Two family converted from one family
599A MACON STREET
BROOKLYN · BIN 3046600
💬 Discuss this project
1899Year Built
2Stories
B3Building Class
R6BZoning
2,576 sfGross Floor Area
2Units
Two family converted from one family · 2,000 sf lot · 1.29 FAR built · Flood zone X
Locations of Work
General
Roof1p · 1 filing · 9 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TOM PETERSEN ARCHITECT, LLC108/18/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SOLAR CONTRACTING LLCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
THOMAS PETERSEN ARCHITECT7854108/18/2025
Building Lifecycle
All (8)Filed (1)Permit Issued (1)Signed Off (1)Special Inspection (5)
07/31/2026
Signed off — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONIC GENERATING SYSTEM.ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEING APPROVED AND/OR PERMITTED BY THENYC DEPARTMENT OF BUILDINGS.*NO CHANGE TO USE, EGRESS OR OCCUPANCY.*
B01270327-I1
10/09/2025
Permit issued — Solar
B01270327-I1-SL
08/18/2025
Filed — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONIC GENERATING SYSTEM.ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEING APPROVED AND/OR PERMITTED BY THENYC DEPARTMENT OF BUILDINGS.*NO CHANGE TO USE, EGRESS OR OCCUPANCY.*
B01270327-I1
08/12/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
TOM PETERSEN
08/12/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
TOM PETERSEN
08/12/2025
Special inspection requirement — Energy Code Compliance Inspections
TOM PETERSEN
08/12/2025
Special inspection requirement — Final
TOM PETERSEN
08/12/2025
Special inspection requirement — Air barrier - visual inspection
TOM PETERSEN
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSOLAR CONTRACTING LLC10/09/2025
3 projects · most recent 05/06/2026
General Wiring
FiledStatusContractorScope
05/06/2026CompleteVILLAGE ELECTL CONTRS INC—
03/30/2026CompleteVILLAGE ELECTL CONTRS INCGeneral Wiring
01/09/2025CompleteSTRONG ISLAND ELEC. LLC—
1 project · most recent 08/18/2025
FiledStatusContractorScope
08/18/2025Signed-offSOLAR CONTRACTING LLC7 panels, 3.01 kw, 147.13 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
08/12/2025Fire-Resistant Penetrations and JointsTOM PETERSENspecial
08/12/2025Structural Stability – Alterations of existing buildingsTOM PETERSENspecial
08/12/2025Energy Code Compliance InspectionsTOM PETERSENprogress
08/12/2025FinalTOM PETERSENprogress
08/12/2025Air barrier - visual inspectionTOM PETERSENenergy_progress
▾Documents — 9 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/20/2026B01270327-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
08/24/2026B01270327-I1Open ↗
08/24/2026B01270327-I1Open ↗
08/24/2026B01270327-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/24/2026B01270327-I1Open ↗
08/24/2026B01270327-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026B01270327-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026B01270327-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/20/2026B01270327-I1Open ↗