Two stories - detached, small or mid-size
584 EAST 54 STREET
BROOKLYN · East Flatbush-Farragut · BIN 3105905
💬 Discuss this project
1935Year Built
2.5Stories
A1Building Class
R4Zoning
1,620 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 1,950 sf lot · 0.83 FAR built · Flood zone X
Locations of Work
ArchitectureElectrical
Roof1p · 1 filing · 9 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
03/09/2023$699K—— → —$432/sf building
03/09/2023$775K—— → —$478/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TOM PETERSEN ARCHITECT, LLC103/18/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
THE GREEN PLUG LLCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
THOMAS PETERSEN ARCHITECT7854103/18/2025
Building Lifecycle
All (8)Filed (1)Permit Issued (1)Signed Off (1)Special Inspection (5)
06/18/2025
Signed off — Alteration
The scope of work pertains exclusively to the installation of the solar system. Any additional tasks or activities should not be assumed as approved or permitted by the NYC Department of Buildings. No change to use, egress, or occupancy
B01196547-I1
03/21/2025
Permit issued — Solar
B01196547-I1-SL
03/18/2025
Filed — Alteration
The scope of work pertains exclusively to the installation of the solar system. Any additional tasks or activities should not be assumed as approved or permitted by the NYC Department of Buildings. No change to use, egress, or occupancy
B01196547-I1
03/18/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
TOM PETERSEN
03/18/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
TOM PETERSEN
03/18/2025
Special inspection requirement — Energy Code Compliance Inspections
TOM PETERSEN
03/18/2025
Special inspection requirement — Final
TOM PETERSEN
03/18/2025
Special inspection requirement — Air barrier - visual inspection
TOM PETERSEN
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offTHE GREEN PLUG LLC03/21/2025
2 projects · most recent 03/05/2025
General Wiring
FiledStatusContractorScope
03/05/2025CompleteL.D.M. ELECTL CONTRS INCGeneral Wiring
03/05/2025CompleteL.D.M. ELECTL CONTRS INC—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
03/18/2025Fire-Resistant Penetrations and JointsTOM PETERSENspecial
03/18/2025Structural Stability – Alterations of existing buildingsTOM PETERSENspecial
03/18/2025Energy Code Compliance InspectionsTOM PETERSENprogress
03/18/2025FinalTOM PETERSENprogress
03/18/2025Air barrier - visual inspectionTOM PETERSENenergy_progress
▾Documents — 9 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/22/2026B01196547-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
08/27/2026B01196547-I1Open ↗
08/27/2026B01196547-I1Open ↗
08/27/2026B01196547-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/27/2026B01196547-I1Open ↗
08/27/2026B01196547-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/22/2026B01196547-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/22/2026B01196547-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026B01196547-I1Open ↗