| Owner | Filings | Most Recent |
|---|---|---|
| Brickstone Group | 9 | 07/08/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/28/2026 | $2.4M | — | 599 VAN BUREN LLC → Private party | $1,073/sf building |
| 05/15/2025 | $880K | — | EST & LWT OF MARY HUTCHINSON DOD 10/31/2017 → 599 VAN BUREN LLC | $394/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| Peter Cho Architects | 7 | 05/05/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| WM Arch | 10 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Morell Builders | General Contractor | 4 | 07/08/2026 |
| Plumbing P & H | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| D&E Build Evergreen I | 9342 | 6 | 05/05/2026 |
| NKM Engineering | 6244 | 1 | 06/17/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | Plumbing P & H | 06/26/2025 |
| DOB NOW | Structural | Signed-off | Morell Builders | 06/25/2025 |
| DOB NOW | General Construction | Signed-off | Morell Builders | 06/24/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/05/2026 | Signed-off | Plumbing P & H | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/06/2026 | Complete | Apex Electric | General Wiring |
| 07/09/2025 | Complete | Flow State Electric | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/05/2026 | Signed-off | Plumbing P & H | Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/13/2026 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 02/02/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/20/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 08/20/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/20/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 08/17/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/06/2026 | Fenestration areas | Danny Chen | energy_progress |
| 05/06/2026 | Structural Stability – Alterations of existing buildings | NARESH MAHANGU | special |
| 05/06/2026 | Energy Code Compliance Inspections | Danny Chen | progress |
| 05/06/2026 | Fire-Resistance Rated Construction | Danny Chen | progress |
| 05/06/2026 | HVAC-R and service water heating equipment | Danny Chen | energy_progress |
| 05/06/2026 | Air barrier — testing | Danny Chen | energy_progress |
| 05/06/2026 | Metering | Danny Chen | energy_progress |
| 05/06/2026 | Insulation placement and R values | Danny Chen | energy_progress |
| 05/06/2026 | Fenestration and door U-factor and product ratings | Danny Chen | energy_progress |
| 05/06/2026 | HVAC-R and service water piping design and insulation | Danny Chen | energy_progress |
| 05/06/2026 | HVAC-R and service water heating system controls | Danny Chen | energy_progress |
| 05/06/2026 | Maintenance information | Danny Chen | energy_progress |
| 05/06/2026 | Fire-Resistant Penetrations and Joints | Danny Chen | special |
| 05/06/2026 | Interior lighting power | Danny Chen | energy_progress |
| 05/06/2026 | Fenestration air leakage | Danny Chen | energy_progress |
| 05/04/2026 | Fire-Resistant Penetrations and Joints | Danny Chen | special |
| 05/04/2026 | Structural Stability – Alterations of existing buildings | — | special |
| 05/04/2026 | Energy Code Compliance Inspections | Danny Chen | progress |
| 05/04/2026 | Fire-Resistance Rated Construction | Danny Chen | progress |
| 05/04/2026 | HVAC-R and service water piping design and insulation | Danny Chen | energy_progress |
| 05/04/2026 | Air barrier — testing | Danny Chen | energy_progress |
| 05/04/2026 | Maintenance information | Danny Chen | energy_progress |
| 05/04/2026 | Fenestration and door U-factor and product ratings | Danny Chen | energy_progress |
| 05/04/2026 | Metering | Danny Chen | energy_progress |
| 05/04/2026 | Interior lighting power | Danny Chen | energy_progress |