| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/18/2017 | $918K | — | Private party → Private party | $101/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| FELLENZER ENGINEERING LLP | 5 | 02/13/2025 |
| PERRY M PETRILLO ARCHITECTS, PC | 4 | 07/18/2023 |
| SHAABAN ENGINEERING, LLC | 6 | 04/20/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| KAZAM CONSULTANTS | 12 | 03/21/2026 |
| GERALD J. CALIENDO R.A., P.C. | 3 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MAMC CONSULTING REPS LLC | General Contractor | 7 | 07/08/2026 |
| BALATON CONSULTING LLC | Scaffold | 6 | 07/08/2026 |
| IMPACT BUILDERS CORP | General Contractor | 4 | 07/08/2026 |
| 2260 MAG CORP | General Contractor | 2 | 07/08/2026 |
| CAPE PLUMBING INC | Plumbing | 2 | 07/08/2026 |
| CITY ELEC'L SIGN ERECTORS | Electrical | 1 | 03/22/2026 |
| STANDARD FIRE PROTECT LLC | Fire Protection | 1 | 07/08/2026 |
| SALVATORE FILOTEO | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 3 | 02/13/2025 |
| DOYUN KIM; RA | 7415 | 3 | 12/12/2023 |
| BADALY ARCHITECT PLLC | 7137 | 1 | 07/18/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | IMPACT BUILDERS CORP | 02/25/2025 |
| DOB NOW | Mechanical Systems | Signed-off | IMPACT BUILDERS CORP | 09/10/2024 |
| DOB NOW | Sprinklers | Signed-off | STANDARD FIRE SUPP CORP | 08/03/2023 |
| DOB NOW | Sign | Signed-off | NORTH SHORE NEON SIGN CO | 04/20/2023 |
| DOB NOW | Sign | Signed-off | NORTH SHORE NEON SIGN CO | 04/20/2023 |
| DOB NOW | Sign | Signed-off | NORTH SHORE NEON SIGN CO | 04/20/2023 |
| DOB NOW | Sign | Signed-off | NORTH SHORE NEON SIGN CO | 04/20/2023 |
| DOB NOW | Sign | Signed-off | NORTH SHORE NEON SIGN CO | 04/20/2023 |
| DOB NOW | Sign | Signed-off | NORTH SHORE NEON SIGN CO | 04/20/2023 |
| DOB NOW | Mechanical Systems | Signed-off | MAMC CONSULTING REPS LLC | 01/13/2023 |
| DOB NOW | General Construction | Signed-off | MAMC CONSULTING REPS LLC | 01/12/2023 |
| DOB NOW | Construction Fence | Signed-off | MAMC CONSULTING REPS LLC | 01/12/2023 |
| DOB NOW | Plumbing | Signed-off | CAPE PLUMBING INC | 02/15/2022 |
| DOB NOW | Construction Fence | Signed-off | 2260 MAG CORP | 10/19/2021 |
| DOB NOW | General Construction | Signed-off | 2260 MAG CORP | 09/30/2021 |
| BIS | — | ISSUED | L.S. SIGN CO., INC | 07/30/2014 |
| BIS | — | ISSUED | L.S. SIGN CO., INC | 07/30/2014 |
| BIS | — | ISSUED | L.S. SIGN CO., INC | 07/25/2014 |
| BIS | — | ISSUED | NORTH SHORE NEON SIGNS CO. INC. | 07/20/2006 |
| BIS | — | ISSUED | NORTH SHORE NEON SIGNS CO. INC. | 07/20/2006 |
| BIS | — | ISSUED | NORTH SHORE NEON SIGN CO. INC. | 07/13/2006 |
| BIS | — | ISSUED | NORTH SHORE NEON SIGN CO. INC. | 07/13/2006 |
| BIS | BL | ISSUED | COURT OIL HEATING CORP. | 01/11/1994 |
| BIS | — | ISSUED | SERVICE SIGN ERECTORS | 10/03/1990 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/07/2024 | Permit Issued | GENMAR ELECT. CONT'G CORP | General Wiring |
| 10/27/2023 | Permit Issued | GENMAR ELECT. CONT'G CORP | General Wiring |
| 06/22/2023 | Permit Issued | RAYON'S ELECTRICAL | General Wiring, Lighting |
| 04/24/2023 | Complete | CITY ELEC'L SIGN ERECTORS | — |
| 04/24/2023 | Complete | CITY ELEC'L SIGN ERECTORS | — |
| 04/24/2023 | Complete | CITY ELEC'L SIGN ERECTORS | — |
| 04/24/2023 | Complete | CITY ELEC'L SIGN ERECTORS | — |
| 04/24/2023 | Complete | CITY ELEC'L SIGN ERECTORS | — |
| 04/24/2023 | Complete | CITY ELEC'L SIGN ERECTORS | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/15/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 08/08/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/08/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/28/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/06/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/23/2022 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 03/18/2022 | No Access-Final PL - Up to 3 Requested Floors | No Access | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/07/2025 | Mechanical Systems | FAHAD FATEH | special |
| 01/07/2025 | Final | FAHAD FATEH | progress |
| 09/26/2024 | Final | FAHAD FATEH | progress |
| 09/26/2024 | Mechanical Systems | FAHAD FATEH | special |
| 09/24/2024 | Mechanical Systems | FAHAD FATEH | special |
| 09/24/2024 | Final | FAHAD FATEH | progress |
| 12/13/2023 | Mechanical Systems | DOYUN KIM | special |
| 12/13/2023 | Final | JEFFREY BELL | progress |
| 12/07/2023 | Final | JEFFREY BELL | progress |
| 12/07/2023 | Mechanical Systems | DOYUN KIM | special |
| 07/11/2023 | Sprinkler Systems | SHAHIN BADALY | special |
| 04/18/2023 | Final | AHMED SHAABAN | progress |
| 04/18/2023 | Final | AHMED SHAABAN | progress |
| 04/18/2023 | Final | AHMED SHAABAN | progress |
| 04/18/2023 | Final | AHMED SHAABAN | progress |
| 09/27/2021 | Fenestration areas | Perry Petrillo | energy_progress |
| 09/27/2021 | Fenestration air leakage | Perry Petrillo | energy_progress |
| 09/27/2021 | Lighting controls | Perry Petrillo | energy_progress |
| 09/27/2021 | Maintenance information | Perry Petrillo | energy_progress |
| 09/27/2021 | Insulation placement and R values | Perry Petrillo | energy_progress |
| 09/27/2021 | Fenestration and door U-factor and product ratings | Perry Petrillo | energy_progress |
| 09/27/2021 | Fire-Resistance Rated Construction | Perry Petrillo | progress |
| 09/27/2021 | Energy Code Compliance Inspections | Perry Petrillo | progress |
| 09/27/2021 | Final | Perry Petrillo | progress |
| 09/27/2021 | Masonry | DOYUN KIM | special |