| Owner | Filings | Most Recent |
|---|---|---|
| MATRIX DEVELOPMENT GROUP | 49 | 07/08/2026 |
| MATRIX DEVELOPMENT | 3 | 07/08/2026 |
| NEW GENERATION ENERGY AND ENVIRONME | 7 | 03/22/2026 |
| TRIANGLE ENTERPRISE NYC I | 4 | 03/22/2026 |
| MATRIX PPF STATEN ISLAND LOT 1, LLC | 1 | 03/22/2026 |
| MATRIX CONSTRUCTION SERV | 3 | 03/22/2026 |
| 380 DEVELOPMENT | 8 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| HARRISON-HAMNETT, P.C. | 1 | 09/25/2024 |
| NEW CONCEPT ENGINEERING, PC | 1 | 04/09/2021 |
| GREEN DESIGN | 1 | 11/05/2020 |
| KZ ENGINEERING, P.C | 1 | 07/13/2020 |
| JOSE L. PENA,P.E. | 2 | 11/08/2018 |
| NORMAN C. LOK, PE | 2 | 10/12/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| LOUIS STRIAR | 8 | 03/21/2026 |
| R-DESIGN | 1 | 03/21/2026 |
| SYNERGY BUILDING CONSULTANTS | 1 | 03/21/2026 |
| CONSTRUCTION LAB | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| TRIANGLE ENTERPRISE NYC I | General Contractor | 6 | 03/21/2026 |
| NEPTUNE SIGNS AWNINGS | Scaffold | 5 | 07/08/2026 |
| CS BRIDGE CORP | General Contractor | 4 | 03/21/2026 |
| CHRISTOPHER PALLARINO | Electrical | 1 | 03/21/2026 |
| THE FANIA CO INC | General Contractor | 1 | 07/08/2026 |
| RMS INDUSTRIES OF NY, INC | General Contractor | 1 | 07/08/2026 |
| MAC ELECT'L CONTR. INC. | Electrical | 1 | 03/22/2026 |
| R. NUZZOLO ELECTRIC INC | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| NEW CONCEPT ENGINEERING, | 3906 | 1 | 04/09/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | THE FANIA CO INC | 10/01/2024 |
| DOB NOW | Supported Scaffold | Signed-off | CS BRIDGE CORP | 06/21/2021 |
| DOB NOW | Mechanical Systems | Signed-off | RMS INDUSTRIES OF NY, INC | 04/13/2021 |
| DOB NOW | Supported Scaffold | Permit Issued | TRIANGLE ENTERPRISE NYC I | 12/05/2020 |
| DOB NOW | Supported Scaffold | Permit Issued | TRIANGLE ENTERPRISE NYC I | 11/06/2020 |
| DOB NOW | Supported Scaffold | Signed-off | CS BRIDGE CORP | 07/14/2020 |
| DOB NOW | Sign | Signed-off | NEPTUNE SIGNS&AWNINGS INC | 11/14/2018 |
| DOB NOW | Sign | Signed-off | NEPTUNE SIGNS&AWNINGS INC | 11/14/2018 |
| DOB NOW | Sign | Permit Issued | NEPTUNE SIGNS&AWNINGS INC | 11/14/2018 |
| DOB NOW | Sign | Signed-off | NEPTUNE SIGNS&AWNINGS INC | 10/30/2018 |
| DOB NOW | Sign | Signed-off | NEPTUNE SIGNS&AWNINGS INC | 10/30/2018 |
| BIS | OT | ISSUED | NEW GENERATION ENERGY & E | 10/27/2020 |
| BIS | OT | ISSUED | ZABRANSKY MECHANICAL CORP | 09/06/2019 |
| BIS | FB | ISSUED | SCARAN OIL SERVICE CO INC | 03/27/2019 |
| BIS | PL | ISSUED | WEST SHORE CONSULTING INC | 02/19/2019 |
| BIS | — | ISSUED | MATRIX CONSTRUCTION SERVICE | 02/01/2019 |
| BIS | FS | RE-ISSUED | SCARAN OIL SERVICE CO INC | 01/23/2019 |
| BIS | FS | ISSUED | SCARAN OIL SERVICE CO INC | 01/23/2019 |
| BIS | PL | ISSUED | WEST SHORE CONSULTING INC | 01/11/2019 |
| BIS | OT | ISSUED | NEPTUNE SIGNS & AWNINGS I | 11/26/2018 |
| BIS | PL | ISSUED | WEST SHORE CONTRACTING, I | 09/11/2018 |
| BIS | FB | ISSUED | MPW ENGINEERING | 08/29/2018 |
| BIS | SP | ISSUED | CALLAHAN PIPING LLC | 08/07/2018 |
| BIS | FS | ISSUED | DOSE ENGINEERING PLLC | 07/26/2018 |
| BIS | FS | ISSUED | DOSE ENGINEERING PLLC | 07/26/2018 |
| BIS | FB | ISSUED | DOSE ENGINEERING PLLC | 07/24/2018 |
| BIS | FB | ISSUED | DOSE ENGINEERING PLLC | 07/24/2018 |
| BIS | — | ISSUED | MATRIX DEVELOPMENT GROUP | 07/16/2018 |
| BIS | OT | ISSUED | FRAZIER INDUSTRIAL COMPAN | 06/29/2018 |
| BIS | OT | ISSUED | MATRIX CONSTRUCTION SERVI | 06/08/2018 |
| BIS | — | ISSUED | MATRIX CONSTRUCTION SERVI | 06/07/2018 |
| BIS | SP | ISSUED | CALLAHAN PIPING LLC | 05/11/2018 |
| BIS | SP | ISSUED | CALLAHAN PIPING LLC | 05/11/2018 |
| BIS | SP | ISSUED | CALLAHAN PIPING LLC | 05/11/2018 |
| BIS | OT | ISSUED | FRAZIER INDUSTRIAL COMPAN | 04/04/2018 |
| BIS | — | ISSUED | MATRIX CONSTRUCTION SERVI | 11/27/2017 |
| BIS | — | ISSUED | MATRIX CONSTRUCTION SERVI | 10/06/2017 |
| BIS | — | ISSUED | BLUE ROCK CONSTRUCTION IN | 09/25/2017 |
| BIS | EQ | ISSUED | FISHER INSTALLATIONS INC | 09/21/2017 |
| BIS | SD | ISSUED | CALLAHAN PIPING LLC | 07/21/2017 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/18/2025 | Complete | R. NUZZOLO ELECTRIC INC | — |
| 05/08/2024 | Complete | DAVEN ELECTRIC CORP | — |
| 07/07/2022 | Complete | CONTROL ELEC'L CONT'G COR | General Wiring |
| 04/13/2021 | Complete | HESO ELECTRICAL INC | 3 meters, 3 new_meters |
| 02/11/2021 | Cancelled | AGIR ELEC'L LTD. D/B/A | General Wiring |
| 07/24/2019 | Complete | MACK ELECTRICAL INC | General Wiring |
| 05/13/2019 | Complete | CONTROL ELEC'L CONT'G COR | General Wiring |
| 01/18/2019 | Complete | ROBERT S. COVELLO | — |
| 01/18/2019 | Complete | ROBERT S. COVELLO | — |
| 11/09/2018 | Complete | ROBERT S. COVELLO | — |
| 11/08/2018 | Complete | ROBERT S. COVELLO | — |
| 09/13/2018 | Complete | CONTROL ELEC'L CONT'G COR | General Wiring |
| 09/05/2018 | Complete | MAC ELECT'L CONTR. INC. | General Wiring |
| 09/05/2018 | Complete | MAC ELECT'L CONTR. INC. | General Wiring |
| 07/23/2018 | Complete | MAC ELECT'L CONTR. INC. | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/13/2024 | Final | JOHN HARRISON | progress |