| Owner | Filings | Most Recent |
|---|---|---|
| ALY REALTY MANAGEMENT | 26 | 07/08/2026 |
| SSP CONSTRUCTION | 4 | 07/08/2026 |
| ATLAS NY CONSTRUCTION | 4 | 07/08/2026 |
| 5901 INVESTOR LLC | 2 | 03/22/2026 |
| NEWLAND CONSTRUCTION | 2 | 03/22/2026 |
| YIN KEAT HOI 98 CONSTRUCT | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 03/29/2024 | $3.5M | — | — → — | $723/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| MW PROFESSIONAL ENGINEERING, P.C. | 3 | 07/20/2026 |
| CLIP ARCHITECTS | 1 | 03/30/2026 |
| BASSIRI | 3 | 07/08/2025 |
| SIMON JIANG | 12 | 12/21/2024 |
| JIAN ENGINEERING PLLC | 1 | 11/08/2024 |
| NYX ENGINEERING, PLLC | 1 | 10/02/2020 |
| HARRY TENENBAUM,PE | 1 | 02/25/2020 |
| ASHRAF CORP | 1 | 05/13/2019 |
| GREEN DESIGN | 1 | 11/12/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| MS | 24 | 03/21/2026 |
| ATLANTIC BUILDING SUPPLY INC. | 2 | 03/21/2026 |
| ECDESIGN STUDIO | 6 | 03/21/2026 |
| JRK CREATIVE | 2 | 03/21/2026 |
| ADVANCED BUILDERS SERVICES | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| GENESIS NYC CONSTRUCTION | General Contractor | 6 | 08/26/2026 |
| PREMIER FLOW PLBG AND HTG | Plumbing | 3 | 07/08/2026 |
| PREMIER FLOW PLBG HTG | General Contractor | 3 | 03/22/2026 |
| ATLAS NY CONSTRUCTION CORP | General Contractor | 2 | 07/08/2026 |
| LONG SHOT CRANE | Scaffold | 1 | 07/08/2026 |
| HI-RITE ELECTRIC CORP | Electrical | 1 | 03/22/2026 |
| NEPTUNE SIGNS AWNINGS | Scaffold | 1 | 07/08/2026 |
| AMM GEN'L CONTRACTING.INC | Fire Protection | 1 | 06/28/2026 |
| AMM GEN'L CONTRACTING INC | Plumbing | 1 | 06/28/2026 |
| CONTROL PLBG & HTG INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MW PROFESSIONAL ENGINEERI | 570 | 3 | 07/20/2026 |
| GREAT WALL CONSULTANT P.E | 5633 | 1 | 03/30/2026 |
| SIMON | 7555 | 12 | 12/21/2024 |
| JIAN ENGINEERING PLLC | 7397 | 1 | 11/08/2024 |
| S M TAM ARCHITECT, PLLC | 1666 | 1 | 02/25/2020 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Permit Issued | GENESIS NYC CONSTRUCTION | 07/20/2026 |
| DOB NOW | Boiler Equipment | Permit Issued | AMM GEN'L CONTRACTING INC | 06/26/2026 |
| DOB NOW | Sprinklers | Permit Issued | AMM GEN'L CONTRACTING.INC | 06/26/2026 |
| DOB NOW | General Construction | Permit Issued | GENESIS NYC CONSTRUCTION | 05/19/2026 |
| DOB NOW | Sign | Signed-off | NEPTUNE SIGNS&AWNINGS INC | 06/12/2025 |
| DOB NOW | Plumbing | Permit Issued | GALICJA PLBG AND HTG.CORP | 05/13/2024 |
| DOB NOW | General Construction | Permit Issued | GENESIS NYC CONSTRUCTION | 04/25/2024 |
| DOB NOW | Construction Fence | Permit Issued | GENESIS NYC CONSTRUCTION | 04/25/2024 |
| DOB NOW | Sign | Signed-off | LONG SHOT CRANE LLC | 10/08/2020 |
| DOB NOW | Plumbing | Signed-off | CONTROL PLBG & HTG INC | 02/28/2020 |
| DOB NOW | Supported Scaffold | Signed-off | ATLAS NY CONSTRUCTION COR | 05/13/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | ATLAS NY CONSTRUCTION COR | 11/13/2018 |
| BIS | OT | ISSUED | PRIMO DESIGN & CONSTRUCTI | 10/20/2020 |
| BIS | OT | ISSUED | YILIN CONSTRUCTION INC | 10/15/2020 |
| BIS | PL | ISSUED | SO PLUMBING & HEATING INC | 04/29/2019 |
| BIS | OT | ISSUED | STAR UNIVERSE RENOVATION* | 04/08/2019 |
| BIS | — | ISSUED | SUPERB PROPERTY MNG'T | 02/26/2019 |
| BIS | EQ | ISSUED | NEWLAND CONSTRUCTION INC | 08/30/2018 |
| BIS | PL | ISSUED | TOP PLUMBING GROUP,INC | 03/20/2018 |
| BIS | OT | ISSUED | NEWLAND CONSTRUCTION INC | 03/09/2018 |
| BIS | — | ISSUED | NEWLAND CONSTRUCTION INC | 03/09/2018 |
| BIS | — | ISSUED | NEWLAND CONSTRUCTION INC | 02/13/2018 |
| BIS | — | ISSUED | NEWLAND CONSTRUCTION INC | 02/09/2018 |
| BIS | PL | ISSUED | TOP PLUMBING GROUP,INC | 01/25/2018 |
| BIS | — | ISSUED | NEWLAND CONSTRUCTION INC | 09/15/2017 |
| BIS | — | ISSUED | NEWLAND CONSTRUCTION INC | 07/27/2017 |
| BIS | EQ | ISSUED | NEWLAND CONSTRUCTION INC | 07/12/2017 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/20/2026 | Permit Issued | AMM GEN'L CONTRACTING.INC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/30/2026 | Permit Issued | AMM GEN'L CONTRACTING INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/09/2025 | Complete | KJK ELECTRIC INC | — |
| 10/03/2019 | Complete | HI-RITE ELECTRIC CORP | General Wiring, Lighting |
| 11/12/2018 | Complete | RICHARD NEU | — |
| 03/12/2018 | Complete | HI-RITE ELECTRIC CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/15/2026 | Permit Issued | GENESIS NYC CONSTRUCTION | Steel |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/30/2026 | Permit Issued | AMM GEN'L CONTRACTING INC | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/17/2025 | Pass-Final Sign Permit Inspection | Pass | View ↗ |
| 12/10/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/15/2024 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 10/24/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/23/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/24/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/14/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/14/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 06/13/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/07/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/23/2024 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 05/14/2024 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 04/18/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/21/2026 | Tenant Protection Plan Compliance | — | special |
| 07/21/2026 | Sprinkler Systems | MING WAI WONG | special |
| 07/20/2026 | Tenant Protection Plan Compliance | — | special |
| 07/20/2026 | Sprinkler Systems | MING WAI WONG | special |
| 03/24/2026 | Fire-Resistant Penetrations and Joints | Xiong Wei Wu | special |
| 03/24/2026 | Tenant Protection Plan Compliance | Xiong Wei Wu | special |
| 12/25/2025 | Air barrier - visual inspection | JIAN DENG | energy_progress |
| 10/01/2025 | Maintenance information | JIAN DENG | energy_progress |
| 05/07/2025 | Lighting controls | JIAN DENG | energy_progress |
| 05/07/2025 | Interior lighting power | JIAN DENG | energy_progress |
| 12/24/2024 | Tenant Protection Plan Compliance | SIMON JIANG | special |
| 12/24/2024 | Energy Code Compliance Inspections | SIMON JIANG | progress |
| 12/24/2024 | Fire-Resistant Penetrations and Joints | SIMON JIANG | special |
| 12/16/2024 | Energy Code Compliance Inspections | SIMON JIANG | progress |
| 12/16/2024 | Tenant Protection Plan Compliance | — | special |
| 12/16/2024 | Fire-Resistant Penetrations and Joints | SIMON JIANG | special |
| 11/15/2024 | Tenant Protection Plan Compliance | — | special |
| 11/15/2024 | Energy Code Compliance Inspections | SIMON JIANG | progress |
| 11/15/2024 | Fire-Resistant Penetrations and Joints | SIMON JIANG | special |
| 11/08/2024 | Fire-Resistance Rated Construction | JIAN DENG | progress |
| 11/08/2024 | Fire-Resistant Penetrations and Joints | JIAN DENG | special |
| 11/08/2024 | Structural Stability – Alterations of existing buildings | JIAN DENG | special |
| 11/08/2024 | Energy Code Compliance Inspections | JIAN DENG | progress |
| 11/08/2024 | Fenestration air leakage | JIAN DENG | energy_progress |
| 11/08/2024 | Fenestration and door U-factor and product ratings | JIAN DENG | energy_progress |