← Back
Three families
591 CARLTON AVENUE
BROOKLYN · BIN 3028100
💬 Discuss this project
1883Year Built
3Stories
C0Building Class
R6BZoning
3,240 sfGross Floor Area
3Units
1 Open Violation ▸FDNY Report ↗
Three families · 1,850 sf lot · 1.75 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire Protection
Roof1p · 1 filing · 16 docs
Floor 313p · 4 filings · 20 docs
Floor 212p · 4 filings · 20 docs
Floor 114p · 4 filings · 20 docs
Cellar13p · 3 filings · 20 docs
Basement1p · 1 filing · 16 docs
Sub-Basement10p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
J G CONSTRUCTION SRVCS707/08/2026
591 CARLTON AVENUE CORP103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
03/25/2021$2.4M—GOTHAM ASSET HOLDINGS, LLC → Private party$741/sf building
11/13/2020$2.2M—Private party → GOTHAM ASSET HOLDINGS, LLC$679/sf building
01/25/2018$50K—Private party → 591 CARLTON AVENUE CORP$15/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
JOSEPH K. BLUM CO. LLP105/12/2026
EAB ENGINEERING PC811/21/2024
SYED ENGINEERING, P.C.206/07/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ARSENAL BUILDING CONSULTANTS LLC403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
PETTIBONE DESIGN INCGeneral Contractor507/08/2026
J & G CONSTRUCTION SVCSGeneral Contractor207/08/2026
A.D.S. PLBG AND HTG INCPlumbing207/08/2026
RICHARD NEUElectrical103/22/2026
A.D.S. PLBG AND HTG INCFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
EAB ENGINEERING, PC2048709/17/2024
Building Lifecycle
All (114)Filed (11)Permit Issued (8)Violation (2)Inspection (4)Objection (59)Special Inspection (30)
06/02/2026
Objection raised — Other
05/26/2026
Objection raised — Other
05/12/2026
Filed — Alteration CO
ONE STORY ENLARGEMENT AT REAR IN BASEMENT LEVEL AND REPLACE WINDOWS IN EXISTING TWO FAMILY DWELLING. OBTAIN NEW CERTIFICATE OF OCCUPANCY.
B00573927-S1
05/07/2026
Objection resolved — Resolved
05/07/2026
Objection resolved — Resolved
05/07/2026
Objection resolved — Resolved
05/07/2026
Objection resolved — Resolved
12/01/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
11/24/2025
Special inspection requirement — Designated Seismic System
12/05/2024
Objection raised — Other
12/05/2024
Objection raised — Q-4
12/05/2024
Objection raised — Other
12/05/2024
Objection raised — Scope
12/05/2024
Objection raised — Scope
11/21/2024
Filed — Alteration CO
ONE STORY ENLARGEMENT AT REAR IN BASEMENT LEVEL AND REPLACE WINDOWS IN EXISTING TWO FAMILY DWELLING. OBTAIN NEW CERTIFICATE OF OCCUPANCY.
B00573927-I1
09/27/2024
Objection raised — Admin
09/17/2024
Filed — Alteration
INTERIOR RENOVATION OF EXISTING TWO FAMILY DWELLING INCLUDING REMOVAL AND INSTALLATION OF PARTITIONS AND FINISHES. NO CHAGE TO USE, EGRESS OR OCCUPANCY.
B00689825-P2
09/13/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Iraj Issapour
09/13/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Iraj Issapour
09/13/2024
Special inspection requirement — Mechanical Systems
Iraj Issapour
09/13/2024
Special inspection requirement — Lighting controls
Iraj Issapour
09/13/2024
Special inspection requirement — Interior lighting power
Iraj Issapour
09/13/2024
Special inspection requirement — Maintenance information
Iraj Issapour
09/13/2024
Special inspection requirement — Metering
Iraj Issapour
09/13/2024
Special inspection requirement — Final
Iraj Issapour
08/23/2024
Objection raised — Other
08/18/2024
Filed — Alteration
REMOVE AND INSTALL NEW PLUMBING FIXTURES IN CONJUNCTION WITH CONSTRUCTION APPLICATION #B00689825
B00709977-P2
02/12/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
02/05/2024
Special inspection requirement — Maintenance information
Iraj Issapour
02/05/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Iraj Issapour
02/05/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
Iraj Issapour
02/05/2024
Special inspection requirement — HVAC-R and service water heating equipment
Iraj Issapour
02/05/2024
Special inspection requirement — HVAC-R and service water heating system controls
Iraj Issapour
02/02/2024
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
01/29/2024
Filed — Alteration
REMOVE AND INSTALL NEW PLUMBING FIXTURES IN CONJUNCTION WITH CONSTRUCTION APPLICATION #B00689825
B00709977-P1
01/25/2024
Special inspection requirement — HVAC-R and service water heating system controls
Iraj Issapour
01/25/2024
Special inspection requirement — Maintenance information
Iraj Issapour
01/25/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
Iraj Issapour
01/25/2024
Special inspection requirement — HVAC-R and service water heating equipment
Iraj Issapour
01/25/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Iraj Issapour
01/09/2024
Permit issued — Plumbing
B00709977-I1-PL
12/19/2023
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
07/21/2023
Permit issued — Mechanical Systems
B00689825-I1-GC-CX
07/19/2023
Special inspection requirement — Insulation placement and R values
07/19/2023
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
07/19/2023
Special inspection requirement — Concrete - Cast-In-Place
07/19/2023
Special inspection requirement — Masonry
07/19/2023
Special inspection requirement — Post-installed Anchors
07/19/2023
Special inspection requirement — Structural Cold-Formed Steel
07/19/2023
Special inspection requirement — Structural Steel - Details
07/19/2023
Special inspection requirement — Protection of exposed foundation insulation
07/19/2023
Special inspection requirement — Structural Steel - High Strength Bolting
07/19/2023
Special inspection requirement — Structural Steel - Welding
02/13/2023
Permit issued — Sprinklers
B08040668-I1-EW-SP
02/01/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/18/2023
Permit issued — Plumbing
B00709977-I1-PL
11/30/2022
Objection raised — Inspections
11/30/2022
Objection resolved — Addressed
11/30/2022
Objection raised — Mechanical
11/30/2022
Objection resolved — Addressed
Latest 60 of 114 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedA.D.S. PLBG AND HTG INC01/09/2024
DOB NOWMechanical SystemsPermit IssuedPETTIBONE DESIGN INC07/21/2023
DOB NOWSprinklersPermit IssuedA.D.S. PLBG AND HTG INC02/13/2023
DOB NOWPlumbingPermit IssuedA.D.S. PLBG AND HTG INC01/18/2023
DOB NOWMechanical SystemsPermit IssuedPETTIBONE DESIGN INC07/25/2022
DOB NOWMechanical SystemsPermit IssuedPETTIBONE DESIGN INC04/21/2022
DOB NOWSupported ScaffoldPermit IssuedJ & G CONSTRUCTION SVCS06/07/2021
DOB NOWSidewalk ShedPermit IssuedJ & G CONSTRUCTION SVCS06/07/2021
1 project · most recent 09/17/2024
Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
09/17/2024Permit IssuedPETTIBONE DESIGN INCVentilation Systems
Ventilation
Panasonic FV-0510V51 400 CFM · Exhaust Fan ×12
1 project · most recent 11/16/2022
FiledStatusContractorScope
11/16/2022Permit IssuedA.D.S. PLBG AND HTG INC—
1 project · most recent 08/18/2024
Gas Water/Sanitary
FiledStatusContractorScope
08/18/2024Permit IssuedA.D.S. PLBG AND HTG INCGas, Water/Sanitary
2 projects · most recent 04/21/2022
General Wiring
FiledStatusContractorScope
04/21/2022Permit IssuedJSP ELECTRIC, INCGeneral Wiring
06/07/2021Permit IssuedRICHARD NEU—
1 project · most recent 05/12/2026
Steel Masonry
FiledStatusContractorScope
05/12/2026——Steel, Masonry
1 project · most recent 06/07/2021
Sidewalk Shed
FiledStatusContractorScope
06/07/2021Permit IssuedJ & G CONSTRUCTION SVCSSidewalk Shed
▾Field Inspections (DOB CAP) — 4
DateTypeResultReport
02/12/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
02/02/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
12/19/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
02/01/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 51
DateRequirementInspectorRole
12/01/2025Fire-Resistant Penetrations and Joints—special
11/24/2025Designated Seismic System—special
09/13/2024Fire-Resistant Penetrations and JointsIraj Issapourspecial
09/13/2024Structural Stability – Alterations of existing buildingsIraj Issapourspecial
09/13/2024Mechanical SystemsIraj Issapourspecial
09/13/2024Lighting controlsIraj Issapourenergy_progress
09/13/2024Interior lighting powerIraj Issapourenergy_progress
09/13/2024Maintenance informationIraj Issapourenergy_progress
09/13/2024MeteringIraj Issapourenergy_progress
09/13/2024FinalIraj Issapourprogress
02/05/2024Maintenance informationIraj Issapourenergy_progress
02/05/2024Fire-Resistant Penetrations and JointsIraj Issapourspecial
02/05/2024HVAC-R and service water piping design and insulationIraj Issapourenergy_progress
02/05/2024HVAC-R and service water heating equipmentIraj Issapourenergy_progress
02/05/2024HVAC-R and service water heating system controlsIraj Issapourenergy_progress
01/25/2024HVAC-R and service water heating system controlsIraj Issapourenergy_progress
01/25/2024Maintenance informationIraj Issapourenergy_progress
01/25/2024HVAC-R and service water piping design and insulationIraj Issapourenergy_progress
01/25/2024HVAC-R and service water heating equipmentIraj Issapourenergy_progress
01/25/2024Fire-Resistant Penetrations and JointsIraj Issapourspecial
07/19/2023Insulation placement and R values—energy_progress
07/19/2023Alternative Materials - OTCR Buildings Bulletin Number—special
07/19/2023Concrete - Cast-In-Place—special
07/19/2023Masonry—special
07/19/2023Post-installed Anchors—special
Latest 25 of 51.
▾Documents — 76 on file (BIS + DOB NOW)
▸Plans & Drawings11
▸DOB NOWPlans/Sketch11
09/01/2026B00533985-I1Request digital key ↗
09/01/2026B00533982-I1Request digital key ↗
08/24/2026B00709977-P1Request digital key ↗
Showing 3 of 11 on file for this type
▸Applications & Permits7
▸DOB NOWLPC Approval/Permit7
08/15/2026B00689825-P1Open ↗
08/15/2026B00689825-I1Open ↗
08/14/2026B00573927-I1Open ↗
Showing 3 of 7 on file for this type
▸Zoning, Tax Lot & Property Records3
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/14/2026B00573927-I1Open ↗
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026B00573927-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)1
08/13/2026B00573927-I1Open ↗
▸Seals & Professional Certifications40
▸DOB NOWProgress Inspector Seal & Signature18
09/02/2026B00689825-P1Open ↗
09/02/2026B00689825-P1Open ↗
09/02/2026B00689825-P1Open ↗
Showing 3 of 18 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature12
09/01/2026B00533985-I1Open ↗
09/01/2026B00533982-I1Open ↗
08/28/2026B08040668-I1Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature10
09/20/2026B00709977-P1Open ↗
09/02/2026B00689825-P1Open ↗
09/02/2026B00689825-P1Open ↗
Showing 3 of 10 on file for this type
▸Safety & Tenant Protection3
▸DOB NOWStreet Tree Checklist3
08/15/2026B00573927-S1Open ↗
08/13/2026B00573927-S1Open ↗
08/13/2026B00573927-I1Open ↗
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form4
08/15/2026B08040668-I1Open ↗
08/14/2026B00709977-I1Open ↗
08/13/2026B00689825-I1Open ↗
Showing 3 of 4 on file for this type
▸Other Documents8
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone3
08/15/2026B00573927-S1Open ↗
08/13/2026B00573927-I1Open ↗
08/13/2026B00573927-S1Open ↗
▸DOB NOWPlot Diagram3
08/15/2026B00573927-S1Open ↗
08/13/2026B00573927-S1Open ↗
08/13/2026B00573927-I1Open ↗
▸DOB NOWSite Survey: Initial2
08/15/2026B00573927-S1Open ↗
08/13/2026B00573927-S1Open ↗