← Back
BuildNYC
Two stories - detached, small or mid-size
6-01 ELVIRA AVENUE
QUEENS · BIN 4298532
💬 Discuss this project
1960Year Built
1Stories
A1Building Class
R2XZoning
7,754 sfGross Floor Area
1Units
0 Active ViolationsFDNY Report ↗
Two stories - detached, small or mid-size · 11,357 sf lot · 0.68 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionLandscapeCivilGeneralOther
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
Roof2p · 2 filings · 20 docs
AtticUnder Construction8p · 2 filings · 20 docs
Floor 36p · 1 filing · 20 docs
Floor 2Under Construction14p · 2 filings · 20 docs
Floor 1Under Construction15p · 3 filings · 20 docs
CellarUnder Construction20p · 2 filings · 20 docs
Site & exterior56p · 1 filing · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
05/30/2023$2.0M—Private party → Private party$258/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Shmuel D. Flaum, Architect809/14/2026
NY Building Associates102/19/2026
Engineering Professional Service P102/15/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
S R Solar Design203/21/2026
MEP Designs203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
All-Boro Rehab ConstrctScaffold304/09/2026
All-Boro Rehab ConstrctGeneral Contractor204/09/2026
All-Boro Rehab ConstructionPlumbing209/17/2026
Moehlenhoff Plumbing & HeatingPlumbing103/21/2026
J Synergy Greenspecialty_contractor104/09/2026
Safety Fire SprinklerFire Protection109/16/2026
Joseph Moehlenhoff P&HPlumbing108/25/2011
Michael Arciere ContractingGeneral Contractor109/10/2003
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
David Katz, P.E.6087709/14/2026
Shmuel D. Flaum4278307/29/2026
NKM Engineering6244102/19/2026
Building Lifecycle
11/11/2026
Signed off — ALT-CO - New Building with Existing Elements to Remain
PROPOSED ALTERATION OF CELLAR AND 1ST FLOOR. NEW SECOND FLOOR AND ATTIC.
Q00959096-S2
10/15/2026
Objection raised — Other
10/14/2026
Objection raised — Other
10/14/2026
Objection resolved — Addressed
10/08/2026
Objection raised — Other
114 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedAll-Boro Rehab Construction09/16/2026
DOB NOWSprinklersPermit IssuedSafety Fire Sprinkler09/15/2026
DOB NOWSolarPermit IssuedJ Synergy Green03/09/2026
DOB NOWPlumbingPermit IssuedAll-Boro Rehab Construction09/03/2025
DOB NOWConstruction FenceSigned-offAll-Boro Rehab Constrct01/23/2025
DOB NOWFoundationPermit IssuedAll-Boro Rehab Constrct01/23/2025
DOB NOWEarth WorkPermit IssuedAll-Boro Rehab Constrct08/07/2024
DOB NOWConstruction FenceSigned-offAll-Boro Rehab Constrct03/15/2024
BISPLISSUEDJoseph Moehlenhoff P&H08/25/2011
BISPLISSUEDJoseph Moehlenhoff P&H02/11/2004
BIS—ISSUEDMichael Arciere Contracting09/10/2003
1 project · most recent 09/14/2026
Heating and Air Conditioning Systems
FiledStatusContractorScope
09/14/2026Permit IssuedAll-Boro Rehab ConstrctHeating and Air Conditioning Systems
1 project · most recent 09/14/2026
Gas Storm Water/Sanitary
FiledStatusContractorScope
09/14/2026Permit IssuedAll-Boro Rehab ConstructionGas, Storm, Water/Sanitary
2 projects · most recent 01/29/2026
General Wiring
FiledStatusContractorScope
01/29/2026Permit IssuedGreen Light Electrical & Mechanical—
07/17/2025Permit IssuedHirschel ElectricalGeneral Wiring
1 project · most recent 09/14/2026
Concrete Masonry
FiledStatusContractorScope
09/14/2026Permit IssuedAll-Boro Rehab ConstructionConcrete, Masonry
1 project · most recent 09/14/2026
Fence
FiledStatusContractorScope
09/14/2026Permit IssuedAll-Boro Rehab ConstructionFence
▾Field Inspections (DOB CAP) — 4
DateTypeResultReport
09/16/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
11/20/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
11/20/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/10/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 85
DateRequirementInspectorRole
09/09/2026Maintenance informationDavid Katzenergy_progress
09/09/2026Fire-Resistant Penetrations and JointsDavid Katzspecial
09/09/2026Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationDavid Katzspecial
09/09/2026Energy Code Compliance InspectionsDavid Katzprogress
09/09/2026HVAC-R and service water heating system controlsDavid Katzenergy_progress
09/09/2026HVAC-R and service water heating equipmentDavid Katzenergy_progress
09/09/2026HVAC-R and service water piping design and insulationDavid Katzenergy_progress
08/26/2026HVAC-R and service water heating equipmentDavid Katzenergy_progress
08/26/2026Maintenance informationDavid Katzenergy_progress
08/26/2026Energy Code Compliance InspectionsDavid Katzprogress
08/26/2026Fire-Resistant Penetrations and JointsDavid Katzspecial
08/26/2026Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationDavid Katzspecial
08/26/2026HVAC-R and service water heating system controlsDavid Katzenergy_progress
08/26/2026HVAC-R and service water piping design and insulationDavid Katzenergy_progress
06/30/2026Fire-Resistant Penetrations and JointsDavid Katzspecial
06/30/2026Maintenance informationDavid Katzenergy_progress
06/30/2026HVAC-R and service water piping design and insulationDavid Katzenergy_progress
06/30/2026HVAC-R and service water heating system controlsDavid Katzenergy_progress
06/30/2026Energy Code Compliance InspectionsDavid Katzprogress
06/30/2026Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationDavid Katzspecial
06/30/2026HVAC-R and service water heating equipmentDavid Katzenergy_progress
02/11/2026Fire-Resistant Penetrations and JointsNARESH MAHANGUspecial
02/11/2026Structural Stability – Alterations of existing buildingsNARESH MAHANGUspecial
02/11/2026Energy Code Compliance InspectionsNARESH MAHANGUprogress
02/11/2026FinalNARESH MAHANGUprogress
Latest 25 of 85.
65 filed documents on file for this building. Sign in free to see the full history. Sign in · Create account