| Owner | Filings | Most Recent |
|---|---|---|
| BOSTION PROPERTIES | 1,490 | 09/26/2026 |
| BXP | 16 | 07/08/2026 |
| SUGARFISH | 3 | 07/08/2026 |
| C PLUS DESIGN GROUP INC | 5 | 03/22/2026 |
| BP 599 LEXINGTON AVENUE LLC | 9 | 03/22/2026 |
| GANNON CONTRACTING | 1 | 03/22/2026 |
| CF LEX ASSOC. | 1 | 03/22/2026 |
| EUROPA OF 53RD STREET INC | 2 | 03/22/2026 |
| EUROPE OF 53 RD ST INC | 1 | 03/22/2026 |
| OWNER:140 W 53 ST | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| STUDIOS ARCHITECTURE | 3 | 08/06/2026 |
| AMA CONSULTING ENGINEERS, PC | 34 | 05/29/2026 |
| TPG ARCHITECTURE, LLP | 8 | 05/15/2026 |
| ROBERT DERECTOR ASSOCIATES | 3 | 04/08/2026 |
| NELSON ARCHITECTURE &INTERIORS, INC | 4 | 03/20/2026 |
| GENSLER | 2 | 02/19/2026 |
| JAROS BAUM & BOLLES | 18 | 02/13/2026 |
| JOHN MIN | 1 | 12/08/2025 |
| ASD/SKY | 1 | 11/17/2025 |
| FISKAA ENGINEERING | 11 | 11/13/2025 |
| ROBERT FINGER | 1 | 11/11/2025 |
| ARCHITECTURE PLUS INFORMATION | 3 | 10/23/2025 |
| SYSKA HENNESSY GROUP | 14 | 09/24/2025 |
| GILSANZ MURRAY STEFICEK LLP | 1 | 08/29/2025 |
| THORNTON TOMASETTI | 13 | 05/22/2025 |
| JOHN F. GIUSEFFI, ARCHITECT, PC | 2 | 04/14/2025 |
| INTERIOR ARCHITECTS | 2 | 04/11/2025 |
| JACOB FEINBERG KATZ & MICHAELI CONS | 29 | 04/08/2025 |
| AKF ENGINEERS, LLP | 11 | 03/18/2025 |
| TREAD A&D LLC | 2 | 08/09/2024 |
| THE SWITZER GROUP | 5 | 03/28/2024 |
| WILLIAM GRAHAM RICE | 5 | 08/21/2023 |
| JONG HAE CHANG ARCHITECT | 1 | 01/04/2023 |
| MG ENGINEERING D.P.C. | 6 | 08/24/2022 |
| CFS ENGINEERING, DPC | 2 | 04/11/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| A1 EXPEDITING SERVICE CORP. | 306 | 03/21/2026 |
| CAESAR BUSTAMANTE, AIA | 4 | 03/21/2026 |
| GILLMAN CONSULTING | 4 | 03/21/2026 |
| CAESAR BUSTAMANTE AIA | 8 | 03/21/2026 |
| C PLUS DESIGN GROUP | 2 | 03/21/2026 |
| YOUN DESIGN CORP | 2 | 03/21/2026 |
| JP EXPEDITE | 4 | 03/21/2026 |
| RPO | 2 | 03/21/2026 |
| NY SIGNS COM | 2 | 03/21/2026 |
| LOUIS STRIAR | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| STRUCTURE TONE, LLC | General Contractor | 53 | 07/08/2026 |
| L&K PARTNERS, INC | General Contractor | 23 | 07/08/2026 |
| GANNON CONTRACTING LLC | General Contractor | 20 | 07/08/2026 |
| ABCO-PEERLESS SPRKLR CORP | Fire Protection | 16 | 07/08/2026 |
| JT MAGEN & COMPANY INC | General Contractor | 12 | 09/26/2026 |
| PAR PLUMBING CO., INC | Plumbing | 11 | 07/08/2026 |
| UNISPACE OF BOSTON LLC | General Contractor | 11 | 07/08/2026 |
| CLUNE CONSTRUCTION CO LP | General Contractor | 10 | 07/08/2026 |
| JAMES E FITZGERALD INC | General Contractor | 8 | 09/07/2026 |
| GEOFFREY A. LAGAS & ASSOC | Plumbing | 7 | 07/08/2026 |
| SOH PAR SPRINKLER LLC | Fire Protection | 7 | 07/08/2026 |
| PREFERRED MECHANICAL INC | Plumbing | 6 | 07/08/2026 |
| AEROK INC | General Contractor | 6 | 03/21/2026 |
| J. CAIAZZO PLBG & HTG CORP | Fire Protection | 5 | 07/08/2026 |
| KLEINKNECHT ELEC. CO.,INC | Electrical | 5 | 03/22/2026 |
| PREFERRED SPKLR AND MECH | Fire Protection | 5 | 07/08/2026 |
| SIRINA FIRE PROT CORP | Fire Protection | 5 | 07/08/2026 |
| J. CAIAZZO PLBG & HTG COR | Plumbing | 4 | 07/08/2026 |
| CUSTOM COMMERCIAL CONSTRUCTION | General Contractor | 4 | 07/08/2026 |
| LAWRENCE J. LEVINE | Fire Protection | 4 | 03/21/2026 |
| LUCIANO, ANTHONY | Electrical | 4 | 03/21/2026 |
| PAR FIRE PROTECTION LLC | Fire Protection | 4 | 07/08/2026 |
| ANTHONY LUCIANO | Electrical | 4 | 03/21/2026 |
| SIGNS CAD | Scaffold | 4 | 07/08/2026 |
| JVS RESTORATION INC | General Contractor | 3 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ENGINEERING BUILDING SERV | 7303 | 19 | 05/29/2026 |
| MILROSE CONSULTANTS LLC | 2003 | 19 | 04/08/2026 |
| SOCOTEC ENGINEERING | 4983 | 9 | 02/13/2026 |
| JKM ARCHITECTURE P.C. | 8906 | 1 | 12/08/2025 |
| KATZ ENGINEERING | 238 | 8 | 11/13/2025 |
| GILSANZ MURRAY STEFICEK | 240 | 1 | 08/29/2025 |
| CODEGREEN | 510 | 7 | 04/17/2025 |
| AK ENGINEERING PC | 678 | 7 | 04/11/2025 |
| ATLAS ATC ENGINEERING INC | 8011 | 27 | 02/14/2025 |
| ATLANTIC ENGINEERINGLABOR | 1381 | 67 | 01/30/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | JT MAGEN & COMPANY INC | 09/25/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | JT MAGEN & COMPANY INC | 09/25/2026 |
| DOB NOW | General Construction | Permit Issued | JT MAGEN & COMPANY INC | 09/25/2026 |
| DOB NOW | General Construction | Permit Issued | JT MAGEN & COMPANY INC | 09/25/2026 |
| DOB NOW | Structural | Permit Issued | JT MAGEN & COMPANY INC | 09/25/2026 |
| DOB NOW | General Construction | Permit Issued | JAMES E FITZGERALD INC | 09/03/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | JAMES E FITZGERALD INC | 06/11/2026 |
| DOB NOW | Sprinklers | Permit Issued | CAPITOL FIRE SPRINKLER CO | 06/01/2026 |
| DOB NOW | Plumbing | Permit Issued | A&A PLUMBING CORP | 05/27/2026 |
| DOB NOW | General Construction | Permit Issued | JAMES E FITZGERALD INC | 05/20/2026 |
| DOB NOW | Sprinklers | Permit Issued | PAR PLUMBING CO., INC | 04/21/2026 |
| DOB NOW | Mechanical Systems | Signed-off | STRUCTURE TONE, LLC | 04/13/2026 |
| DOB NOW | Sprinklers | Permit Issued | ABCO-PEERLESS SPRKLR CORP | 04/13/2026 |
| DOB NOW | Plumbing | Permit Issued | PAR PLUMBING CO., INC | 04/10/2026 |
| DOB NOW | Sprinklers | Signed-off | BEDROCK MECHANICAL INC | 04/09/2026 |
| DOB NOW | Plumbing | Signed-off | BEDROCK PLBG. & HTG., INC | 04/07/2026 |
| DOB NOW | General Construction | Signed-off | STRUCTURE TONE, LLC | 03/31/2026 |
| DOB NOW | Mechanical Systems | Signed-off | STRUCTURE TONE, LLC | 03/30/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | STRUCTURE TONE, LLC | 03/27/2026 |
| DOB NOW | General Construction | Permit Issued | STRUCTURE TONE, LLC | 03/27/2026 |
| DOB NOW | General Construction | Signed-off | STRUCTURE TONE, LLC | 03/25/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | JT MAGEN & COMPANY INC | 03/18/2026 |
| DOB NOW | General Construction | Permit Issued | JT MAGEN & COMPANY INC | 03/18/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | L&K PARTNERS, INC | 03/11/2026 |
| DOB NOW | General Construction | Permit Issued | L&K PARTNERS, INC | 03/10/2026 |
| DOB NOW | Plumbing | Permit Issued | PAR PLUMBING CO., INC | 01/23/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | C PLUS DESIGN GROUP INC | 12/11/2025 |
| DOB NOW | Plumbing | Signed-off | SOH PAR SPRINKLER LLC | 12/11/2025 |
| DOB NOW | Sprinklers | Permit Issued | ASHLAND PLUMBING CORP | 11/24/2025 |
| DOB NOW | General Construction | Signed-off | COYLE CONTRACTING CORP | 11/21/2025 |
| DOB NOW | Sprinklers | Permit Issued | ABCO-PEERLESS SPRKLR CORP | 11/19/2025 |
| DOB NOW | Standpipe | Permit Issued | ABCO-PEERLESS SPRKLR CORP | 11/19/2025 |
| DOB NOW | General Construction | Signed-off | STRUCTURE TONE, LLC | 11/14/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | JT MAGEN & COMPANY INC | 10/29/2025 |
| DOB NOW | General Construction | Permit Issued | JT MAGEN & COMPANY INC | 10/27/2025 |
| DOB NOW | Structural | Permit Issued | JT MAGEN & COMPANY INC | 09/04/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | JT MAGEN & COMPANY INC | 09/03/2025 |
| DOB NOW | General Construction | Permit Issued | JT MAGEN & COMPANY INC | 09/03/2025 |
| DOB NOW | Sprinklers | Signed-off | PAR PLUMBING CO., INC | 08/05/2025 |
| DOB NOW | Plumbing | Signed-off | LAWRENCE J. LEVINE | 08/05/2025 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 05/29/2026 | Permit Issued | JAMES E FITZGERALD INC | Air Conditioning Systems | Cooling Climatemaster SC-018 17,800 BTU · Wshp ×1 |
| 04/08/2026 | Signed-off | STRUCTURE TONE, LLC | Air Conditioning Systems | Cooling Florida Heat Pump CL036 3 tons · Wshp ×1 |
| 10/24/2025 | Permit Issued | JT MAGEN & COMPANY INC | Air Conditioning Systems | — |
| 04/17/2025 | Permit Issued | STRUCTURE TONE, LLC | Air Conditioning Systems | Cooling Mammoth VVW-433-GXM 15,000 CFM ×5 |
| 04/08/2025 | Permit Issued | L&K PARTNERS, INC | Air Conditioning Systems | Cooling Climatemaster SC-024 2 tons · Wshp ×2 Vertiv PX011UG 3 tons · Wshp ×2 |
| 04/15/2024 | Permit Issued | CLUNE CONSTRUCTION CO LP | Air Conditioning Systems | |
| 03/26/2024 | Permit Issued | GANNON CONTRACTING LLC | Air Conditioning Systems | Cooling |
| 05/09/2023 | Permit Issued | GANNON CONTRACTING LLC | Air Conditioning Systems | Cooling Mammoth VVW-604-GXM 785,000 BTU · Wshp ×2 |
| 06/23/2022 | Permit Issued | L&K PARTNERS, INC | Air Conditioning Systems | Cooling Daikin WGTV0381 38 BTU · Wshp ×6 |
| 06/18/2021 | Permit Issued | ALCHEMY DEVELOPMENT | Air Conditioning Systems, Ventilation Systems | Cooling Ventilation Loren Cook 100SQN17DEC 580 CFM · Exhaust Fan ×1 |
| 10/01/2020 | Permit Issued | L&K PARTNERS, INC | Air Conditioning Systems | Cooling |
| 08/08/2019 | Permit Issued | HUDSON BLACK INC | Air Conditioning Systems | Cooling Daikin RXYQ192TTJU 192,000 BTU · Vrf Outdoor ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/29/2026 | Permit Issued | CAPITOL FIRE SPRINKLER CO | Sprinkler System |
| 04/08/2026 | Permit Issued | ABCO-PEERLESS SPRKLR CORP | 74 heads |
| 03/25/2026 | Signed-off | BEDROCK MECHANICAL INC | Sprinkler System |
| 02/13/2026 | Permit Issued | ABCO-PEERLESS SPRKLR CORP | 759 heads |
| 12/17/2025 | Signed-off | PAR FIRE PROTECTION LLC | 194 heads |
| 11/17/2025 | Signed-off | PAR FIRE PROTECTION LLC | 16 heads |
| 11/13/2025 | Permit Issued | J. CAIAZZO PLBG & HTG COR | 81 heads |
| 11/03/2025 | Permit Issued | ABCO-PEERLESS SPRKLR CORP | 1 outlets |
| 10/03/2025 | Signed-off | SOH PAR SPRINKLER LLC | 336 heads |
| 04/04/2025 | Signed-off | PREFERRED SPKLR AND MECH | — |
| 04/04/2025 | Permit Issued | PREFERRED SPKLR AND MECH | — |
| 04/04/2025 | Permit Issued | PREFERRED SPKLR AND MECH | 249 heads |
| 05/31/2023 | Permit Issued | PAR FIRE PROTECTION LLC | — |
| 05/16/2023 | Signed-off | ABCO-PEERLESS SPRKLR CORP | 547 heads |
| 05/09/2023 | Signed-off | ABCO-PEERLESS SPRKLR CORP | 1,185 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/29/2026 | Permit Issued | A&A PLUMBING CORP | Water/Sanitary |
| 04/08/2026 | Permit Issued | PAR PLUMBING CO., INC | Water/Sanitary |
| 03/25/2026 | Signed-off | BEDROCK PLUMBING & HEATING INC | Water/Sanitary |
| 02/13/2026 | Permit Issued | PAR PLUMBING CO., INC | Water/Sanitary |
| 12/17/2025 | Signed-off | PAR PLUMBING CO., INC | Water/Sanitary |
| 11/17/2025 | Signed-off | PAR PLUMBING CO., INC | Water/Sanitary |
| 11/13/2025 | Permit Issued | J. CAIAZZO PLBG & HTG COR | Water/Sanitary |
| 11/03/2025 | — | — | — |
| 10/03/2025 | Signed-off | GEOFFREY A. LAGAS & ASSOC | Water/Sanitary |
| 04/04/2025 | Permit Issued | PAR PLUMBING CO., INC | Water/Sanitary |
| 04/04/2025 | Signed-off | PAR PLUMBING CO., INC | Water/Sanitary |
| 05/31/2023 | Permit Issued | GEOFFREY A. LAGAS & ASSOC | Water/Sanitary |
| 05/16/2023 | Permit Issued | PAR PLUMBING CO., INC | Water/Sanitary |
| 05/09/2023 | Signed-off | PAR PLUMBING CO., INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/02/2026 | Complete | KLEINKNECHT ELEC. CO.,INC | 1 meters, 1 new_meters |
| 08/07/2026 | Permit Issued | STRAND ELECTRIC CO., INC. | 1 meters, 1 new_meters |
| 07/17/2026 | Permit Issued | W 8 ELECTRIC CORP | General Wiring |
| 06/03/2026 | Permit Issued | STRAND ELECTRIC CO., INC. | General Wiring |
| 04/14/2026 | Permit Issued | ATLAS-ACON ELEC. SERVICE | General Wiring |
| 04/07/2026 | Complete | STRAND ELECTRIC CO., INC. | — |
| 03/31/2026 | Permit Issued | STRAND ELECTRIC CO., INC. | General Wiring |
| 03/26/2026 | Permit Issued | ADCO ELEC'L CORP | General Wiring |
| 12/09/2025 | Complete | PIERPONT ELECTRICAL LLC | General Wiring |
| 10/27/2025 | Complete | KLEINKNECHT ELEC. CO.,INC | General Wiring |
| 10/27/2025 | Permit Issued | KLEINKNECHT ELEC. CO.,INC | General Wiring |
| 10/01/2025 | Permit Issued | KLEINKNECHT ELEC. CO.,INC | General Wiring |
| 09/18/2025 | Permit Issued | FIVE BOROUGH ELECTRIC INC | 1 meters |
| 07/23/2025 | Complete | STRAND ELECTRIC CO., INC. | General Wiring |
| 06/17/2025 | Complete | ADCO ELEC'L CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/29/2025 | Permit Issued | JT MAGEN & COMPANY INC | Steel, Concrete |
| 08/10/2021 | — | — | Steel, Concrete |
| 07/07/2020 | — | — | Concrete |
| 05/08/2020 | — | — | Steel |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/03/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/08/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/24/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/18/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/15/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/15/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/01/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/28/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/27/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/12/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/08/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/08/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/17/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/09/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/02/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/27/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 02/27/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/06/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 02/03/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 02/03/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 01/15/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/08/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 01/08/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/23/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/10/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/07/2026 | Final | Graham Clegg | progress |
| 05/20/2026 | Final | Graham Clegg | progress |
| 05/11/2026 | Post-installed Anchors | Tony Cartagine | special |
| 05/11/2026 | HVAC-R and service water piping design and insulation | Tony Cartagine | energy_progress |
| 05/11/2026 | Energy Code Compliance Inspections | Tony Cartagine | progress |
| 05/11/2026 | Duct leakage testing, insulation and design | Tony Cartagine | energy_progress |
| 05/11/2026 | Mechanical Systems | Tony Cartagine | special |
| 05/11/2026 | Sprinkler Systems | Tony Cartagine | special |
| 05/11/2026 | Lighting controls | Tony Cartagine | energy_progress |
| 05/11/2026 | HVAC-R and service water heating system controls | Tony Cartagine | energy_progress |
| 05/11/2026 | Maintenance information | Tony Cartagine | energy_progress |
| 05/11/2026 | HVAC-R and service water heating equipment | Tony Cartagine | energy_progress |
| 05/11/2026 | Final | Tony Cartagine | progress |
| 05/11/2026 | Interior lighting power | Tony Cartagine | energy_progress |
| 05/11/2026 | Fire-Resistant Penetrations and Joints | Tony Cartagine | special |
| 04/08/2026 | Energy Code Compliance Inspections | Christopher Drutjons | progress |
| 04/08/2026 | Interior lighting power | Christopher Drutjons | energy_progress |
| 03/05/2026 | Mechanical Systems | Christopher Drutjons | special |
| 03/05/2026 | HVAC-R and service water heating system controls | Christopher Drutjons | energy_progress |
| 03/05/2026 | HVAC-R and service water piping design and insulation | Christopher Drutjons | energy_progress |
| 03/05/2026 | HVAC-R and service water heating equipment | Christopher Drutjons | energy_progress |
| 03/05/2026 | Duct leakage testing, insulation and design | Christopher Drutjons | energy_progress |
| 03/05/2026 | Maintenance information | Christopher Drutjons | energy_progress |
| 03/05/2026 | Post-installed Anchors | Christopher Drutjons | special |
| 03/05/2026 | Final | Christopher Drutjons | progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| WCAS | Office | Floor 17 | Project M01367988 Project M01368012 Project M01367343 |
| Reed Smith | Office | Floor 22 | Project M01348859 Project M01348864 |
| Millennium | Office | Floors 19–21 | Project M01276383 Project M01263789 Project M01213917 |
| Cornerstone Research | Office | Floors 39–43 | Project M01179305 Project M01179315 Project M01179341 Project M01179332 Project M01179355 Project M01184057 Project M01184096 Project M00690021 |
| Evercore | Office | Floor 13 | Project M01083616 Project M01083622 |
| Bank Itau | Office | Floor 34 | Project M01051970 Project M01054302 |
| Café Joyeux USA | Restaurant / Food Service | Floor 1 | Project M00843008 Project M00842913 |
| Welsh, Carson, Anderson & Stowe | Office | Floors 17, 18 | Project M00797467 Project M00797494 Project M00637185 Project M00637141 Project M00341093 |
| Shearman & Sterling | Office | Sub-cellar, Floors 2–12 | Project M00562271 Project M00541424 Project M00559588 Project M00545381 Project M00452269 Project M00409215 Project M00389551 Project M00389580 Project M00341682 |
| Sugar Fish | Restaurant / Food Service | Floor 1 | Project M00338812 Project M00343281 |
| Sweetgreen | Restaurant / Food Service | Cellar, Floor 1 | Project M00334522 Project M00334559 |
| Fields Good Chicken | Restaurant / Food Service | Floor 1, Mezzanine | Project M00230521 Project M00205418 |
| Amazon Go | Retail | Floors 1–5 | Project M00187859 |