| Owner | Filings | Most Recent |
|---|---|---|
| JASCO | 8 | 07/08/2026 |
| 593 E137TH, LLC | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 10/12/2023 | $1.0M | — | — → — | $230/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| SION CONSULTING ENGINEERING PC | 11 | 04/13/2026 |
| ASR ENGINEERING PC | 2 | 06/26/2025 |
| AUTOMATED DESIGN ENGINEERING, PLLC | 1 | 12/20/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| ADVANCED BUILDERS SERVICES | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JASCO, INC | General Contractor | 4 | 07/08/2026 |
| PLBG P & H INC | Plumbing | 4 | 07/08/2026 |
| BRUCHE MECHANICAL NY LLC | Fire Protection | 1 | 07/08/2026 |
| DAVILAS CONTRACTOR CORP | General Contractor | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 10 | 04/13/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Boiler Equipment | Signed-off | PLBG P & H INC | 04/30/2026 |
| DOB NOW | Boiler Equipment | Signed-off | PLBG P & H INC | 04/10/2026 |
| DOB NOW | Plumbing | Signed-off | PLBG P & H INC | 02/12/2026 |
| DOB NOW | Sprinklers | Signed-off | BRUCHE MECHANICAL NY LLC | 08/19/2025 |
| DOB NOW | Supported Scaffold | Signed-off | JASCO, INC | 06/26/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | JASCO, INC | 06/16/2025 |
| DOB NOW | Plumbing | Signed-off | PLBG P & H INC | 12/10/2024 |
| DOB NOW | General Construction | Signed-off | DAVILAS CONTRACTOR CORP | 11/22/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 03/10/2025 | Signed-off | DAVILAS CONTRACTOR CORP | Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/10/2025 | Signed-off | PLBG P & H INC | 52 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/09/2026 | Signed-off | PLBG P & H INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/26/2025 | Complete | V. VASS ELECTRIC CORP | General Wiring |
| 06/14/2025 | Complete | RICHARD NEU | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/10/2025 | Signed-off | PLBG P & H INC | Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/22/2026 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 12/23/2025 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 12/05/2025 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 10/20/2025 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 10/02/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/22/2025 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 08/26/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 01/23/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 01/23/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/23/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/27/2026 | Heating Systems | SHAHRIAR QUAYYUM | special |
| 04/13/2026 | Heating Systems | SHAHRIAR QUAYYUM | special |
| 04/02/2026 | Heating Systems | — | special |
| 03/20/2026 | Heating Systems | SHAHRIAR QUAYYUM | special |
| 01/25/2026 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 01/09/2026 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 12/10/2025 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 03/24/2025 | HVAC-R and service water heating system controls | FAHAD FATEH | energy_progress |
| 03/24/2025 | Lighting controls | FAHAD FATEH | energy_progress |
| 03/24/2025 | Permanent certificate | FAHAD FATEH | energy_progress |
| 03/24/2025 | Interior lighting power | FAHAD FATEH | energy_progress |
| 03/24/2025 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 03/24/2025 | Fenestration and door U-factor and product ratings | FAHAD FATEH | energy_progress |
| 03/24/2025 | Fenestration air leakage | FAHAD FATEH | energy_progress |
| 03/24/2025 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 03/24/2025 | Mechanical Systems | FAHAD FATEH | special |
| 03/24/2025 | Fenestration areas | FAHAD FATEH | energy_progress |
| 03/24/2025 | Metering | FAHAD FATEH | energy_progress |
| 03/24/2025 | HVAC-R and service water piping design and insulation | FAHAD FATEH | energy_progress |
| 03/24/2025 | HVAC-R and service water heating equipment | FAHAD FATEH | energy_progress |
| 03/24/2025 | Maintenance information | FAHAD FATEH | energy_progress |
| 03/24/2025 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 03/24/2025 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 03/24/2025 | Final | FAHAD FATEH | progress |
| 03/24/2025 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |