHATTAN · BIN 1002428
💬 Discuss this project
1924Year Built
1Stories
K7Building Class
C6-1GZoning
17,616 sfGross Floor Area
3Units
2 Active Violations 2 old, status unconfirmed ▸FDNY Report ↗
Banking facility, with or without parking · 8,804 sf lot · 2 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofJLL - HSBC Bank USA, HSBC Bank7p · 2 filings · 20 docs
Floor 2Alexander Wang, HSBC BankUnder Construction27p · 4 filings · 20 docs
Floor 1Alexander Wang Fashion Show, KCD Worldwide +2Under Construction13p · 11 filings · 20 docs
CellarAlexander Wang, HSBC BankUnder Construction3p · 4 filings · 20 docs
Sub-BasementHSBC Bank USA, HSBC Bank5p · 3 filings · 20 docs
Site & exteriorHSBC Bank1p · 1 filing · 4 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
HSBC Bank USA2907/08/2026
Manhattan Savings Bank203/21/2026
HSBC103/21/2026
HSBC Bank USA National As103/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
07/24/2025$9.5M—HSBC BANK USA, NATIONAL ASSOCIATION, AS SUCCESSOR → Private party$539/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Kett Murphy410/06/2026
Valerio Architects212/17/2025
Gregory Schnackel212/17/2025
SYNC Architecture209/08/2025
Murdoch Engineering103/06/2023
GNP Design Group205/27/2022
Michael Savarese Assc., Architects105/13/2022
Enthink Engineers212/29/2021
DJM Consulting Engineering509/08/2021
KBN Services109/01/2021
Metro Structures205/23/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Kazam Consultants203/21/2026
Valerio Architects203/21/2026
Desarno Associates1603/21/2026
Municipal Building Consultants103/21/2026
Pinnacle Building Con203/21/2026
Storn103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Henegan Construction CoGeneral Contractor307/08/2026
StornGeneral Contractor303/21/2026
Winick ProductionsGeneral Contractor209/15/2026
JascoScaffold207/08/2026
Elemco Testing Co Inc DbaElectrical203/21/2026
Computer Cool/Ice AgeGeneral Contractor203/21/2026
Aqua Plumbing & HeatingPlumbing107/08/2026
Lab Plumbing & Heating CoPlumbing107/08/2026
Bestco General Electric MaintenanceElectrical103/21/2026
MPS Plumbing & HeatingPlumbing107/08/2026
Kleinknecht Electric CoElectrical103/22/2026
A.W. & S. Construction CoGeneral Contractor107/08/2026
Legacy Builders/DevelopersGeneral Contractor104/09/2026
Pro-H DevelopmentGeneral Contractor108/26/2026
National MaintenanceSign hanger107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Schnackel Engineers1821112/17/2025
Winton Group Architecture4343605/27/2022
Superior - Home Inspectio1804205/23/2021
Building Lifecycle
All (146)Filed (24)Permit Issued (16)Signed Off (12)Violation (53)Inspection (5)Objection (6)Special Inspection (30)
10/06/2026
Filed — No Work
M01466126-I1
09/29/2026
Signed off — Alteration
M01320036-I1
09/29/2026
Signed off — Alteration
UPDATES TO 2ND FLOOR BANK PER PLANS FILED HEREWITH. INCLUDES MINOR UPDATES TO NON BEARING PARTITION WALLS, UPDATED FINISHES, FURNITURE AND FIXTURES.
M01320025-I1
09/14/2026
Permit issued — General Construction
M01449960-I1-GC
09/01/2026
Filed — Alteration
Temporary art build out.
M01449960-I1
08/26/2026
Filed — No Work
M01447223-I1
08/22/2026
Special inspection requirement — Final
Kett Murphy
08/05/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
05/28/2026
Permit issued — Plumbing
M01320036-I1-PL
05/12/2026
Permit issued — General Construction
M01320025-I1-GC
02/13/2026
Objection resolved — Addressed
02/13/2026
Objection resolved — Addressed
02/12/2026
Objection resolved — Addressed
02/05/2026
Objection raised — Other
02/05/2026
Objection raised — Other
02/05/2026
Objection raised — Other
02/03/2026
Filed — No Work
M01351146-I1
01/21/2026
Permit issued — Plumbing
M01320036-I1-PL
01/05/2026
Permit issued — General Construction
M01320025-I1-GC
12/17/2025
Filed — Alteration
M01320036-I1
12/17/2025
Filed — Alteration
UPDATES TO 2ND FLOOR BANK PER PLANS FILED HEREWITH. INCLUDES MINOR UPDATES TO NON BEARING PARTITION WALLS, UPDATED FINISHES, FURNITURE AND FIXTURES.
M01320025-I1
12/17/2025
Filed — Alteration
M01320032-I1
12/01/2025
Signed off — Alteration
Temporary and portable structures for a fashion show in the existing bank hall. Structures removed at the end of the programing. No changes to existing structures, use or egress.
M01281958-I1
11/24/2025
Special inspection requirement — Final
Niccolo Valerio
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
09/10/2025
Permit issued — General Construction
M01281958-I1-GC
09/08/2025
Filed — Alteration
Temporary and portable structures for a fashion show in the existing bank hall. Structures removed at the end of the programing. No changes to existing structures, use or egress.
M01281958-I1
09/08/2025
Filed — No Work
M01280788-I1
09/05/2025
Signed off — Alteration
MINOR INTERIOR REMOVAL OF NON-STRUCTURAL PARTITIONS, FURNITURE, AND SELECT FINISHES. NO CHANGES TO EXTERIOR OF BUILDING OR STRUCTURAL MODIFICATIONS. INCLUDES WORK AT FLOOR 001 ONLY. NO SCOPE AT 2ND FLOOR AND BASEMENT
M01261605-I1
09/04/2025
Special inspection requirement — Final
ANDY ENGLER ROTH
08/06/2025
Permit issued — General Construction
M01261605-I1-GC
08/01/2025
Filed — Alteration
MINOR INTERIOR REMOVAL OF NON-STRUCTURAL PARTITIONS, FURNITURE, AND SELECT FINISHES. NO CHANGES TO EXTERIOR OF BUILDING OR STRUCTURAL MODIFICATIONS. INCLUDES WORK AT FLOOR 001 ONLY. NO SCOPE AT 2ND FLOOR AND BASEMENT
M01261605-I1
07/25/2025
Special inspection requirement — Final
Niccolo Valerio
09/23/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/30/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
04/25/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
04/06/2023
Signed off — Alteration
Installation of 1 New Electric Hot Water Heater, 2 New Water Closets, 1 LAV, 1 Drinking Fountain and 1 Service Sink as indicated on plans.
M00709234-I1
03/27/2023
Signed off — Alteration
M08041838-I1
03/13/2023
Signed off — Alteration
Installation of new ductwork & fire dampers and 1 TON AC Unit as indicated on plans.
M00709226-I1
03/06/2023
Filed — Alteration
M08041838-I1
03/06/2023
Permit issued — Sign
M08041838-I1-SG
01/17/2023
Signed off — Alteration
Interior renovations as indicated on plans
M00709219-I1
01/10/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
11/28/2022
Violation issued (FDNY_NOV, closed)
10/25/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
09/30/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
09/09/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
07/07/2022
Permit issued — Plumbing
M00709234-I1-PL
06/02/2022
Permit issued — General Construction
M00709219-I1-GC
06/02/2022
Permit issued — Mechanical Systems
M00709226-I1-MS
05/27/2022
Filed — Alteration
Installation of new ductwork & fire dampers and 1 TON AC Unit as indicated on plans.
M00709226-I1
05/24/2022
Filed — Alteration
Installation of 1 New Electric Hot Water Heater, 2 New Water Closets, 1 LAV, 1 Drinking Fountain and 1 Service Sink as indicated on plans.
M00709234-I1
05/24/2022
Signed off — Alteration
M00585601-I1
05/24/2022
Special inspection requirement — Interior lighting power
Vladimir Kaushansky
05/24/2022
Special inspection requirement — Ventilation and air distribution system
Vladimir Kaushansky
05/24/2022
Special inspection requirement — Lighting controls
Vladimir Kaushansky
05/24/2022
Special inspection requirement — Maintenance information
Vladimir Kaushansky
05/24/2022
Special inspection requirement — Duct leakage testing, insulation and design
Vladimir Kaushansky
05/13/2022
Filed — Alteration
Interior renovations as indicated on plans
M00709219-I1
05/06/2022
Signed off — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
M00651437-I1
Latest 60 of 146 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedWinick Productions09/14/2026
DOB NOWPlumbingPermit IssuedMPS Plumbing & Heating05/28/2026
DOB NOWGeneral ConstructionSigned-offPro-H Development05/12/2026
DOB NOWPlumbingSigned-offAqua Plumbing & Heating01/21/2026
DOB NOWGeneral ConstructionSigned-offLegacy Builders/Developer01/05/2026
DOB NOWGeneral ConstructionSigned-offWinick Productions09/10/2025
DOB NOWGeneral ConstructionSigned-offA.W. & S. Construction Co08/06/2025
DOB NOWSignSigned-offNational Maintenance03/06/2023
DOB NOWPlumbingSigned-offLab Plumbing & Heating Co07/07/2022
DOB NOWGeneral ConstructionSigned-offHenegan Construction Co06/02/2022
DOB NOWMechanical SystemsSigned-offHenegan Construction Co06/02/2022
DOB NOWGeneral ConstructionSigned-offStorn01/08/2022
DOB NOWSidewalk ShedSigned-offJasco12/29/2021
DOB NOWSupported ScaffoldSigned-offJasco12/29/2021
DOB NOWMechanical SystemsPermit IssuedHenegan Construction Co09/14/2021
DOB NOWMechanical SystemsSigned-offComputer Cool/Ice Age05/17/2021
BIS—ISSUEDPeter Poon A Rchitects10/26/2020
BISMHISSUEDWeather Champions12/14/2017
BISOTISSUEDHenegan Construction Co08/21/2012
BISOTISSUEDHenegan Construction Co01/05/2012
BIS—ISSUEDNational Maintenance12/08/2011
BIS—ISSUEDNational Maintenance12/08/2011
BIS—ISSUEDNational Maintenance12/08/2011
BIS—ISSUEDNational Maintenance12/08/2011
BIS—ISSUEDNational Maintenance12/08/2011
BIS—ISSUEDNational Maintenance12/08/2011
BIS—ISSUEDNational Maintenance12/08/2011
BIS—ISSUEDNational Maintenance12/08/2011
BIS—ISSUEDNational Maintenance12/08/2011
BISOTISSUEDIzzo Construction11/05/2009
BISSPISSUEDAdvanced Plumbing09/18/2000
BISOTISSUEDBvi08/17/2000
BIS—ISSUEDParker Service Industries04/04/2000
BIS—ISSUEDParker Service Industries03/22/2000
BIS—ISSUEDParker Service Industries03/22/2000
BIS—ISSUEDParker Service Industries03/21/2000
BIS—ISSUEDParker Service Industries03/21/2000
BIS—ISSUEDParker Service Industries03/21/2000
BIS—ISSUEDParker Service Industries03/21/2000
BIS—ISSUEDParker Service Industries03/21/2000
+ 7 more permits on file
1 project · most recent 09/07/2021
Gas Water/Sanitary
FiledStatusContractorScope
09/07/2021——Gas, Water/Sanitary
5 projects · most recent 06/05/2025
General Wiring Lighting
FiledStatusContractorScope
06/05/2025CompleteCiti-Wide Electric—
01/25/2024CompleteKleinknecht Electric CoGeneral Wiring
07/01/2022CompleteKleinknecht Electric CoGeneral Wiring
05/23/2022CompleteCiti-Wide ElectricLighting
12/29/2021CompleteRichard Neu—
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
08/05/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
01/10/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/25/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/30/2022Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
09/09/2022Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 38
DateRequirementInspectorRole
08/22/2026FinalKett Murphyprogress
11/24/2025FinalNiccolo Valerioprogress
09/04/2025FinalANDY ENGLER ROTHprogress
07/25/2025FinalNiccolo Valerioprogress
05/24/2022Interior lighting powerVladimir Kaushanskyenergy_progress
05/24/2022Ventilation and air distribution systemVladimir Kaushanskyenergy_progress
05/24/2022Lighting controlsVladimir Kaushanskyenergy_progress
05/24/2022Maintenance informationVladimir Kaushanskyenergy_progress
05/24/2022Duct leakage testing, insulation and designVladimir Kaushanskyenergy_progress
04/26/2022Fire-Resistant Penetrations and JointsVladimir Kaushanskyspecial
04/26/2022Fire-Resistant Penetrations and JointsVladimir Kaushanskyspecial
03/30/2022FinalVladimir Kaushanskyprogress
03/30/2022Mechanical SystemsVladimir Kaushanskyspecial
12/21/2021FinalSunil Saigalprogress
09/08/2021Heating SystemsVladimir Kaushanskyspecial
09/08/2021Fire-Resistant Penetrations and JointsVladimir Kaushanskyspecial
09/08/2021Maintenance informationVladimir Kaushanskyenergy_progress
09/08/2021HVAC and service water heating equipment Vladimir Kaushanskyenergy_progress
09/08/2021HVAC and service water heating system controls Vladimir Kaushanskyenergy_progress
05/26/2021HVAC-R and service water heating system controlsAugustine Angbaenergy_progress
05/26/2021HVAC-R and service water heating equipmentAugustine Angbaenergy_progress
05/26/2021Energy Code Compliance InspectionsAugustine Angbaprogress
05/26/2021FinalAugustine Angbaprogress
05/26/2021Mechanical SystemsSteven Williamsspecial
05/26/2021HVAC-R and service water piping design and insulationAugustine Angbaenergy_progress
Latest 25 of 38.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Alexander Wang Fashion ShowOtherFloor 1
Project M01449960 Alteration · Permit Entire · 09/01/2026
Alexander WangRetailFloor 2
Project M01320025 Alteration · LOC Issued · 12/17/2025
Project M01320032 Alteration · Approved · 12/17/2025
Project M01320036 Alteration · LOC Issued · 12/17/2025
KCD WorldwideOfficeFloor 1
Project M01281958 Alteration · LOC Issued · 09/08/2025
HSBC BankBank / Financial branchCellar, Sub-basement, Floors 1, 2, Roof
Project M08041838 Alteration · LOC Issued · 03/06/2023
Project M00709219 Alteration · LOC Issued · 05/13/2022
Project M00484737 Alteration · Permit Entire · 09/08/2021
Project M00356355 Alteration · Approved · 09/07/2021
Project M00473684 Alteration · LOC Issued · 03/12/2021
Project M00342935 Alteration · Filing Withdrawn · 08/06/2020
HSBC Bank USABank / Financial branchSub-basement, Floor 1
Project M00709226 Alteration · LOC Issued · 05/27/2022
Project M00709234 Alteration · LOC Issued · 05/24/2022
JLL - HSBC Bank USAOfficeRoof
Project M00585601 Alteration · LOC Issued · 09/01/2021
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 319 on file (BIS + DOB NOW)
▸Plans & Drawings25
▸DOB NOWPlans/Sketch14
10/13/2026M01449960-I1Request digital key ↗
09/03/2026M00585601-I1Request digital key ↗
09/03/2026M00484737-I1Request digital key ↗
Showing 3 of 14 on file for this type
▸DOB NOWPlans/Sketch - Temporary Place of Assembly4
10/07/2026M01466126-I1Request digital key ↗
08/27/2026M01447223-I1Request digital key ↗
08/21/2026M01280788-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Boiler Equipment3
09/03/2026M00342935-I1Request digital key ↗
08/15/2026M00342935-P1Request digital key ↗
08/15/2026M00342935-P2Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems2
09/03/2026M00473684-P1Request digital key ↗
09/03/2026M00473684-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing2
09/03/2026M00356355-I1Request digital key ↗
08/15/2026M00356355-P1Request digital key ↗
▸Applications & Permits46
▸BISWORK PERMIT APPLICATION15
10/26/2020121189150Open ↗
12/15/2017123172271Open ↗
08/23/2012120874367Open ↗
Showing 3 of 15 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION15
12/03/2019121189150Open ↗
11/20/2017123172271Open ↗
05/19/2016122744842Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWLPC Approval/Permit15
09/16/2026M01449960-I1Open ↗
09/03/2026M00473684-I1Open ↗
09/03/2026M00473684-P1Open ↗
Showing 3 of 15 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
11/06/2020121189150Open ↗
▸Zoning, Tax Lot & Property Records4
▸BISZONING EXHIBIT V: CERTIFICATION1
12/16/2019121189150Open ↗
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
12/16/2019121189150Open ↗
▸BISZONING EXHIBIT II: CERTIFICATION1
12/16/2019121189150Open ↗
▸BISZONING EXHIBIT IV: CERTIFICATION1
12/16/2019121189150Open ↗
▸Seals & Professional Certifications103
▸DOB NOWProgress Inspector Seal & Signature27
09/02/2026M00342935-I1Open ↗
09/02/2026M00342935-I1Open ↗
09/02/2026M00342935-I1Open ↗
Showing 3 of 27 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature25
10/07/2026M01466126-I1Open ↗
09/16/2026M01449960-I1Open ↗
09/03/2026M00473684-I1Open ↗
Showing 3 of 25 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION21
02/13/2019123172271Open ↗
12/15/2017123172271Open ↗
12/15/2017123172271Open ↗
Showing 3 of 21 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST10
12/09/2011120915215Open ↗
12/09/2011120915171Open ↗
12/09/2011120915153Open ↗
Showing 3 of 10 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM10
12/09/2011120915215Open ↗
12/09/2011120915171Open ↗
12/09/2011120915153Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature10
09/02/2026M00342935-I1Open ↗
09/02/2026M00342935-I1Open ↗
09/01/2026M00473684-P1Open ↗
Showing 3 of 10 on file for this type
▸Trade Schedules & Equipment10
▸BISSIGN HANGER CERTIFICATE9
12/09/2011120915199Open ↗
12/09/2011120915215Open ↗
12/09/2011120915153Open ↗
Showing 3 of 9 on file for this type
▸BISEQUIPMENT USE APPLICATION-PERMIT1
06/09/2011120715119Open ↗
▸Safety & Tenant Protection4
▸BISSTREET TREE CHECKLIST3
08/13/2020121189150Open ↗
11/20/2017123172271Open ↗
06/09/2011120715119Open ↗
▸BISTenant Protection Plan and Notes1
11/20/2017123172271Open ↗
▸Environmental & Asbestos34
▸DOB NOWDEP ACP-5: Asbestos Assessment Report15
09/03/2026M00585601-I1Open ↗
09/03/2026M00342935-I1Open ↗
09/02/2026M00709219-I1Open ↗
Showing 3 of 15 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'9
12/16/2011120915153Open ↗
12/09/2011120915171Open ↗
12/09/2011120915162Open ↗
Showing 3 of 9 on file for this type
▸BISASBESTOS-CERTIFICATION (DEP ACP5)8
12/09/2011120915153Open ↗
12/09/2011120915162Open ↗
12/09/2011120915206Open ↗
Showing 3 of 8 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER2
06/09/2011120715119Open ↗
08/04/2009120121475Open ↗
▸Energy Compliance12
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS4
02/13/2019123172271Open ↗
12/15/2017123172271Open ↗
11/20/2017123172271Open ↗
Showing 3 of 4 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS3
02/13/2019123172271Open ↗
11/20/2017123172271Open ↗
12/31/2013120874367Open ↗
▸BISTECHNICAL REPORT: ENERGY3
10/28/2011120874367Open ↗
10/28/2011120874367Open ↗
06/09/2011120715119Open ↗
▸DOB NOWEN2: As Built Energy Analysis.2
09/03/2026M00473684-I1Open ↗
09/02/2026M00709226-I1Open ↗
▸Approvals, Objections & Sign-offs37
▸BISLANDMARKS APPROVAL17
08/13/2020121189150Open ↗
11/20/2017123172271Open ↗
02/04/2014120915153Open ↗
Showing 3 of 17 on file for this type
▸BISADMINISTRATIVE OBJECTIONS11
12/09/2011120915171Open ↗
12/09/2011120915162Open ↗
12/09/2011120915180Open ↗
Showing 3 of 11 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST7
02/13/2019123172271Open ↗
02/04/2014120915199Open ↗
02/04/2014120915153Open ↗
Showing 3 of 7 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION1
02/13/2019123172271Open ↗
▸BISSCHEDULE A - OCCUPANCY / USE1
12/03/2019121189150Open ↗
▸Cost, Insurance & Ownership21
▸BISCOST AFFIDAVIT20
02/13/2019123172271Open ↗
11/20/2017123172271Open ↗
05/19/2016122744842Open ↗
Showing 3 of 20 on file for this type
▸BISCOST AFFIDAVIT ESTIMATE: (PW3)1
08/13/2020121189150Open ↗
▸Filing & Intake Forms18
▸BISEFILING COVER SHEET14
11/20/2017123172271Open ↗
05/19/2016122744842Open ↗
12/09/2011120915171Open ↗
Showing 3 of 14 on file for this type
▸BISADDITIONAL INFORMATION3
01/23/2012120915180Open ↗
01/23/2012120915206Open ↗
01/20/2012120915199Open ↗
▸BISBOROUGH INTAKE FORM1
02/13/2019123172271Open ↗
▸Other Documents5
▸DOB NOWProof of Historic Building4
08/13/2026M01320032-I1Open ↗
08/13/2026M01320036-I1Open ↗
08/13/2026M01320025-I1Open ↗
Showing 3 of 4 on file for this type
▸BISPLOT DIAGRAM1
12/16/2019121189150Open ↗