← Back
Primarily 3 family with 1 store or office
59 HUDSON AVENUE
BROOKLYN · BIN 3000064
💬 Discuss this project
1852Year Built
4.5Stories
S3Building Class
R6BZoning
4,394 sfGross Floor Area
4Units
Rent Stabilized12 Open Violations 9 unresolved · 3 paperwork only ▸FDNY Report ↗
Primarily 3 family with 1 store or office · 1,750 sf lot · 2.51 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Permit Issued — active, not yet Signed-off
Floor 4Under Construction4p · 1 filing · 13 docs
Floor 3Under Construction3p · 1 filing · 13 docs
Floor 2Under Construction4p · 1 filing · 13 docs
Floor 1
CellarUnder Construction2p · 1 filing · 13 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
MEGHNA CONSTRUCTION509/16/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ARC-HI-TECT ASSOCIATE INC212/16/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ARCHITECTURAL DESIGN SOLUTIONS203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MEGHNA CONSTRUCTIONGeneral Contractor303/21/2026
ZONE PLUMBING & HEATING CPlumbing109/16/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ARC-HI-TECH ASSOCIATES IN6963106/03/2025
Building Lifecycle
All (68)Filed (2)Permit Issued (2)Violation (19)Objection (41)Special Inspection (4)
09/15/2026
Permit issued — Plumbing
B01225219-S1-PL
05/05/2026
Violation issued (HPD, open)
A
04/06/2026
Violation issued (ECB, open)
Construction
04/06/2026
Violation issued (ECB, open)
Construction
04/06/2026
Violation issued (ECB, open)
Unknown
01/30/2026
Objection resolved — Addressed
01/30/2026
Objection resolved — Addressed
01/27/2026
Objection resolved — Addressed
01/27/2026
Objection resolved — Addressed
01/09/2026
Objection resolved — Addressed
01/09/2026
Objection resolved — Addressed
01/09/2026
Objection resolved — Addressed
12/23/2025
Objection raised — Energy
12/23/2025
Objection raised — Plumbing
12/23/2025
Objection raised — Scope
12/23/2025
Objection raised — Scope
12/23/2025
Objection raised — Admin
12/23/2025
Objection raised — Other
12/23/2025
Objection raised — Inspections
12/23/2025
Objection raised — Plumbing
12/16/2025
Filed — Alteration
GENERAL CONSTRUCTION WORK DUE TO NEW ADDITIONAL BATHROOM AS PER 2ND,3RD AND 4TH FLOOR PLAN.NO CHANGE IN USE, EGRESS OR OCCUPANCY
B01225219-S1
11/18/2025
Violation issued (HPD, open)
I
09/09/2025
Permit issued — General Construction
B01225219-I1-GC
07/24/2025
Objection resolved — Addressed
07/24/2025
Objection resolved — Addressed
07/24/2025
Objection resolved — Addressed
07/21/2025
Objection resolved — Addressed
07/16/2025
Objection resolved — Addressed
07/15/2025
Special inspection requirement — Fire-Resistance Rated Construction
IGOR LISOVENKO
07/08/2025
Objection resolved — Addressed
07/08/2025
Objection resolved — Addressed
07/08/2025
Objection resolved — Addressed
07/08/2025
Objection resolved — Addressed
07/08/2025
Objection resolved — Addressed
07/07/2025
Objection resolved — Addressed
07/02/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
IGOR LISOVENKO
06/27/2025
Objection raised — Plumbing
06/27/2025
Objection raised — Cost
06/20/2025
Objection resolved — Addressed
06/20/2025
Objection resolved — Addressed
06/12/2025
Objection raised — Scope
06/12/2025
Objection raised — Scope
06/12/2025
Objection raised — Scope
06/12/2025
Objection raised — Scope
06/12/2025
Objection raised — Plumbing
06/12/2025
Objection raised — Scope
06/12/2025
Objection raised — Energy
06/12/2025
Objection raised — Scope
06/12/2025
Objection raised — Scope
06/12/2025
Objection raised — Scope
06/12/2025
Objection raised — Inspections
06/10/2025
Violation issued (HPD, open)
A
06/03/2025
Filed — Alteration
GENERAL CONSTRUCTION WORK DUE TO NEW ADDITIONAL BATHROOM AS PER 2ND,3RD AND 4TH FLOOR PLAN.NO CHANGE IN USE, EGRESS OR OCCUPANCY
B01225219-I1
05/14/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
IGOR LISOVENKO
05/13/2025
Special inspection requirement — Final
IGOR LISOVENKO
11/25/2024
Violation issued (HPD, open)
I
04/10/2024
Violation issued (HPD, open)
A
11/17/2023
Violation issued (HPD, open)
I
03/23/2023
Violation issued (HPD, open)
A
11/04/2022
Violation issued (HPD, closed)
I
Latest 60 of 68 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedZONE PLUMBING & HEATING C09/15/2026
DOB NOWGeneral ConstructionPermit IssuedMEGHNA CONSTRUCTION09/09/2025
1 project · most recent 12/16/2025
Gas Water/Sanitary
FiledStatusContractorScope
12/16/2025Permit Issued5 BORO'S PLUMBING INCGas, Water/Sanitary
1 project · most recent 05/20/2026
General Wiring
FiledStatusContractorScope
05/20/2026Permit IssuedADAM ELECL CONTRNG LLCGeneral Wiring
▾Special Inspection Requirements (DOB NOW) — 4
DateRequirementInspectorRole
07/15/2025Fire-Resistance Rated ConstructionIGOR LISOVENKOprogress
07/02/2025Structural Stability – Alterations of existing buildingsIGOR LISOVENKOspecial
05/14/2025Fire-Resistant Penetrations and JointsIGOR LISOVENKOspecial
05/13/2025FinalIGOR LISOVENKOprogress
▾Documents — 15 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/15/2026B01225219-I1Request digital key ↗
08/14/2026B01225219-S1Request digital key ↗
▸Applications & Permits2
▸DOB NOWLPC Approval/Permit2
08/13/2026B01225219-I1Open ↗
08/13/2026B01225219-S1Open ↗
▸Seals & Professional Certifications8
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/19/2026B01225219-S1Open ↗
08/13/2026B01225219-S2Open ↗
08/13/2026B01225219-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProgress Inspector Seal & Signature2
09/23/2026B01225219-I1Open ↗
09/23/2026B01225219-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
09/23/2026B01225219-I1Open ↗
09/23/2026B01225219-I1Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/13/2026B01225219-S2Open ↗
08/13/2026B01225219-I1Open ↗
08/13/2026B01225219-S1Open ↗