| Owner | Filings | Most Recent |
|---|---|---|
| BRIDLE ESTATES INC | 17 | 03/22/2026 |
| NIRO | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| TONY SAYAD ARCHITECT | 5 | 12/14/2022 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| NIRO INC | General Contractor | 3 | 03/21/2026 |
| BRIDLE ESTATES INC | General Contractor | 2 | 03/21/2026 |
| D AND H ELECTRICAL CONST | Electrical | 1 | 03/22/2026 |
| FLOW-RIGHT PLBG & HTG COR | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SRA PLANNING & EXPEDITING | 5677 | 4 | 12/14/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | BRIDLE ESTATES INC | 12/12/2022 |
| DOB NOW | Plumbing | Signed-off | FLOW-RIGHT PLBG & HTG COR | 02/24/2022 |
| DOB NOW | General Construction | Permit Issued | NIRO INC | 02/14/2022 |
| BIS | OT | RE-ISSUED | AMBER ELECTRICAL CONTRACT | 01/19/2023 |
| BIS | OT | ISSUED | SOLAR STRING INC | 12/01/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 12/14/2022 | Signed-off | BRIDLE ESTATES INC | Air Conditioning Systems, Associated Ducts and Piping, Heating Systems, Ventilation Systems | Cooling Comfort Aire RSF1342SIM 86,000 BTU · Condensing Unit ×2 Heating Triangle Tube INSTINCT INS199C 199,000 BTU · Boiler ×1 Ventilation Fantech HERO 200H 210 CFM · Erv ×1 Ducts & Piping Southwark Metal G-60 COATED GALVANIZED STEEL 24 GA. 2,950 CFM · Ductwork ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/14/2022 | Signed-off | FLOW-RIGHT PLBG & HTG COR | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/06/2023 | Complete | AMBER ELECTL CONTNG INC | — |
| 05/12/2022 | Complete | D AND H ELECTRICAL CONST | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/14/2022 | Signed-off | BRIDLE ESTATES INC | Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/21/2022 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/21/2022 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 12/05/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/01/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/27/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/06/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/13/2022 | Pass-Final PL - Underground | Pass | View ↗ |
| 04/05/2022 | Fail-Final PL - Underground | Fail | View ↗ |
| 03/17/2022 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/16/2022 | Fenestration and door U-factor and product ratings | WILLIAM MONTAGUE | energy_progress |
| 12/16/2022 | HVAC-R and service water heating equipment | WILLIAM MONTAGUE | energy_progress |
| 12/16/2022 | Duct leakage testing, insulation and design | WILLIAM MONTAGUE | energy_progress |
| 12/16/2022 | Insulation placement and R values | WILLIAM MONTAGUE | energy_progress |
| 12/16/2022 | Fenestration air leakage | WILLIAM MONTAGUE | energy_progress |
| 12/16/2022 | Ventilation and air distribution system | WILLIAM MONTAGUE | energy_progress |
| 12/16/2022 | Fenestration areas | WILLIAM MONTAGUE | energy_progress |
| 12/16/2022 | Interior lighting power | WILLIAM MONTAGUE | energy_progress |
| 12/16/2022 | Mechanical Systems | WILLIAM MONTAGUE | special |
| 12/16/2022 | Concrete - Cast-In-Place | WILLIAM MONTAGUE | special |
| 12/16/2022 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | WILLIAM MONTAGUE | special |
| 12/16/2022 | Fire-Resistant Penetrations and Joints | WILLIAM MONTAGUE | special |
| 12/16/2022 | Subgrade Inspections | WILLIAM MONTAGUE | special |
| 12/16/2022 | Exterior Insulation and Finish Systems (EIFS) | WILLIAM MONTAGUE | special |
| 12/16/2022 | Subsurface Investigations (Borings/Test Pits) | WILLIAM MONTAGUE | special |
| 12/16/2022 | Footing and Foundation | WILLIAM MONTAGUE | progress |
| 12/16/2022 | Final | WILLIAM MONTAGUE | progress |
| 12/16/2022 | Fire-Resistance Rated Construction | WILLIAM MONTAGUE | progress |
| 12/16/2022 | Energy Code Compliance Inspections | WILLIAM MONTAGUE | progress |
| 12/16/2022 | Structural Wood Frame | WILLIAM MONTAGUE | progress |
| 12/16/2022 | HVAC-R and service water piping design and insulation | WILLIAM MONTAGUE | energy_progress |
| 12/16/2022 | Permanent certificate | WILLIAM MONTAGUE | energy_progress |
| 12/16/2022 | Air barrier - visual inspection | WILLIAM MONTAGUE | energy_progress |
| 12/16/2022 | HVAC-R and service water heating system controls | WILLIAM MONTAGUE | energy_progress |
| 12/16/2022 | Fireplaces | WILLIAM MONTAGUE | energy_progress |